Market Notices

125924PRICES UNCHANGED24/03/2025 05:30:21 PM

[EventId:202503241710_confirmed] Prices for interval 24-Mar-2025 17:10 are now confirmed

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1730 hrs on 24 March 2025

PRICES ARE NOW CONFIRMED for trading interval 24-Mar-2025 17:10.

In accordance with Market Notice 125912 AEMO has reviewed this trading interval and determined that:
- Manifestly Incorrect Inputs did not apply

Prices remain unchanged.


This is an AEMO autogenerated Market Notice.
     
125922PRICES UNCHANGED24/03/2025 05:30:21 PM

[EventId:202503241730_confirmed] Prices for interval 24-Mar-2025 17:30 are now confirmed

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1730 hrs on 24 March 2025

PRICES ARE NOW CONFIRMED for trading interval 24-Mar-2025 17:30.

In accordance with Market Notice 125917 AEMO has reviewed this trading interval and determined that:
- Manifestly Incorrect Inputs did not apply

Prices remain unchanged.


This is an AEMO autogenerated Market Notice.
     
125921PRICES UNCHANGED24/03/2025 05:30:21 PM

[EventId:202503241725_confirmed] Prices for interval 24-Mar-2025 17:25 are now confirmed

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1730 hrs on 24 March 2025

PRICES ARE NOW CONFIRMED for trading interval 24-Mar-2025 17:25.

In accordance with Market Notice 125916 AEMO has reviewed this trading interval and determined that:
- Manifestly Incorrect Inputs did not apply

Prices remain unchanged.


This is an AEMO autogenerated Market Notice.
     
125920PRICES UNCHANGED24/03/2025 05:30:21 PM

[EventId:202503241720_confirmed] Prices for interval 24-Mar-2025 17:20 are now confirmed

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1730 hrs on 24 March 2025

PRICES ARE NOW CONFIRMED for trading interval 24-Mar-2025 17:20.

In accordance with Market Notice 125914 AEMO has reviewed this trading interval and determined that:
- Manifestly Incorrect Inputs did not apply

Prices remain unchanged.


This is an AEMO autogenerated Market Notice.
     
125919PRICES UNCHANGED24/03/2025 05:30:22 PM

[EventId:202503241715_confirmed] Prices for interval 24-Mar-2025 17:15 are now confirmed

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1730 hrs on 24 March 2025

PRICES ARE NOW CONFIRMED for trading interval 24-Mar-2025 17:15.

In accordance with Market Notice 125913 AEMO has reviewed this trading interval and determined that:
- Manifestly Incorrect Inputs did not apply

Prices remain unchanged.


This is an AEMO autogenerated Market Notice.
     
125918PRICES UNCHANGED24/03/2025 05:30:20 PM

[EventId:202503241705_confirmed] Prices for interval 24-Mar-2025 17:05 are now confirmed

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1730 hrs on 24 March 2025

PRICES ARE NOW CONFIRMED for trading interval 24-Mar-2025 17:05.

In accordance with Market Notice 125911 AEMO has reviewed this trading interval and determined that:
- Manifestly Incorrect Inputs did not apply

Prices remain unchanged.


This is an AEMO autogenerated Market Notice.
     
125910RECLASSIFY CONTINGENCY24/03/2025 04:16:21 PM

Reclassification of a Non-Credible Contingency Event: Guybal Munjan - Chalumbin 857 275kV line line and Guybal Munjan - Chalumbin 858 275kV line line in QLD1 due to Lightning.

AEMO ELECTRICITY MARKET NOTICE

Reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits to now be more likely and reasonably possible. Accordingly AEMO has reclassified it as a credible contingency event.

Region: QLD1

Lines: Guybal Munjan - Chalumbin 857 275kV line and Guybal Munjan - Chalumbin 858 275kV line

Duration: 24/03/2025 16:16 until further notice

Constraint set(s) invoked:
Q-RSCH_N-2 Constraint set contains the following interconnector(s) on the left hand side:
NONE


Auto-generated on behalf of Manager NEM Real Time Operations
     
125909RECLASSIFY CONTINGENCY24/03/2025 04:16:20 PM

Reclassification of a Non-Credible Contingency Event: Chalumbin - Turkinje No.7165 132 kV line and Chalumbin - Turkinje No.7166 132 kV line in QLD1 due to Lightning.

AEMO ELECTRICITY MARKET NOTICE

Reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits to now be more likely and reasonably possible. Accordingly AEMO has reclassified it as a credible contingency event.

Region: QLD1

Lines: Chalumbin - Turkinje No.7165 132 kV and Chalumbin - Turkinje No.7166 132 kV

Duration: 24/03/2025 16:16 until further notice

Constraint set(s) invoked:
NONE

Auto-generated on behalf of Manager NEM Real Time Operations
     
125904RECLASSIFY CONTINGENCY23/03/2025 05:19:15 PM

Cancellation of a Non-Credible Contingency Event: Chalumbin - Turkinje No.7165 132 kV line and Chalumbin - Turkinje No.7166 132 kV line in QLD1 due to Lightning.

AEMO ELECTRICITY MARKET NOTICE

Cancellation of reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits is no longer reasonably possible. There is no longer any lightning activity in the vicinity of the following lines. Accordingly its classification has reverted to a non-credible contingency event.

Region: QLD1

Lines: Chalumbin - Turkinje No.7165 132 kV and Chalumbin - Turkinje No.7166 132 kV

Cancellation time: 23/03/2025 17:19

Constraint set(s) revoked:
NONE

Refer AEMO Electricity Market Notice 125893

Auto-generated on behalf of Manager NEM Real Time Operations
     
X
Cookies help us improve your website experience.
By using our website, you agree to our use of cookies.
Confirm