123815RECLASSIFY CONTINGENCY28/01/2025 04:30:15 PM

Reclassification of a Non-Credible Contingency Event: Bayswater - Mt Piper No.5A3 500kV line and Wollar - Mt Piper No.5A5 500kV line in NSW1 due to Lightning.

AEMO ELECTRICITY MARKET NOTICE

Reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits to now be more likely and reasonably possible. Accordingly AEMO has reclassified it as a credible contingency event.

Region: NSW1

Lines: Bayswater - Mt Piper No.5A3 500kV and Wollar - Mt Piper No.5A5 500kV

Duration: 28/01/2025 16:30 until further notice

Constraint set(s) invoked:
NONE

Auto-generated on behalf of Manager NEM Real Time Operations
     
123813RESERVE NOTICE28/01/2025 03:08:46 PM

STPASA - Forecast Lack Of Reserve Level 1 (LOR1) in the VIC Region on 03/02/2025

AEMO ELECTRICITY MARKET NOTICE

AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the VIC region for the following period:

From 1630 hrs to 1900 hrs 03/02/2025.
The forecast capacity reserve requirement is 1148 MW.
The minimum capacity reserve available is 977 MW.

AEMO Operations
     
123812MARKET INTERVENTION28/01/2025 02:15:53 PM

Update Direction - AGL SA Generation Pty Limited - TORRB2 TORRENS ISLAN

AEMO ELECTRICITY MARKET NOTICE.

Update Direction - AGL SA Generation Pty Limited - TORRB2 TORRENS ISLAN

Refer to Market Notice 123761

TORRB2 TORRENS ISLAN at 0030 hrs 27/01/2025 to Remain synchronised and follow dispatch targets.

The TORRB2 TORRENS ISLAN direction is now expected to stay in place until 0400 hrs 30/01/2025.

The direction update is issued at 1410 hrs 28/01/2025.

Manager NEM Real Time Operations
     
123811MARKET INTERVENTION28/01/2025 02:09:48 PM

Update Direction - Pelican Point Power Limited - PPCCGT PELICAN POINT

AEMO ELECTRICITY MARKET NOTICE.

Update Direction - Pelican Point Power Limited - PPCCGT PELICAN POINT

Refer to Market Notice 123762

PPCCGT PELICAN POINT at 0100 hrs 27/01/2025 to Remain synchronised and follow dispatch targets.

The PPCCGT PELICAN POINT direction is now expected to stay in place until 0400 hrs 30/01/2025.

The direction update is issued at 1410 hrs 28/01/2025.

Manager NEM Real Time Operations
     
123803RESERVE NOTICE28/01/2025 10:43:22 AM

PDPASA - Cancellation of the Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 28/01/2025

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR1 condition in the NSW region advised in AEMO Electricity Market Notice No. 123773 is cancelled at 1030 hrs 28/01/2025.

Manager NEM Real Time Operations
     
123801RECLASSIFY CONTINGENCY28/01/2025 12:14:40 AM

Cancellation of a Non-Credible Contingency Event: Eildon PS - Mt Beauty No.1 220 kV line and Eildon PS - Mt Beauty No.2 220 kV line in VIC1 due to Lightning.

AEMO ELECTRICITY MARKET NOTICE

Cancellation of reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits is no longer reasonably possible. There is no longer any lightning activity in the vicinity of the following lines. Accordingly its classification has reverted to a non-credible contingency event.

Region: VIC1

Lines: Eildon PS - Mt Beauty No.1 220 kV and Eildon PS - Mt Beauty No.2 220 kV

Cancellation time: 28/01/2025 00:14

Constraint set(s) revoked:
NONE

Refer AEMO Electricity Market Notice 123795

Auto-generated on behalf of Manager NEM Real Time Operations
     
123800RECLASSIFY CONTINGENCY27/01/2025 09:34:38 PM

Cancellation of a Non-Credible Contingency Event: Bannaby - Mt Piper 5A6 500kV line and Bannaby - Mt Piper 5A7 500kV line in NSW1 due to Lightning.

AEMO ELECTRICITY MARKET NOTICE

Cancellation of reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits is no longer reasonably possible. There is no longer any lightning activity in the vicinity of the following lines. Accordingly its classification has reverted to a non-credible contingency event.

Region: NSW1

Lines: Bannaby - Mt Piper 5A6 500kV and Bannaby - Mt Piper 5A7 500kV

Cancellation time: 27/01/2025 21:34

Constraint set(s) revoked:
N-5A6+5A7_N-2 Constraint set contains the following interconnector(s) on the left hand side:
N-Q-MNSP1
NSW1-QLD1
VIC1-NSW1


Refer AEMO Electricity Market Notice 123760

Auto-generated on behalf of Manager NEM Real Time Operations
     
123799RECLASSIFY CONTINGENCY27/01/2025 09:19:40 PM

Cancellation of a Non-Credible Contingency Event: Bayswater - Mt Piper No.5A3 500kV line and Wollar - Mt Piper No.5A5 500kV line in NSW1 due to Lightning.

AEMO ELECTRICITY MARKET NOTICE

Cancellation of reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits is no longer reasonably possible. There is no longer any lightning activity in the vicinity of the following lines. Accordingly its classification has reverted to a non-credible contingency event.

Region: NSW1

Lines: Bayswater - Mt Piper No.5A3 500kV and Wollar - Mt Piper No.5A5 500kV

Cancellation time: 27/01/2025 21:19

Constraint set(s) revoked:
NONE

Refer AEMO Electricity Market Notice 123796

Auto-generated on behalf of Manager NEM Real Time Operations
     
123798RECLASSIFY CONTINGENCY27/01/2025 08:49:43 PM

Cancellation of a Non-Credible Contingency Event: Armidale - Dumaresq 8C 330kV line and Armidale - Sapphire WF 8E 330kV line in NSW1 due to Lightning.

AEMO ELECTRICITY MARKET NOTICE

Cancellation of reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits is no longer reasonably possible. There is no longer any lightning activity in the vicinity of the following lines. Accordingly its classification has reverted to a non-credible contingency event.

Region: NSW1

Lines: Armidale - Dumaresq 8C 330kV and Armidale - Sapphire WF 8E 330kV

Cancellation time: 27/01/2025 20:49

Constraint set(s) revoked:
N-ARDM_ARSR_1PH_N-2 Constraint set contains the following interconnector(s) on the left hand side:
N-Q-MNSP1
NSW1-QLD1


Refer AEMO Electricity Market Notice 123756

Auto-generated on behalf of Manager NEM Real Time Operations
     
X
Cookies help us improve your website experience.
By using our website, you agree to our use of cookies.
Confirm