Inter-regional transfer limit variation - Armidale No 1 SVC- NSW region - 11/02/2025
Inter-regional transfer limit variation - Armidale No 1 SVC - NSW region - 11/02/2025
At 2315 hrs 11/02/2025 there was an unplanned outage of Armidale No 1 SVC.
The following constraint set(s) invoked at 2325 hrs 11/02/2025
N-AR_VC1
This constraint set(s) contains equations with the following interconnectors on the LHS.
N-Q-MNSP1,NSW1-QLD1
Refer to the AEMO Network Outage Scheduler for further information.
Manager NEM Real Time Operations
Inter-regional transfer limit variation - Yass Overload Control Scheme - NSW region - 11/02/2025
Inter-regional transfer limit variation - Yass Overload Control Scheme - NSW region - 11/02/2025
At 1750 hrs 11/02/2025 there was a short notice outage of Yass Overload Control Scheme.
The following constraint set(s) invoked at 1750 hrs: N-YSWG_SCHEME
This constraint set(s) contains equations with the following interconnectors on the LHS,
V-S-MNSP1
VIC1-NSW1
Refer to the AEMO Network Outage Scheduler for further information.
Manager NEM Real Time Operations
Inter-regional transfer limit variation - MLTS-SMTS No1 500 kV line CB at SYTS - VIC region - 11/02/2025
Inter-regional transfer limit variation - MLTS-SMTS No1 500 kV line CB at SYTS - VIC region - 11/02/2025
At 1538 hrs 11/02/2025 there was an unplanned outage of MLTS-SMTS No1 500 kV line CB at SYTS .
The following constraint set(s) invoked at 1600 hrs 11/02/2025
V-SY_CB
This constraint set(s) contains equations with the following interconnectors on the LHS.
T-V-MNSP1,V-S-MNSP1,V-SA,VIC1-NSW1
Refer to the AEMO Network Outage Scheduler for further information.
Manager NEM Real Time Operations
Cancellation - Inter-regional transfer limit variation - constraint automation to manage Power System Security in SA region - 11/02/2025
Referring to Market Notice 124466.
The power system security condition in the SA region, requiring AEMO to invoke the automated constraint set CA_SYDS_56BD5936 has ended at 1520 hrs.
Constraint set revoked: CA_SYDS_56BD5936
Manager NEM Real Time Operations
Forecast Minimum System Load (MSL1) condition in the VIC region on 16/02/2025
Update to Market Notice 124437 - AEMO has detected that there is an elevated risk of insufficient demand to maintain a secure operating state in the VIC region on 16/02/2025.
Minimum System Load (MSL) conditions are forecast when regional demand is less than the relevant MSL threshold. The advisory MSL thresholds are:
o MSL1 - 2115 MW
o MSL2 - 1615 MW
o MSL3 - 1115 MW
The regional demand is forecast to be below the MSL1 threshold for the following period:
From 1200 hrs to 1500 hrs 16/02/2025. Minimum regional demand is forecast to be 1873 MW at 1330 hrs.
Forecast regional demand (DEMAND50) is published in Short Term and Pre-Dispatch PASA region solution reports available on Market Data NEMWEB: https://aemo.com.au/en/energy-systems/electricity/national-electricity-market-nem/data-nem/market-data-nemweb .
AEMO Operations
Inter-regional transfer limit variation - constraint automation to manage Power System Security in SA region - 11/02/2025
In order to maintain the power system in a secure operating state in the SA region, AEMO has invoked automated constraint set CA_SYDS_56BD5936 from 1410 hrs until further notice.
This constraint set contains equations with the following interconnector on the LHS;
V-SA
Manager NEM Real Time Operations
Forecast Minimum System Load (MSL1) condition in the VIC region on 16/02/2025
AEMO has detected that there is an elevated risk of insufficient demand to maintain a secure operating state in the VIC region on 16/02/2025.
Minimum System Load (MSL) conditions are forecast when regional demand is less than the relevant MSL threshold. The advisory MSL thresholds are:
o MSL1 - 2060 MW
o MSL2 - 1560 MW
o MSL3 - 1060 MW
The regional demand is forecast to be below the MSL1 threshold for the following period:
From 1130 hrs to 1430 hrs 16/02/2025. Minimum regional demand is forecast to be 1838 MW at 1330 hrs.
Forecast regional demand (DEMAND50) is published in Short Term and Pre-Dispatch PASA region solution reports available on Market Data NEMWEB: https://aemo.com.au/en/energy-systems/electricity/national-electricity-market-nem/data-nem/market-data-nemweb .
AEMO Operations
Inter-regional transfer limit variation - Ingleburn - Wallerawang (77) 330 kV line - NSW region - 10/02/2025
Inter-regional transfer limit variation - Ingleburn - Wallerawang (77) 330 kV line - NSW region - 10/02/2025
At 0945 hrs 10/02/2025 there was an unplanned outage of Ingleburn - Wallerawang (77) 330 kV line.
The following constraint set(s) invoked at 0955 hrs 10/02/2025
N-X_AVMA_SSWW
This constraint set(s) contains equations with the following interconnectors on the LHS.
N-Q-MNSP1,NSW1-QLD1,VIC1-NSW1
Refer to the AEMO Network Outage Scheduler for further information.
Manager NEM Real Time Operations
Inter-regional transfer limit variation - Collector - Marulan (4) 330 kV line - NSW region - 06/02/2025
Inter-regional transfer limit variation -Collector - Marulan (4) 330 kV line - NSW region - 06/02/2025
The outage has been completed and Collector - Marulan (4) 330 kV line returned to service at 0825 hrs 06/02/2025
Constraint set(s) revoked: N-CTMN_4_WG_CLOSE
Manager NEM Real Time Operations