Market Notices

120411NON-CONFORMANCE14/11/2024 08:10:16 AM

NON-CONFORMANCE Region QLD1 Thursday, 14 November 2024

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE QLD1 Region Thursday, 14 November 2024

AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:

Unit: MPP_1
Duration: 14/11/2024 08:05 to 14/11/2024 08:10
Amount: -47 MW
Constraint: NC-Q_MPP_1

Auto-generated on behalf of Manager NEM Real Time Operations
     
120400SETTLEMENTS RESIDUE13/11/2024 09:05:43 PM

[EventId:202411132105_NRM_NSW1_VIC1_stopped] NEGRES CONSTRAINT NRM_NSW1_VIC1 ceased operating from 13 November 2024 21:05

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 2105 hrs on 13 November 2024

CANCELLATION - ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 13 November 2024.

Refer to market notice: 120397

AEMO has ceased taking action to minimize the further accumulation of negative settlement residues on the NSW to VIC directional interconnector.

The negative residue constraint NRM_NSW1_VIC1 ceased operating at 2105 hrs on 13 November 2024.

This is an AEMO autogenerated Market Notice.
     
120398NON-CONFORMANCE13/11/2024 08:45:15 PM

NON-CONFORMANCE Region VIC1 Wednesday, 13 November 2024

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE VIC1 Region Wednesday, 13 November 2024

AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:

Unit: GANNB1
Duration: 13/11/2024 20:35 to 13/11/2024 20:45
Amount: 10 MW
Constraint: NC-V_GANNB1

Auto-generated on behalf of Manager NEM Real Time Operations
     
120397SETTLEMENTS RESIDUE13/11/2024 07:07:57 PM

[EventId:202411131900_NRM_NSW1_VIC1_started] NEGRES CONSTRAINT NRM_NSW1_VIC1 started operating from 13 November 2024 19:00

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1900 hrs on 13 November 2024

ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 13 November 2024.

Electricity Market outcomes have resulted in the accumulation of negative settlement residues that have exceeded the allowable negative residue threshold for the NSW to VIC directional interconnector.

The negative residue constraint set NRM_NSW1_VIC1 commenced operating from 1900 hrs on 13 November 2024.

This constraint set contains an equation with the following interconnectors on the LHS:
VIC1-NSW1

The RHS of the constraint equation may be adjusted to manage residues.


This is an AEMO autogenerated Market Notice.
     
120385SETTLEMENTS RESIDUE13/11/2024 06:32:04 PM

[EventId:202411131830_NRM_NSW1_VIC1_stopped] NEGRES CONSTRAINT NRM_NSW1_VIC1 ceased operating from 13 November 2024 18:30

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1830 hrs on 13 November 2024

CANCELLATION - ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 13 November 2024.

Refer to market notice: 120367

AEMO has ceased taking action to minimize the further accumulation of negative settlement residues on the NSW to VIC directional interconnector.

The negative residue constraint NRM_NSW1_VIC1 ceased operating at 1830 hrs on 13 November 2024.

This is an AEMO autogenerated Market Notice.
     
120367SETTLEMENTS RESIDUE13/11/2024 03:21:51 PM

[EventId:202411131520_NRM_NSW1_VIC1_started] NEGRES CONSTRAINT NRM_NSW1_VIC1 started operating from 13 November 2024 15:20

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1520 hrs on 13 November 2024

ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 13 November 2024.

Electricity Market outcomes have resulted in the accumulation of negative settlement residues that have exceeded the allowable negative residue threshold for the NSW to VIC directional interconnector.

The negative residue constraint set NRM_NSW1_VIC1 commenced operating from 1520 hrs on 13 November 2024.

This constraint set contains an equation with the following interconnectors on the LHS:
VIC1-NSW1

The RHS of the constraint equation may be adjusted to manage residues.


This is an AEMO autogenerated Market Notice.
     
120341RESERVE NOTICE13/11/2024 11:27:41 AM

PDPASA - Cancellation of the Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region [beginning] on 13/11/2024

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR1 condition in the NSW region advised in AEMO Electricity Market Notice No. 120335 is cancelled at 1125 hrs 13/11/2024.

Manager NEM Real Time Operations
     
120335RESERVE NOTICE13/11/2024 07:47:24 AM

PDPASA - Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 13/11/2024

AEMO ELECTRICITY MARKET NOTICE

AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the NSW region for the following Period:

[1.] From 1800 hrs 13/11/2024 to 1900 hrs 13/11/2024.
The forecast capacity reserve requirement is 1430 MW.
The minimum capacity reserve available is 1372 MW.

Manager NEM Real Time Operations
     
120334NON-CONFORMANCE13/11/2024 02:50:19 AM

NON-CONFORMANCE Region QLD1 Wednesday, 13 November 2024

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE QLD1 Region Wednesday, 13 November 2024

AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:

Unit: MPP_2
Duration: 13/11/2024 02:10 to 13/11/2024 02:50
Amount: 39 MW
Constraint: NC-Q_MPP_2

Auto-generated on behalf of Manager NEM Real Time Operations
     
X
Cookies help us improve your website experience.
By using our website, you agree to our use of cookies.
Confirm