Update to Victorian system normal Kerang voltage stability limit
AEMO has completed a review of a system normal voltage stability limit in north west Victoria as a result of commissioning of BESS at Koorangie. The revised limit manages pre-contingent flow on the Wemen to Koorangie 220 kV line to avoid voltage collapse at Koorangie, Kerang or Wemen on loss of the Crowlands to Bulgana to Horsham or Horsham to Murra Warra to Kiamal 220 kV line. The revised constraint equation includes the generators in south-west NSW and north-west Victoria on the left-hand side as well as Murraylink and V-SA. Full details on the limits advice are to be published shortly on the AEMO website: https://www.aemo.com.au/energy-systems/electricity/national-electricity-market-nem/system-operations/congestion-information-resource/limits-advice
The revised limit will be implemented at 0900 hrs on Monday 31st March 2025, by updating V^^V_NIL_KGTS.
For full details on the factors this constraint equation has now been loaded into AEMO's pre-production systems.
For further details on this constraint equation please contact terry.liu@aemo.com.au
Terry Liu
AEMO Operations
Non-credible contingency event - TAS region - 26/03/2025
Non-credible contingency event - TAS region - 26/03/2025
At 1551 hrs the Palmerston A 220kV Bus tripped.
AEMO did not instruct load shedding.
AEMO has not been advised of any disconnection of bulk electrical load.
Approximately 40MW of generation was disconnected.
The cause of this non credible contingency event has been identified and AEMO is satisfied that another occurrence of this event is unlikely under the current circumstances.
AEMO will not reclassify this event as a credible contingency event.
Manager NEM Real Time Operations
Cancellation of Actual (LOR1) condition in the NSW region - 16/03/2025
Cancellation of Actual (LOR1) condition in the NSW region - 16/03/2025
The Actual LOR1 Condition in the NSW Region advised in AEMO Electricity Market Notice No.125715 is cancelled at 1915 hrs 16/03/2025.
Manager NEM Real Time Operations
Actual Lack Of Reserve Level 1 (LOR1) in the NSW region - 16/03/2025
Actual Lack Of Reserve Level 1 (LOR1) in the NSW region - 16/03/2025
An Actual LOR1 condition has been declared under clause 4.8.4(b) of the National Electricity Rules for the NSW region from 1700 hrs.
The Actual LOR1 condition is forecast to exist until 1830 hrs
The forecast capacity reserve requirement is 1684 MW.
The minimum capacity reserve available is 1242 MW.
Manager NEM Real Time Operations
PDPASA - Update of the Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 16/03/2025
The Forecast LOR1 condition in the NSW region advised in AEMO Electricity Market Notice No. 125700 has been updated at1415 hrs to the following:
[1.] From 1700 hrs 16/03/2025 to 1930 hrs 16/03/2025.
The forecast capacity reserve requirement is 1720 MW.
The minimum capacity reserve available is 1162 MW.
Manager NEM Real Time Operations
PDPASA - Cancellation of the Forecast Lack Of Reserve Level 2 (LOR2) in the NSW Region on 16/03/2025
The Forecast LOR2 condition in the NSW region advised in AEMO Electricity Market Notice No. 125699 is cancelled at 1415 hrs.
Manager NEM Real Time Operations
Non-credible contingency event - QLD region - 16/03/2025
Non-credible contingency event - QLD region - 16/03/2025
At 1131 hrs the H35 Strathmore 132 kV No 2 bus tripped. Whitsunday Solar farm and Hamilton Solar farm were disconnected.
AEMO did not instruct load shedding.
The cause of this non credible contingency event is not known at this stage.
Manager NEM Real Time Operations
PDPASA - Update of the Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 16/03/2025
The Forecast LOR1 condition in the NSW region advised in AEMO Electricity Market Notice No. 125698 has been updated at1045 hrs to the following:
[1.] From 1600 hrs 16/03/2025 to 1700 hrs 16/03/2025.
The forecast capacity reserve requirement is 1370 MW.
The minimum capacity reserve available is 725 MW.
[2.] From 1830 hrs 16/03/2025 to 2000 hrs 16/03/2025.
The forecast capacity reserve requirement is 1817 MW.
The minimum capacity reserve available is 1159 MW.
Manager NEM Real Time Operations
PDPASA - Update of the Forecast Lack Of Reserve Level 2 (LOR2) in the NSW Region on 16/03/2025
The Forecast LOR2 condition in the NSW region advised in AEMO Electricity Market Notice No. 125697 has been updated at 1045 hrs to the following:
From 1700 hrs 16/03/2025 to 1830 hrs 16/03/2025.
The forecast capacity reserve requirement is 730 MW.
The minimum capacity reserve available is 656 MW.
AEMO is seeking a market response.
AEMO has not yet estimated the latest time it would need to intervene through an AEMO intervention event.
Manager NEM Real Time Operations