PDPASA - Update of the Forecast Lack Of Reserve Level 1 (LOR1) in the SA Region on 03/02/2025
The Forecast LOR1 condition in the SA region advised in AEMO Electricity Market Notice No. 124026 has been updated at 0445 hrs 03/02/2025 to the following:
[1.] From 1800 hrs 03/02/2025 to 1830 hrs 03/02/2025.
The forecast capacity reserve requirement is 598 MW.
The minimum capacity reserve available is 419 MW.
[2.] From 1930 hrs 03/02/2025 to 2030 hrs 03/02/2025.
The forecast capacity reserve requirement is 617 MW.
The minimum capacity reserve available is 380 MW.
Manager NEM Real Time Operations
PDPASA - Forecast Lack Of Reserve Level 1 (LOR1) in the SA Region on 03/02/2025
AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the SA region for the following Period:
[1.] From 1800 hrs 03/02/2025 to 2000 hrs 03/02/2025.
The forecast capacity reserve requirement is 630 MW.
The minimum capacity reserve available is 384 MW.
Manager NEM Real Time Operations
PDPASA - Forecast Lack Of Reserve Level 1 (LOR1) in the VIC Region on 03/02/2025
AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the VIC region for the following Period:
[1.] From 1800 hrs 03/02/2025 to 1930 hrs 03/02/2025.
The forecast capacity reserve requirement is 1135 MW.
The minimum capacity reserve available is 999 MW.
Manager NEM Real Time Operations
Update - Inter-regional transfer limit variation - Ararat to Waubra to Ballarat 220 kV line - VIC region - 02/02/2025
Inter-regional transfer limit variation - Ararat to Waubra to Ballarat 220 kV line - VIC region - 02/02/2025
At 2138 hrs 02/02/2025 there was an unplanned outage of Ararat to Waubra to Ballarat 220 kV line.
The following constraint set(s) invoked at 2150 hrs 02/02/2025
V-AR_WB_BA
The following constraint set(s) invoked at 2230 hrs 02/02/2025
V-KIAMAL_SC_220CB
This constraint set(s) contains equations with the following interconnectors on the LHS.
V-S-MNSP1,T-V-MNSP1,V-SA,VIC1-NSW1
Refer to the AEMO Network Outage Scheduler for further information.
Manager NEM Real Time Operations
Inter-regional transfer limit variation - Ararat to Waubra to Ballarat 220 kV line - VIC region - 02/02/2025
Inter-regional transfer limit variation - Ararat to Waubra to Ballarat 220 kV line - VIC region - 02/02/2025
At 2138 hrs 02/02/2025 there was an unplanned outage of Ararat to Waubra to Ballarat 220 kV line.
The following constraint set(s) invoked at 2150 hrs 02/02/2025
V-AR_WB_BA
This constraint set(s) contains equations with the following interconnectors on the LHS.
V-S-MNSP1,T-V-MNSP1,V-SA,VIC1-NSW1
Refer to the AEMO Network Outage Scheduler for further information.
Manager NEM Real Time Operations
STPASA - Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 07/02/2025
AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the NSW region for the following period[s]:
[1.] From 1600 hrs 07/02/2025 to 1800 hrs 07/02/2025.
The forecast capacity reserve requirement is 1400 MW.
The minimum capacity reserve available is 1160 MW.
Manager NEM Real Time Operations
Cancellation - AEMO Intervention Event - SA region 01/02/2025
Cancellation - AEMO Intervention Event - SA region 01/02/2025
Refer to Market Notice 123988
The AEMO Intervention Event and all associated directions are cancelled from 0900 hrs on 02/02/2025.
Manager NEM Real Time Operations
Cancellation: Direction issued to: Pelican Point Power Limited - PPCCGT PELICAN POINT
Cancellation: Direction issued to: Pelican Point Power Limited - PPCCGT PELICAN POINT
Refer to Market Notice 123989
Direction is cancelled from: 0900 hrs 02/02/2025
Manager NEM Real Time Operations
[EventId:202502011830_NRM_VIC1_SA1_stopped] NEGRES CONSTRAINT NRM_VIC1_SA1 ceased operating from 01 February 2025 18:30
Issued by Australian Energy Market Operator Ltd at 1830 hrs on 1 February 2025
CANCELLATION - ACTUAL NEGATIVE SETTLEMENT RESIDUES - VIC to SA - 1 February 2025.
Refer to market notice: 123990
AEMO has ceased taking action to minimize the further accumulation of negative settlement residues on the VIC to SA directional interconnector.
The negative residue constraint NRM_VIC1_SA1 ceased operating at 1830 hrs on 1 February 2025.
This is an AEMO autogenerated Market Notice.