[EventId:202502191200_confirmed] Prices for interval 19-Feb-2025 12:00 are now confirmed
Issued by Australian Energy Market Operator Ltd at 1220 hrs on 19 February 2025
PRICES ARE NOW CONFIRMED for trading interval 19-Feb-2025 12:00.
In accordance with Market Notice 124875 AEMO has reviewed this trading interval and determined that:
- Manifestly Incorrect Inputs did not apply
Prices remain unchanged.
This is an AEMO autogenerated Market Notice.
[EventId:202502191220_confirmed] Prices for interval 19-Feb-2025 12:20 are now confirmed
Issued by Australian Energy Market Operator Ltd at 1220 hrs on 19 February 2025
PRICES ARE NOW CONFIRMED for trading interval 19-Feb-2025 12:20.
In accordance with Market Notice 124881 AEMO has reviewed this trading interval and determined that:
- Manifestly Incorrect Inputs did not apply
Prices remain unchanged.
This is an AEMO autogenerated Market Notice.
[EventId:202502191215_confirmed] Prices for interval 19-Feb-2025 12:15 are now confirmed
Issued by Australian Energy Market Operator Ltd at 1220 hrs on 19 February 2025
PRICES ARE NOW CONFIRMED for trading interval 19-Feb-2025 12:15.
In accordance with Market Notice 124880 AEMO has reviewed this trading interval and determined that:
- Manifestly Incorrect Inputs did not apply
Prices remain unchanged.
This is an AEMO autogenerated Market Notice.
[EventId:202502191210_confirmed] Prices for interval 19-Feb-2025 12:10 are now confirmed
Issued by Australian Energy Market Operator Ltd at 1220 hrs on 19 February 2025
PRICES ARE NOW CONFIRMED for trading interval 19-Feb-2025 12:10.
In accordance with Market Notice 124878 AEMO has reviewed this trading interval and determined that:
- Manifestly Incorrect Inputs did not apply
Prices remain unchanged.
This is an AEMO autogenerated Market Notice.
[EventId:202502191205_confirmed] Prices for interval 19-Feb-2025 12:05 are now confirmed
Issued by Australian Energy Market Operator Ltd at 1220 hrs on 19 February 2025
PRICES ARE NOW CONFIRMED for trading interval 19-Feb-2025 12:05.
In accordance with Market Notice 124876 AEMO has reviewed this trading interval and determined that:
- Manifestly Incorrect Inputs did not apply
Prices remain unchanged.
This is an AEMO autogenerated Market Notice.
[EventId:202502191155_confirmed] Prices for interval 19-Feb-2025 11:55 are now confirmed
Issued by Australian Energy Market Operator Ltd at 1220 hrs on 19 February 2025
PRICES ARE NOW CONFIRMED for trading interval 19-Feb-2025 11:55.
In accordance with Market Notice 124874 AEMO has reviewed this trading interval and determined that:
- Manifestly Incorrect Inputs did not apply
Prices remain unchanged.
This is an AEMO autogenerated Market Notice.
NON-CONFORMANCE Region QLD1 Wednesday, 19 February 2025
NON-CONFORMANCE QLD1 Region Wednesday, 19 February 2025
AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:
Unit: MPP_2
Duration: 19/02/2025 11:55 to 19/02/2025 12:10
Amount: -18 MW
Constraint: NC-Q_MPP_2
Auto-generated on behalf of Manager NEM Real Time Operations
Inital - CHG0100546 - Production eMDM February Maintenance Release
Notification issued to: Market Notice
Notification Type: Initial
Change Type: Normal
Service/ Component: MDM - Meter Data Management
Change Title: Production eMDM February Maintenance Release
Change Start Date & Time: 23/02/2025 10:00:00
Change End Date & Time: 23/02/2025 17:00:00
Outage Start Date & Time: 23/02/2025 10:00:00
Outage End Date & Time: 23/02/2025 14:00:00
Environment: Production
Participant Impact and Requirements: Users will not be able to access MSATS during the outage period.
Meter data processing and RM reports will not be available during the outage period.
User Rights Management (URM) will continue to operate, however the administration screens will not be accessible.
MSATS B2B/B2M Transactions and B2B MSATS Screens will be unavailable during this outage
NMI Discovery will not be available during the outage period.
CDR and CDP will not be available during the outage period.
Support Information:
Report any impacts to the AEMO Information and Support Hub or call 1300 236 600.
Please refer to https://aemo.service-now.com/participantportal?id=pp_services_status for any planned/unplanned maintenance activities .
[EventId:202502191125_NRM_NSW1_VIC1_started] NEGRES CONSTRAINT NRM_NSW1_VIC1 started operating from 19 February 2025 11:25
Issued by Australian Energy Market Operator Ltd at 1125 hrs on 19 February 2025
ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 19 February 2025.
Electricity Market outcomes have resulted in the accumulation of negative settlement residues that have exceeded the allowable negative residue threshold for the NSW to VIC directional interconnector.
The negative residue constraint set NRM_NSW1_VIC1 commenced operating from 1125 hrs on 19 February 2025.
This constraint set contains an equation with the following interconnectors on the LHS:
VIC1-NSW1
The RHS of the constraint equation may be adjusted to manage residues.
This is an AEMO autogenerated Market Notice.