Filter by category
Filter by Date
Inter-regional transfer limit variation - Ingleburn - Wallerawang (77) 330 kV line - NSW region - 10/02/2025
Inter-regional transfer limit variation - Ingleburn - Wallerawang (77) 330 kV line - NSW region - 10/02/2025
At 0945 hrs 10/02/2025 there was an unplanned outage of Ingleburn - Wallerawang (77) 330 kV line.
The following constraint set(s) invoked at 0955 hrs 10/02/2025
N-X_AVMA_SSWW
This constraint set(s) contains equations with the following interconnectors on the LHS.
N-Q-MNSP1,NSW1-QLD1,VIC1-NSW1
Refer to the AEMO Network Outage Scheduler for further information.
Manager NEM Real Time Operations
NON-CONFORMANCE Region VIC1 Saturday, 8 February 2025
NON-CONFORMANCE VIC1 Region Saturday, 8 February 2025
AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:
Unit: LYA2
Duration: 08/02/2025 07:55 to 08/02/2025 08:05
Amount: -39 MW
Constraint: NC-V_LYA2
Auto-generated on behalf of Manager NEM Real Time Operations
Update - Non-credible contingency event - NSW region - 23/01/2025
Update - Non-credible contingency event - NSW region - 23/01/2025
Refer AEMO Electricity Market Notice 123615
At 0240 hrs on the 23/01/2025 there was a trip and auto reclose of the Kempsey - Macksville 9W5 and the Kempsey - Raleigh 9W2 132kV Lines
The cause of this non-credible contingency event has been identified and AEMO is satisfied that another occurrence of this event is unlikely under the current circumstances.
AEMO will not reclassify this event as a credible contingency event.
Manager NEM Real Time Operations
NON-CONFORMANCE Region NSW1 Friday, 7 February 2025
NON-CONFORMANCE NSW1 Region Friday, 7 February 2025
AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:
Unit: VP5
Duration: 07/02/2025 03:40 to 07/02/2025 03:50
Amount: -20 MW
Constraint: NC-N_VP5
Auto-generated on behalf of Manager NEM Real Time Operations
NON-CONFORMANCE Region QLD1 Thursday, 6 February 2025
NON-CONFORMANCE QLD1 Region Thursday, 6 February 2025
AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:
Unit: KINGASF1
Duration: 06/02/2025 14:55 to 06/02/2025 16:15
Amount: 29 MW
Constraint: NC-Q_KINGASF1
Auto-generated on behalf of Manager NEM Real Time Operations
NON-CONFORMANCE Region NSW1 Thursday, 6 February 2025
NON-CONFORMANCE NSW1 Region Thursday, 6 February 2025
AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:
Unit: BERYLSF1
Duration: 06/02/2025 12:35 to 06/02/2025 13:15
Amount: 78 MW
Constraint: NC-N_BERYLSF1
Auto-generated on behalf of Manager NEM Real Time Operations
NON-CONFORMANCE Region SA1 Thursday, 6 February 2025
NON-CONFORMANCE SA1 Region Thursday, 6 February 2025
AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:
Unit: BLYTHB1
Duration: 06/02/2025 13:00 to 06/02/2025 13:05
Amount: -199 MW
Constraint: NC-S_BLYTHB1
Auto-generated on behalf of Manager NEM Real Time Operations
Inter-regional transfer limit variation - Collector - Marulan (4) 330 kV line - NSW region - 06/02/2025
Inter-regional transfer limit variation -Collector - Marulan (4) 330 kV line - NSW region - 06/02/2025
The outage has been completed and Collector - Marulan (4) 330 kV line returned to service at 0825 hrs 06/02/2025
Constraint set(s) revoked: N-CTMN_4_WG_CLOSE
Manager NEM Real Time Operations
NON-CONFORMANCE Region NSW1 Thursday, 6 February 2025
NON-CONFORMANCE NSW1 Region Thursday, 6 February 2025
AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:
Unit: VP5
Duration: 06/02/2025 01:25 to 06/02/2025 04:30
Amount: -44 MW
Constraint: NC-N_VP5
Auto-generated on behalf of Manager NEM Real Time Operations