123698RECLASSIFY CONTINGENCY24/01/2025 10:54:40 PM

Cancellation of a Non-Credible Contingency Event: Tumoulin - Woree No.877 275 kV line and Chalumbin - Turkinje No.7166 132 kV line in QLD1 due to Lightning.

AEMO ELECTRICITY MARKET NOTICE

Cancellation of reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits is no longer reasonably possible. There is no longer any lightning activity in the vicinity of the following lines. Accordingly its classification has reverted to a non-credible contingency event.

Region: QLD1

Lines: Tumoulin - Woree No.877 275 kV and Chalumbin - Turkinje No.7166 132 kV

Cancellation time: 24/01/2025 22:54

Constraint set(s) revoked:
NONE

Refer AEMO Electricity Market Notice 123696

Auto-generated on behalf of Manager NEM Real Time Operations
     
123697RECLASSIFY CONTINGENCY24/01/2025 10:54:40 PM

Cancellation of a Non-Credible Contingency Event: Chalumbin - Turkinje No.7165 132 kV line and Chalumbin - Turkinje No.7166 132 kV line in QLD1 due to Lightning.

AEMO ELECTRICITY MARKET NOTICE

Cancellation of reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits is no longer reasonably possible. There is no longer any lightning activity in the vicinity of the following lines. Accordingly its classification has reverted to a non-credible contingency event.

Region: QLD1

Lines: Chalumbin - Turkinje No.7165 132 kV and Chalumbin - Turkinje No.7166 132 kV

Cancellation time: 24/01/2025 22:54

Constraint set(s) revoked:
NONE

Refer AEMO Electricity Market Notice 123695

Auto-generated on behalf of Manager NEM Real Time Operations
     
123696RECLASSIFY CONTINGENCY24/01/2025 09:50:05 PM

Reclassification of a Non-Credible Contingency Event: Tumoulin - Woree No.877 275 kV line and Chalumbin - Turkinje No.7166 132 kV line in QLD1 due to Lightning.

AEMO ELECTRICITY MARKET NOTICE

Reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits to now be more likely and reasonably possible. Accordingly AEMO has reclassified it as a credible contingency event.

Region: QLD1

Lines: Tumoulin - Woree No.877 275 kV and Chalumbin - Turkinje No.7166 132 kV

Duration: 24/01/2025 21:50 until further notice

Constraint set(s) invoked:
NONE

Auto-generated on behalf of Manager NEM Real Time Operations
     
123695RECLASSIFY CONTINGENCY24/01/2025 09:50:01 PM

Reclassification of a Non-Credible Contingency Event: Chalumbin - Turkinje No.7165 132 kV line and Chalumbin - Turkinje No.7166 132 kV line in QLD1 due to Lightning.

AEMO ELECTRICITY MARKET NOTICE

Reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits to now be more likely and reasonably possible. Accordingly AEMO has reclassified it as a credible contingency event.

Region: QLD1

Lines: Chalumbin - Turkinje No.7165 132 kV and Chalumbin - Turkinje No.7166 132 kV

Duration: 24/01/2025 21:49 until further notice

Constraint set(s) invoked:
NONE

Auto-generated on behalf of Manager NEM Real Time Operations
     
123692GENERAL NOTICE24/01/2025 05:50:25 PM

QNI Minor testing (NSW to Qld) 25th January 2025 for flows from NSW to Qld up to 850 MW

AEMO ELECTRICITY MARKET NOTICE

Refer to market notice 117923

There is an opportunity for testing QNI Minor for flows from NSW to Qld up to 850 MW on Saturday 25th January 2025 from 1330 to 1530hrs.

This test includes switching of transmission lines in New South Wales and/or Queensland regions.

Please also refer to the published formal QNI minor testing information at the following link:
https://www.aemo.com.au/consultations/current-and-closed-consultations/qld-to-nsw-interconnector-qni-upgrade

Ben Blake
AEMO Operations
     
123691MARKET INTERVENTION24/01/2025 05:29:53 PM

Cancellation: Direction issued to: Pelican Point Power Limited - PPCCGT PELICAN POINT

AEMO ELECTRICITY MARKET NOTICE

Cancellation: Direction issued to: Pelican Point Power Limited - PPCCGT PELICAN POINT

Refer to Market Notice 123623

Direction is cancelled from: 1730 hrs 24/01/2025

Manager NEM Real Time Operations
     
123676GENERAL NOTICE24/01/2025 04:27:11 PM

Project Energy Connect (PEC-1) testing 25th January 2025 0100-0300 for flows from Victoria to South Australia direction up to 150 MW

AEMO ELECTRICITY MARKET NOTICE

Refer to market notice 122115

There is an opportunity for testing Project Energy Connect (PEC-1) for flows from Victoria to South Australia direction up to 150 MW on 25th January from 01:00hrs to 03:00hrs

This test includes switching of transmission lines and reactive plant in South Australia and in New South Wales.

Please also refer to the published formal PEC Stage 1 and HIC capacity release testing information at the following link https://aemo.com.au/-/media/files/stakeholder_consultation/consultations/nem-consultations/2023/project-energyconnect-stage-1-and-hic-capacity-release/pec-stage-1-and-hic---final-test-program.pdf?la=en.

Ben Blake
AEMO Operations
     
123674MARKET INTERVENTION24/01/2025 04:00:17 PM

Direction - SA region to Pelican Point Power Limited - PPCCGT PELICAN POINT

AEMO ELECTRICITY MARKET NOTICE

Direction - SA region to Pelican Point Power Limited - PPCCGT PELICAN POINT

Refer to Market Notice 123506


In accordance with section 116 of the National Electricity Law, AEMO is issuing a direction to Pelican Point Power Limited. For the purposes of the National Electricity Rules this is a direction under clause 4.8.9(a1)(1).

Direction issued to: Pelican Point Power Limited - PPCCGT PELICAN POINT at 1600 hrs 24/01/2025
Type of resource: generating unit
Required actions: Remain synchronised and follow dispatch targets at 0800 hrs 25/01/2025
Services provided: Voltage Control
Circumstances necessitating the Direction:Voltage
Circumstances necessitating the Direction additional detail: intervention is required to maintain the power system in a secure operating state
Expected duration: 0400 hrs 26/01/2025.

Pelican Point Power Limited does not incur any civil monetary liability for a relevant action taken in accordance with this direction unless the action is taken in bad faith.

Manager NEM Real Time Operations
     
123672MARKET INTERVENTION24/01/2025 03:58:18 PM

Update Direction - AGL SA Generation Pty Limited - TORRB3 TORRENS ISLAN

AEMO ELECTRICITY MARKET NOTICE.

Update Direction - AGL SA Generation Pty Limited - TORRB3 TORRENS ISLAN

Refer to Market Notice 123624

TORRB3 TORRENS ISLAN at 0400 hrs 25/01/2025 to Remain synchronised and follow dispatch targets.

The TORRB3 TORRENS ISLAN direction is now expected to stay in place until 0400 hrs 26/01/2025.

The direction update is issued at 1600 hrs 24/01/2025.