Update - Non-credible contingency event - VIC region - 12/11/2024
Update - Non-credible contingency event - VIC region - 12/11/2024
Refer AEMO Electricity Market Notice 120305
At 1135 hrs the Yallourn No 1 220 kV bus was returned to service.
The cause of this non-credible contingency event has been identified and AEMO is satisfied that another occurrence of this event is unlikely under the current circumstances.
AEMO will not reclassify this event as a credible contingency event.
Manager NEM Real Time Operations
Non-credible contingency event - VIC region - 12/11/2024
Non-credible contingency event - VIC region - 12/11/2024
At 1041 hrs the Yallourn No 1 220 kV bus and Yallourn Unit 4 tripped.
AEMO did not instruct load shedding.
AEMO has not been advised of any disconnection of bulk electrical load.
The cause of this non credible contingency event is not known at this stage.
Manager NEM Real Time Operations
Cancellation of Actual (LOR1) condition in the QLD region - 07/11/2024
Cancellation of Actual (LOR1) condition in the QLD region - 07/11/2024
The Actual LOR1 Condition in the QLD Region advised in AEMO Electricity Market Notice No.120112 is cancelled at 2010 hrs 07/11/2024.
Manager NEM Real Time Operations
Cancellation of Actual (LOR1) condition in the NSW region - 07/11/2024
Cancellation of Actual (LOR1) condition in the NSW region - 07/11/2024
The Actual LOR1 Condition in the NSW Region advised in AEMO Electricity Market Notice No.120113 is cancelled at 1945 hrs 07/11/2024.
Manager NEM Real Time Operations
Actual Lack Of Reserve Level 1 (LOR1) in the NSW region - 07/11/2024
Actual Lack Of Reserve Level 1 (LOR1) in the NSW region - 07/11/2024
An Actual LOR1 condition has been declared under clause 4.8.4(b) of the National Electricity Rules for the NSW region from 1730 hrs.
The Actual LOR1 condition is forecast to exist until 1930 hrs
The capacity reserve requirement is 1430 MW
The minimum capacity reserve available is 1201 MW
Manager NEM Real Time Operations
Actual Lack Of Reserve Level 1 (LOR1) in the QLD region - 07/11/2024
Actual Lack Of Reserve Level 1 (LOR1) in the QLD region - 07/11/2024
An Actual LOR1 condition has been declared under clause 4.8.4(b) of the National Electricity Rules for the QLD region from 1730 hrs.
The Actual LOR1 condition is forecast to exist until 1930 hrs
The capacity reserve requirement is 1090 MW
The minimum capacity reserve available is 897 MW
Manager NEM Real Time Operations
Cancellation of Actual (LOR1) condition in the QLD region - 04/11/2024
Cancellation of Actual (LOR1) condition in the QLD region - 04/11/2024
The Actual LOR1 Condition in the QLD Region advised in AEMO Electricity Market Notice No.119882 is cancelled at 1900 hrs 04/11/2024.
Manager NEM Real Time Operations
Actual Lack Of Reserve Level 1 (LOR1) in the QLD region - 04/11/2024
Actual Lack Of Reserve Level 1 (LOR1) in the QLD region - 04/11/2024
An Actual LOR1 condition has been declared under clause 4.8.4(b) of the National Electricity Rules for the QLD region from 1800 hrs.
The Actual LOR1 condition is forecast to exist until 1930 hrs
The capacity reserve requirement is 1135 MW
The minimum capacity reserve available is 875 MW
Manager NEM Real Time Operations
Cancellation of Actual (LOR1) condition in the QLD region - 31/10/2024
Cancellation of Actual (LOR1) condition in the QLD region - 31/10/2024
The Actual LOR1 Condition in the QLD Region advised in AEMO Electricity Market Notice No.119713 is cancelled at 1839 hrs 31/10/2024.
Manager NEM Real Time Operations