126105NON-CONFORMANCE31/03/2025 08:55:21 AM

NON-CONFORMANCE Region QLD1 Monday, 31 March 2025

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE QLD1 Region Monday, 31 March 2025

AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:

Unit: MPP_2
Duration: 31/03/2025 04:15 to 31/03/2025 08:55
Amount: 38 MW
Constraint: NC-Q_MPP_2

Auto-generated on behalf of Manager NEM Real Time Operations
     
126104NON-CONFORMANCE31/03/2025 08:55:21 AM

NON-CONFORMANCE Region QLD1 Monday, 31 March 2025

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE QLD1 Region Monday, 31 March 2025

AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:

Unit: MPP_1
Duration: 31/03/2025 03:05 to 31/03/2025 08:55
Amount: 41 MW
Constraint: NC-Q_MPP_1

Auto-generated on behalf of Manager NEM Real Time Operations
     
126093NON-CONFORMANCE30/03/2025 11:30:19 PM

NON-CONFORMANCE Region QLD1 Sunday, 30 March 2025

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE QLD1 Region Sunday, 30 March 2025

AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:

Unit: MPP_1
Duration: 30/03/2025 21:45 to 30/03/2025 23:30
Amount: 26 MW
Constraint: NC-Q_MPP_1

Auto-generated on behalf of Manager NEM Real Time Operations
     
126091NON-CONFORMANCE30/03/2025 08:15:19 PM

NON-CONFORMANCE Region QLD1 Sunday, 30 March 2025

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE QLD1 Region Sunday, 30 March 2025

AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:

Unit: MPP_1
Duration: 30/03/2025 17:25 to 30/03/2025 20:15
Amount: -40 MW
Constraint: NC-Q_MPP_1

Auto-generated on behalf of Manager NEM Real Time Operations
     
126086NON-CONFORMANCE30/03/2025 06:15:11 PM

NON-CONFORMANCE Region QLD1 Sunday, 30 March 2025

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE QLD1 Region Sunday, 30 March 2025

AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:

Unit: MPP_2
Duration: 30/03/2025 15:45 to 30/03/2025 18:15
Amount: -113 MW
Constraint: NC-Q_MPP_2

Auto-generated on behalf of Manager NEM Real Time Operations
     
126058INTER-REGIONAL TRANSFER30/03/2025 02:14:22 PM

Inter-regional transfer limit variation - constraint automation to manage Power System Security in NSW region - 30/03/2025

AEMO ELECTRICITY MARKET NOTICE

In order to maintain the power system in a secure operating state in the NSW region, AEMO has invoked automated constraint set CA_SYDS_56FB4FDD from 1405 hrs until further notice.

This constraint set contains equations with the following interconnector on the LHS;

VIC1-NSW1

Refer to AEMO Network Outage Scheduler (NOS) for further information.

Manager NEM Real Time Operations
     
126057NON-CONFORMANCE30/03/2025 04:50:22 AM

NON-CONFORMANCE Region QLD1 Sunday, 30 March 2025

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE QLD1 Region Sunday, 30 March 2025

AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:

Unit: MPP_1
Duration: 30/03/2025 04:40 to 30/03/2025 04:50
Amount: -24 MW
Constraint: NC-Q_MPP_1

Auto-generated on behalf of Manager NEM Real Time Operations
     
126045NON-CONFORMANCE29/03/2025 05:00:17 PM

NON-CONFORMANCE Region QLD1 Saturday, 29 March 2025

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE QLD1 Region Saturday, 29 March 2025

AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:

Unit: CALL_B_2
Duration: 29/03/2025 16:55 to 29/03/2025 17:00
Amount: -11 MW
Constraint: NC-Q_CALL_B_2

Auto-generated on behalf of Manager NEM Real Time Operations
     
126031INTER-REGIONAL TRANSFER29/03/2025 04:45:41 AM

Inter-regional transfer limit variation - Mullumbimby - Dunoon - Lismore 132 kV 9U6 line - NSW region - 29/03/2025

AEMO ELECTRICITY MARKET NOTICE

Inter-regional transfer limit variation - Mullumbimby - Dunoon - Lismore 132 kV 9U6 line - NSW region - 29/03/2025

At 0427 hrs 29/03/2025 there was an unplanned outage of Mullumbimby - Dunoon - Lismore 132 kV 9U6 line.

The following constraint set(s) invoked at 0435 hrs 29/03/2025
N-LSDU_9U6

This constraint set(s) contains equations with the following interconnectors on the LHS.
N-Q-MNSP1

Refer to the AEMO Network Outage Scheduler for further information.

Manager NEM Real Time Operations
     
X
Cookies help us improve your website experience.
By using our website, you agree to our use of cookies.
Confirm