[EventId:202503161720_NRM_NSW1_VIC1_started] NEGRES CONSTRAINT NRM_NSW1_VIC1 started operating from 16 March 2025 17:20
Issued by Australian Energy Market Operator Ltd at 1720 hrs on 16 March 2025
ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 16 March 2025.
Electricity Market outcomes have resulted in the accumulation of negative settlement residues that have exceeded the allowable negative residue threshold for the NSW to VIC directional interconnector.
The negative residue constraint set NRM_NSW1_VIC1 commenced operating from 1720 hrs on 16 March 2025.
This constraint set contains an equation with the following interconnectors on the LHS:
VIC1-NSW1
The RHS of the constraint equation may be adjusted to manage residues.
This is an AEMO autogenerated Market Notice.
[EventId:202503161430_NRM_VIC1_SA1_stopped] NEGRES CONSTRAINT NRM_VIC1_SA1 ceased operating from 16 March 2025 14:30
Issued by Australian Energy Market Operator Ltd at 1430 hrs on 16 March 2025
CANCELLATION - ACTUAL NEGATIVE SETTLEMENT RESIDUES - VIC to SA - 16 March 2025.
Refer to market notice: 125706
AEMO has ceased taking action to minimize the further accumulation of negative settlement residues on the VIC to SA directional interconnector.
The negative residue constraint NRM_VIC1_SA1 ceased operating at 1430 hrs on 16 March 2025.
This is an AEMO autogenerated Market Notice.
[EventId:202503161405_NRM_VIC1_SA1_started] NEGRES CONSTRAINT NRM_VIC1_SA1 started operating from 16 March 2025 14:05
Issued by Australian Energy Market Operator Ltd at 1405 hrs on 16 March 2025
ACTUAL NEGATIVE SETTLEMENT RESIDUES - VIC to SA - 16 March 2025.
Electricity Market outcomes have resulted in the accumulation of negative settlement residues that have exceeded the allowable negative residue threshold for the VIC to SA directional interconnector.
The negative residue constraint set NRM_VIC1_SA1 commenced operating from 1405 hrs on 16 March 2025.
This constraint set contains an equation with the following interconnectors on the LHS:
V-S-MNSP1
V-SA
The RHS of the constraint equation may be adjusted to manage residues.
This is an AEMO autogenerated Market Notice.
[EventId:202503161345_NRM_VIC1_SA1_stopped] NEGRES CONSTRAINT NRM_VIC1_SA1 ceased operating from 16 March 2025 13:45
Issued by Australian Energy Market Operator Ltd at 1345 hrs on 16 March 2025
CANCELLATION - ACTUAL NEGATIVE SETTLEMENT RESIDUES - VIC to SA - 16 March 2025.
Refer to market notice: 125703
AEMO has ceased taking action to minimize the further accumulation of negative settlement residues on the VIC to SA directional interconnector.
The negative residue constraint NRM_VIC1_SA1 ceased operating at 1345 hrs on 16 March 2025.
This is an AEMO autogenerated Market Notice.
[EventId:202503161305_NRM_VIC1_SA1_started] NEGRES CONSTRAINT NRM_VIC1_SA1 started operating from 16 March 2025 13:05
Issued by Australian Energy Market Operator Ltd at 1305 hrs on 16 March 2025
ACTUAL NEGATIVE SETTLEMENT RESIDUES - VIC to SA - 16 March 2025.
Electricity Market outcomes have resulted in the accumulation of negative settlement residues that have exceeded the allowable negative residue threshold for the VIC to SA directional interconnector.
The negative residue constraint set NRM_VIC1_SA1 commenced operating from 1305 hrs on 16 March 2025.
This constraint set contains an equation with the following interconnectors on the LHS:
V-S-MNSP1
V-SA
The RHS of the constraint equation may be adjusted to manage residues.
This is an AEMO autogenerated Market Notice.
Non-credible contingency event - QLD region - 16/03/2025
Non-credible contingency event - QLD region - 16/03/2025
At 1131 hrs the H35 Strathmore 132 kV No 2 bus tripped. Whitsunday Solar farm and Hamilton Solar farm were disconnected.
AEMO did not instruct load shedding.
The cause of this non credible contingency event is not known at this stage.
Manager NEM Real Time Operations
[EventId:202503152000_NRM_NSW1_VIC1_stopped] NEGRES CONSTRAINT NRM_NSW1_VIC1 ceased operating from 15 March 2025 20:00
Issued by Australian Energy Market Operator Ltd at 2000 hrs on 15 March 2025
CANCELLATION - ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 15 March 2025.
Refer to market notice: 125680
AEMO has ceased taking action to minimize the further accumulation of negative settlement residues on the NSW to VIC directional interconnector.
The negative residue constraint NRM_NSW1_VIC1 ceased operating at 2000 hrs on 15 March 2025.
This is an AEMO autogenerated Market Notice.
[EventId:202503151620_confirmed] Prices for interval 15-Mar-2025 16:20 are now confirmed
Issued by Australian Energy Market Operator Ltd at 1645 hrs on 15 March 2025
PRICES ARE NOW CONFIRMED for trading interval 15-Mar-2025 16:20.
In accordance with Market Notice 125673 AEMO has reviewed this trading interval and determined that:
- Manifestly Incorrect Inputs did not apply
Prices remain unchanged.
This is an AEMO autogenerated Market Notice.
[EventId:202503151645_confirmed] Prices for interval 15-Mar-2025 16:45 are now confirmed
Issued by Australian Energy Market Operator Ltd at 1645 hrs on 15 March 2025
PRICES ARE NOW CONFIRMED for trading interval 15-Mar-2025 16:45.
In accordance with Market Notice 125681 AEMO has reviewed this trading interval and determined that:
- Manifestly Incorrect Inputs did not apply
Prices remain unchanged.
This is an AEMO autogenerated Market Notice.