Market Notices

120307GENERAL NOTICE12/11/2024 11:48:51 AM

Project Energy Connect (PEC-1) testing 12th November 2024 1630-2200 for flows in both directions

AEMO ELECTRICITY MARKET NOTICE

Refer to market notice 120276

There is an opportunity for testing Project Energy Connect (PEC-1) for flows in both directions up to 50 MW on 12th November from 16:30hrs to 22:00hrs

This test includes switching of a transmission line in SA and switching of a reactive plant in NSW.

Please also refer to the published formal PEC Stage 1 and HIC capacity release testing information at the following link https://aemo.com.au/-/media/files/stakeholder_consultation/consultations/nem-consultations/2023/project-energyconnect-stage-1-and-hic-capacity-release/pec-stage-1-and-hic---final-test-program.pdf?la=en.

Ben Blake
AEMO Operations
     
120306POWER SYSTEM EVENTS12/11/2024 11:43:52 AM

Update - Non-credible contingency event - VIC region - 12/11/2024

AEMO ELECTRICITY MARKET NOTICE.

Update - Non-credible contingency event - VIC region - 12/11/2024

Refer AEMO Electricity Market Notice 120305

At 1135 hrs the Yallourn No 1 220 kV bus was returned to service.

The cause of this non-credible contingency event has been identified and AEMO is satisfied that another occurrence of this event is unlikely under the current circumstances.

AEMO will not reclassify this event as a credible contingency event.

Manager NEM Real Time Operations
     
120305POWER SYSTEM EVENTS12/11/2024 10:55:18 AM

Non-credible contingency event - VIC region - 12/11/2024

AEMO ELECTRICITY MARKET NOTICE.

Non-credible contingency event - VIC region - 12/11/2024

At 1041 hrs the Yallourn No 1 220 kV bus and Yallourn Unit 4 tripped.

AEMO did not instruct load shedding.

AEMO has not been advised of any disconnection of bulk electrical load.


The cause of this non credible contingency event is not known at this stage.


Manager NEM Real Time Operations
     
120276GENERAL NOTICE11/11/2024 05:07:24 PM

Project Energy Connect (PEC-1) testing 12th November 2024 for flows in both directions

AEMO ELECTRICITY MARKET NOTICE

Refer to market notice 120016

There is an opportunity for testing Project Energy Connect (PEC-1) for flows in both directions up to 50 MW on 12th November from 06:00hrs to 11:00hrs

This test includes the synchronization of the new PEC Stage 1 interconnector and testing of the Phase Shifting transformer at Buronga substation.

Please also refer to the published formal PEC Stage 1 and HIC capacity release testing information at the following link https://aemo.com.au/-/media/files/stakeholder_consultation/consultations/nem-consultations/2023/project-energyconnect-stage-1-and-hic-capacity-release/pec-stage-1-and-hic---final-test-program.pdf?la=en.

Ben Blake
AEMO Operations
     
120099MINIMUM SYSTEM LOAD07/11/2024 03:11:35 PM

Cancellation - Forecast Minimum System Load 1 (MSL1) condition in the VIC Region on 10/11/2024

AEMO ELECTRICITY MARKET NOTICE

Cancellation - Forecast MSL1 - VIC Region at 1400 hrs 07/11/2024.

Refer to Market Notice 119996 for Forecast MSL1.

AEMO Operations
     
120016GENERAL NOTICE06/11/2024 04:57:21 PM

Cancellation of Project Energy Connect (PEC-1) testing on 6th November 2024

AEMO ELECTRICITY MARKET NOTICE

Refer to market notice 119963

The Project Energy Connect (PEC-1) testing on 6th November has now been cancelled.

Terry Liu
AEMO Operations
     
119996MINIMUM SYSTEM LOAD06/11/2024 03:44:08 PM

Forecast Minimum System Load 1 (MSL1) condition in the VIC region on 10/11/2024

AEMO ELECTRICITY MARKET NOTICE
Update to Market Notice 119920 - AEMO has detected that there is an elevated risk of insufficient demand to maintain a secure operating state in the VIC region on 10/11/2024.

Minimum System Load (MSL) conditions are forecast when regional demand is less than the relevant MSL threshold. The advisory MSL thresholds are:
o MSL1 - 1745 MW
o MSL2 - 1245 MW
o MSL3 - 745 MW

The regional demand is forecast to be below the MSL1 threshold for the following period:

1. From 1230 hrs to 1330 hrs 10/11/2024. Minimum regional demand is forecast to be 1719 MW at 1300 hrs.

Forecast regional demand (DEMAND50) is published in Short Term and Pre-Dispatch PASA region solution reports available on Market Data NEMWEB: https://aemo.com.au/en/energy-systems/electricity/national-electricity-market-nem/data-nem/market-data-nemweb .

AEMO Operations
     
119995MINIMUM SYSTEM LOAD06/11/2024 03:45:53 PM

Cancellation - Forecast Minimum System Load 1 (MSL1) condition in the VIC Region on 09/11/2024

AEMO ELECTRICITY MARKET NOTICE

Cancellation - Forecast MSL1 - VIC Region at 1400 hrs 06/11/2024.

Refer to Market Notice 119866 for Forecast MSL1.

AEMO Operations
     
119963GENERAL NOTICE06/11/2024 11:27:15 AM

Correction to testing time for Project Energy Connect (PEC-1) 6th November 2024 for flows in both directions

AEMO ELECTRICITY MARKET NOTICE

Refer to market notice 119961

This is correction to Project Energy Connect (PEC-1) testing time issued in previous notice 119961.
Testing time is on 6th November from 11:00 hrs to 22:00 hrs.

The test is for flows in both directions up to 50 MW. This test includes a trip and reclose of a line in South Australia. Please also refer to the published formal PEC Stage 1 and HIC capacity release testing information at the following link https://aemo.com.au/-/media/files/stakeholder_consultation/consultations/nem-consultations/2023/project-energyconnect-stage-1-and-hic-capacity-release/pec-stage-1-and-hic---final-test-program.pdf?la=en.

Mya San
AEMO Operations
     
X
Cookies help us improve your website experience.
By using our website, you agree to our use of cookies.
Confirm