125937NON-CONFORMANCE24/03/2025 11:30:20 PM

NON-CONFORMANCE Region QLD1 Monday, 24 March 2025

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE QLD1 Region Monday, 24 March 2025

AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:

Unit: MPP_2
Duration: 24/03/2025 22:10 to 24/03/2025 23:30
Amount: -41 MW
Constraint: NC-Q_MPP_2

Auto-generated on behalf of Manager NEM Real Time Operations
     
125936SETTLEMENTS RESIDUE24/03/2025 06:15:17 PM

[EventId:202503241815_NRM_NSW1_VIC1_stopped] NEGRES CONSTRAINT NRM_NSW1_VIC1 ceased operating from 24 March 2025 18:15

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1815 hrs on 24 March 2025

CANCELLATION - ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 24 March 2025.

Refer to market notice: 125915

AEMO has ceased taking action to minimize the further accumulation of negative settlement residues on the NSW to VIC directional interconnector.

The negative residue constraint NRM_NSW1_VIC1 ceased operating at 1815 hrs on 24 March 2025.

This is an AEMO autogenerated Market Notice.
     
125915SETTLEMENTS RESIDUE24/03/2025 05:15:25 PM

[EventId:202503241715_NRM_NSW1_VIC1_started] NEGRES CONSTRAINT NRM_NSW1_VIC1 started operating from 24 March 2025 17:15

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1715 hrs on 24 March 2025

ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 24 March 2025.

Electricity Market outcomes have resulted in the accumulation of negative settlement residues that have exceeded the allowable negative residue threshold for the NSW to VIC directional interconnector.

The negative residue constraint set NRM_NSW1_VIC1 commenced operating from 1715 hrs on 24 March 2025.

This constraint set contains an equation with the following interconnectors on the LHS:
VIC1-NSW1

The RHS of the constraint equation may be adjusted to manage residues.


This is an AEMO autogenerated Market Notice.
     
125889SETTLEMENTS RESIDUE22/03/2025 06:45:25 PM

[EventId:202503221845_NRM_NSW1_VIC1_stopped] NEGRES CONSTRAINT NRM_NSW1_VIC1 ceased operating from 22 March 2025 18:45

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1845 hrs on 22 March 2025

CANCELLATION - ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 22 March 2025.

Refer to market notice: 125879

AEMO has ceased taking action to minimize the further accumulation of negative settlement residues on the NSW to VIC directional interconnector.

The negative residue constraint NRM_NSW1_VIC1 ceased operating at 1845 hrs on 22 March 2025.

This is an AEMO autogenerated Market Notice.
     
125879SETTLEMENTS RESIDUE22/03/2025 06:05:15 PM

[EventId:202503221805_NRM_NSW1_VIC1_started] NEGRES CONSTRAINT NRM_NSW1_VIC1 started operating from 22 March 2025 18:05

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1805 hrs on 22 March 2025

ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 22 March 2025.

Electricity Market outcomes have resulted in the accumulation of negative settlement residues that have exceeded the allowable negative residue threshold for the NSW to VIC directional interconnector.

The negative residue constraint set NRM_NSW1_VIC1 commenced operating from 1805 hrs on 22 March 2025.

This constraint set contains an equation with the following interconnectors on the LHS:
VIC1-NSW1

The RHS of the constraint equation may be adjusted to manage residues.


This is an AEMO autogenerated Market Notice.
     
125864NON-CONFORMANCE22/03/2025 02:45:19 PM

NON-CONFORMANCE Region QLD1 Saturday, 22 March 2025

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE QLD1 Region Saturday, 22 March 2025

AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:

Unit: OAKEY1SF
Duration: 22/03/2025 12:40 to 22/03/2025 14:45
Amount: 23 MW
Constraint: NC-Q_OAKEY1SF

Auto-generated on behalf of Manager NEM Real Time Operations
     
125849SETTLEMENTS RESIDUE21/03/2025 07:30:22 PM

[EventId:202503211930_NRM_NSW1_VIC1_stopped] NEGRES CONSTRAINT NRM_NSW1_VIC1 ceased operating from 21 March 2025 19:30

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1930 hrs on 21 March 2025

CANCELLATION - ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 21 March 2025.

Refer to market notice: 125848

AEMO has ceased taking action to minimize the further accumulation of negative settlement residues on the NSW to VIC directional interconnector.

The negative residue constraint NRM_NSW1_VIC1 ceased operating at 1930 hrs on 21 March 2025.

This is an AEMO autogenerated Market Notice.
     
125848SETTLEMENTS RESIDUE21/03/2025 06:30:33 PM

[EventId:202503211830_NRM_NSW1_VIC1_started] NEGRES CONSTRAINT NRM_NSW1_VIC1 started operating from 21 March 2025 18:30

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1830 hrs on 21 March 2025

ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 21 March 2025.

Electricity Market outcomes have resulted in the accumulation of negative settlement residues that have exceeded the allowable negative residue threshold for the NSW to VIC directional interconnector.

The negative residue constraint set NRM_NSW1_VIC1 commenced operating from 1830 hrs on 21 March 2025.

This constraint set contains an equation with the following interconnectors on the LHS:
VIC1-NSW1

The RHS of the constraint equation may be adjusted to manage residues.


This is an AEMO autogenerated Market Notice.
     
125834NON-CONFORMANCE21/03/2025 05:45:25 PM

NON-CONFORMANCE Region QLD1 Friday, 21 March 2025

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE QLD1 Region Friday, 21 March 2025

AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:

Unit: MPP_2
Duration: 21/03/2025 17:40 to 21/03/2025 17:45
Amount: -55 MW
Constraint: NC-Q_MPP_2