PDPASA - Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 07/02/2025
AEMO ELECTRICITY MARKET NOTICE
AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the NSW region for the following period:
From 1630 hrs 07/02/2025 to 1700 hrs 07/02/2025.
The forecast capacity reserve requirement is 1370 MW.
The minimum capacity reserve available is 1296 MW.
Manager NEM Real Time Operations
[EventId:202502061725_confirmed] Prices for interval 06-Feb-2025 17:25 are now confirmed
Issued by Australian Energy Market Operator Ltd at 1735 hrs on 6 February 2025
PRICES ARE NOW CONFIRMED for trading interval 06-Feb-2025 17:25.
In accordance with Market Notice 124267 AEMO has reviewed this trading interval and determined that:
- Manifestly Incorrect Inputs did not apply
Prices remain unchanged.
This is an AEMO autogenerated Market Notice.
[EventId:202502061735_confirmed] Prices for interval 06-Feb-2025 17:35 are now confirmed
Issued by Australian Energy Market Operator Ltd at 1735 hrs on 6 February 2025
PRICES ARE NOW CONFIRMED for trading interval 06-Feb-2025 17:35.
In accordance with Market Notice 124269 AEMO has reviewed this trading interval and determined that:
- Manifestly Incorrect Inputs did not apply
Prices remain unchanged.
This is an AEMO autogenerated Market Notice.
[EventId:202502061730_confirmed] Prices for interval 06-Feb-2025 17:30 are now confirmed
Issued by Australian Energy Market Operator Ltd at 1735 hrs on 6 February 2025
PRICES ARE NOW CONFIRMED for trading interval 06-Feb-2025 17:30.
In accordance with Market Notice 124268 AEMO has reviewed this trading interval and determined that:
- Manifestly Incorrect Inputs did not apply
Prices remain unchanged.
This is an AEMO autogenerated Market Notice.
[EventId:202502061720_confirmed] Prices for interval 06-Feb-2025 17:20 are now confirmed
Issued by Australian Energy Market Operator Ltd at 1735 hrs on 6 February 2025
PRICES ARE NOW CONFIRMED for trading interval 06-Feb-2025 17:20.
In accordance with Market Notice 124266 AEMO has reviewed this trading interval and determined that:
- Manifestly Incorrect Inputs did not apply
Prices remain unchanged.
This is an AEMO autogenerated Market Notice.
[EventId:202502061715_confirmed] Prices for interval 06-Feb-2025 17:15 are now confirmed
Issued by Australian Energy Market Operator Ltd at 1735 hrs on 6 February 2025
PRICES ARE NOW CONFIRMED for trading interval 06-Feb-2025 17:15.
In accordance with Market Notice 124264 AEMO has reviewed this trading interval and determined that:
- Manifestly Incorrect Inputs did not apply
Prices remain unchanged.
This is an AEMO autogenerated Market Notice.
[EventId:202502061710_confirmed] Prices for interval 06-Feb-2025 17:10 are now confirmed
Issued by Australian Energy Market Operator Ltd at 1735 hrs on 6 February 2025
PRICES ARE NOW CONFIRMED for trading interval 06-Feb-2025 17:10.
In accordance with Market Notice 124263 AEMO has reviewed this trading interval and determined that:
- Manifestly Incorrect Inputs did not apply
Prices remain unchanged.
This is an AEMO autogenerated Market Notice.
PDPASA - Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 06/02/2025
AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the NSW region for the following Periods:
[1.] From 1730 hrs 06/02/2025 to 1800 hrs 06/02/2025.
The forecast capacity reserve requirement is 1370 MW.
The minimum capacity reserve available is 1347 MW.
[2.] From 1630 hrs 07/02/2025 to 1700 hrs 07/02/2025.
The forecast capacity reserve requirement is 1370 MW.
The minimum capacity reserve available is 1248 MW.
Manager NEM Real Time Operations
Direction - SA region to AGL SA Generation Pty Limited - TORRB2 TORRENS ISLAN
Direction - SA region to AGL SA Generation Pty Limited - TORRB2 TORRENS ISLAN
Refer to Market Notice 124253
In accordance with section 116 of the National Electricity Law, AEMO is issuing a direction to AGL SA Generation Pty Limited. For the purposes of the National Electricity Rules this is a direction under clause 4.8.9(a1)(1).
Direction issued to: AGL SA Generation Pty Limited - TORRB2 TORRENS ISLAN at 1500 hrs 06/02/2025
Type of resource: generating unit
Required actions: Remain synchronised and follow dispatch targets at 0730 hrs 07/02/2025
Services provided: Voltage Control
Circumstances necessitating the Direction: Voltage
Circumstances necessitating the Direction additional detail: The synchronous generating units currently expected to be synchronised in SA will be inadequate to maintain sufficient Voltage Control in SA. Intervention is required to maintain the power system in a secure operating state
Expected duration: 0400 hrs 08/02/2025 / further notice.
AGL SA Generation Pty Limited does not incur any civil monetary liability for a relevant action taken in accordance with this direction unless the action is taken in bad faith.
Manager NEM Real Time Operations