Update - Non-credible contingency event - TAS region - 03/02/2025
Update - Non-credible contingency event - TAS region - 03/02/2025
Refer AEMO Electricity Market Notice 124043
The cause of this non credible contingency event is not known at this stage.
AEMO is not satisfied that this non credible event is unlikely to re-occur.
AEMO has therefore reclassified this event as a credible contingency event until further notice.
Region: TAS
Elements: Farrell - Reece No.1 and No.2 220 kV lines
Duration: 1410 hrs 03/02/2025 until further notice
Constraint set(s) invoked: F-T-FARE_N-2
Manager NEM Real Time Operations
Non-credible contingency event - TAS region - 03/02/2025
Non-credible contingency event - TAS region - 03/02/2025
At 1333 hrs the Farrell - Reece No.1 and No.2 220 kV lines tripped.
AEMO did not instruct load shedding.
AEMO has not been advised of any disconnection of bulk electrical load.
The cause of this non credible contingency event has been identified and AEMO is satisfied that another occurrence of this event is unlikely under the current circumstances.
The cause of this non credible contingency event is not known at this stage.
Manager NEM Real Time Operations
NON-CONFORMANCE Region NSW1 Monday, 3 February 2025
NON-CONFORMANCE NSW1 Region Monday, 3 February 2025
AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:
Unit: WTAHB1
Duration: 03/02/2025 10:35 to 03/02/2025 10:40
Amount: -132 MW
Constraint: NC-N_WTAHB1
Auto-generated on behalf of Manager NEM Real Time Operations
CHG0100610 | Completed | Production | Planned Maintenance to Brisbane Internet Router
Notification issued to: Market Notice
Notification Type: Completed
Change Type: Normal
Service/Component: Internet Access
Change Title: Planned Maintenance to Brisbane Internet Router
Support Information: Report any impacts to the AEMO Information and Support Hub or on External 1300 236 600.
[EventId:202502011830_NRM_VIC1_SA1_stopped] NEGRES CONSTRAINT NRM_VIC1_SA1 ceased operating from 01 February 2025 18:30
Issued by Australian Energy Market Operator Ltd at 1830 hrs on 1 February 2025
CANCELLATION - ACTUAL NEGATIVE SETTLEMENT RESIDUES - VIC to SA - 1 February 2025.
Refer to market notice: 123990
AEMO has ceased taking action to minimize the further accumulation of negative settlement residues on the VIC to SA directional interconnector.
The negative residue constraint NRM_VIC1_SA1 ceased operating at 1830 hrs on 1 February 2025.
This is an AEMO autogenerated Market Notice.
[EventId:202502011700_NRM_VIC1_SA1_started] NEGRES CONSTRAINT NRM_VIC1_SA1 started operating from 01 February 2025 17:00
Issued by Australian Energy Market Operator Ltd at 1700 hrs on 1 February 2025
ACTUAL NEGATIVE SETTLEMENT RESIDUES - VIC to SA - 1 February 2025.
Electricity Market outcomes have resulted in the accumulation of negative settlement residues that have exceeded the allowable negative residue threshold for the VIC to SA directional interconnector.
The negative residue constraint set NRM_VIC1_SA1 commenced operating from 1700 hrs on 1 February 2025.
This constraint set contains an equation with the following interconnectors on the LHS:
V-S-MNSP1
V-SA
The RHS of the constraint equation may be adjusted to manage residues.
This is an AEMO autogenerated Market Notice.
CHG0101137 | Production | Planned Maintenance to Norwest Marketnet Site to Site VPN Router
Notification issued to: Market Notice
Notification Type: Initial
Change Type: Normal
Service/ Component: Local Area Network
Change Title: Planned Maintenance to Norwest Marketnet Site to Site VPN Router
Change Start Date & Time: 04/02/2025 11:00:00 AEST
Change End Date & Time: 04/02/2025 15:00:00 AEST
Outage Start Date & Time:
Outage End Date & Time:
Environment: Production
Participant Impact and Requirements: The following impacts are expected to participant connectivity during this planned maintenance:
IPWAN Participants - Nil
Lan-2-Lan VPN Participants (IPSEC) - Nil
B2B VPN - Nil
SSL VPN Participants: Nil
GASHUB: Nil
Other Impacts will have been communicated in advance.
Support Information:
Report any impacts to the AEMO Information and Support Hub or call 1300 236 600.
Please refer to https://aemo.service-now.com/participantportal?id=pp_services_status for any
planned/unplanned maintenance activities .
NON-CONFORMANCE Region NSW1 Friday, 31 January 2025
NON-CONFORMANCE NSW1 Region Friday, 31 January 2025
AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:
Unit: WTAHB1
Duration: 31/01/2025 11:05 to 31/01/2025 11:30
Amount: -226 MW
Constraint: NC-N_WTAHB1
Auto-generated on behalf of Manager NEM Real Time Operations
[EventId:202501301330_NRM_NSW1_VIC1_stopped] NEGRES CONSTRAINT NRM_NSW1_VIC1 ceased operating from 30 January 2025 13:30
Issued by Australian Energy Market Operator Ltd at 1330 hrs on 30 January 2025
CANCELLATION - ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 30 January 2025.
Refer to market notice: 123921
AEMO has ceased taking action to minimize the further accumulation of negative settlement residues on the NSW to VIC directional interconnector.
The negative residue constraint NRM_NSW1_VIC1 ceased operating at 1330 hrs on 30 January 2025.
This is an AEMO autogenerated Market Notice.