125543INTER-REGIONAL TRANSFER12/03/2025 07:03:39 AM

Inter-regional transfer limit variation - Waterloo - Hummocks 132kV Line - SA region - 12/03/2025

AEMO ELECTRICITY MARKET NOTICE

Inter-regional transfer limit variation - Waterloo - Hummocks 132kV Line - SA region - 12/03/2025

At 0641 hrs 12/03/2025 there was an unplanned outage of Waterloo - Hummocks 132kV Line.

The following constraint set(s) invoked at 0650 hrs 12/03/2025
S-HUWT

This constraint set(s) contains equations with the following interconnectors on the LHS.
V-S-MNSP1

Refer to the AEMO Network Outage Scheduler for further information.

Manager NEM Real Time Operations
     
125521NON-CONFORMANCE11/03/2025 11:55:21 AM

NON-CONFORMANCE Region NSW1 Tuesday, 11 March 2025

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE NSW1 Region Tuesday, 11 March 2025

AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:

Unit: WTAHB1
Duration: 11/03/2025 11:25 to 11/03/2025 11:55
Amount: -9 MW
Constraint: NC-N_WTAHB1

Auto-generated on behalf of Manager NEM Real Time Operations
     
125518INTER-REGIONAL TRANSFER11/03/2025 10:05:53 AM

Inter-regional transfer limit variation - Penola West - South East 132 kV line and Kincraig - Penola West 132 kV line - SA region - 11/03/2025

AEMO ELECTRICITY MARKET NOTICE

Inter-regional transfer limit variation - Penola West - South East 132 kV line and Kincraig - Penola West 132 kV line - SA region - 11/03/2025

At 0917 hrs 11/03/2025 there was an unplanned outage of Penola West - South East 132 kV line and Kincraig - Penola West 132 kV line.

The following constraint set(s) invoked at 0925 hrs 11/03/2025
S-KNPW and S-PWSE.

This constraint set(s) contains equations with the following interconnectors on the LHS.
V-SA

Refer to the AEMO Network Outage Scheduler for further information.

Manager NEM Real Time Operations
     
125517POWER SYSTEM EVENTS11/03/2025 10:05:23 AM

Non-credible contingency event - SA region - 11/03/2025

AEMO ELECTRICITY MARKET NOTICE.

Non-credible contingency event - SA region - 11/03/2025

At 0917 hrs the Penola West - South East 132 kV line and the Kincraig - Penola West 132 kV line tripped.

AEMO did not instruct load shedding.

Approximately 3 MW of electrical load has been disconnected.

The cause of this non credible contingency event is not known at this stage.

Manager NEM Real Time Operations
     
125513PRICES UNCHANGED11/03/2025 08:20:19 AM

[EventId:202503110755_confirmed] Prices for interval 11-Mar-2025 07:55 are now confirmed

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 0820 hrs on 11 March 2025

PRICES ARE NOW CONFIRMED for trading interval 11-Mar-2025 07:55.

In accordance with Market Notice 125502 AEMO has reviewed this trading interval and determined that:
- Manifestly Incorrect Inputs did not apply

Prices remain unchanged.


This is an AEMO autogenerated Market Notice.
     
125512PRICES UNCHANGED11/03/2025 08:20:19 AM

[EventId:202503110820_confirmed] Prices for interval 11-Mar-2025 08:20 are now confirmed

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 0820 hrs on 11 March 2025

PRICES ARE NOW CONFIRMED for trading interval 11-Mar-2025 08:20.

In accordance with Market Notice 125507 AEMO has reviewed this trading interval and determined that:
- Manifestly Incorrect Inputs did not apply

Prices remain unchanged.


This is an AEMO autogenerated Market Notice.
     
125511PRICES UNCHANGED11/03/2025 08:20:19 AM

[EventId:202503110815_confirmed] Prices for interval 11-Mar-2025 08:15 are now confirmed

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 0820 hrs on 11 March 2025

PRICES ARE NOW CONFIRMED for trading interval 11-Mar-2025 08:15.

In accordance with Market Notice 125506 AEMO has reviewed this trading interval and determined that:
- Manifestly Incorrect Inputs did not apply

Prices remain unchanged.


This is an AEMO autogenerated Market Notice.
     
125510PRICES UNCHANGED11/03/2025 08:20:19 AM

[EventId:202503110810_confirmed] Prices for interval 11-Mar-2025 08:10 are now confirmed

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 0820 hrs on 11 March 2025

PRICES ARE NOW CONFIRMED for trading interval 11-Mar-2025 08:10.

In accordance with Market Notice 125505 AEMO has reviewed this trading interval and determined that:
- Manifestly Incorrect Inputs did not apply

Prices remain unchanged.


This is an AEMO autogenerated Market Notice.
     
125509PRICES UNCHANGED11/03/2025 08:20:18 AM

[EventId:202503110805_confirmed] Prices for interval 11-Mar-2025 08:05 are now confirmed

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 0820 hrs on 11 March 2025

PRICES ARE NOW CONFIRMED for trading interval 11-Mar-2025 08:05.

In accordance with Market Notice 125504 AEMO has reviewed this trading interval and determined that:
- Manifestly Incorrect Inputs did not apply

Prices remain unchanged.


This is an AEMO autogenerated Market Notice.
     