Filter by category
Filter by Date
PDPASA - Cancellation of the Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region [beginning] on 18/11/2024
The Forecast LOR1 condition in the NSW region advised in AEMO Electricity Market Notice No. 120618 is cancelled at 1822 hrs 18/11/2024.
Manager NEM Real Time Operations
NON-CONFORMANCE Region NSW1 Monday, 18 November 2024
NON-CONFORMANCE NSW1 Region Monday, 18 November 2024
AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:
Unit: WTAHB1
Duration: 18/11/2024 17:25 to 18/11/2024 17:40
Amount: -13 MW
Constraint: NC-N_WTAHB1
Auto-generated on behalf of Manager NEM Real Time Operations
PDPASA - Cancellation of the Forecast Lack Of Reserve Level 1 (LOR1) in the QLD Region beginning on 18/11/2024
The Forecast LOR1 condition in the QLD region advised in AEMO Electricity Market Notice No. 120611 is cancelled at 1630 hrs 18/11/2024.
Manager NEM Real Time Operations
PDPASA - Update of the Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 18/11/2024
The Forecast LOR1 condition in the NSW region advised in AEMO Electricity Market Notice No. 120608 has been updated at 1600 hrs to the following:
[1.] From 1800 hrs 18/11/2024 to 2000 hrs 18/11/2024.
The forecast capacity reserve requirement is 1450 MW.
The minimum capacity reserve available is 1002 MW.
Manager NEM Real Time Operations
Inter-regional transfer limit variation - Southpine - Rocklea 809 275 kV Line - QLD region - 18/11/2024
Inter-regional transfer limit variation - Southpine - Rocklea 809 275 kV Line - QLD region - 18/11/2024
At 1545 hrs 18/11/2024 there was an unplanned outage of Southpine - Rocklea 809 275 kV Line.
The following constraint set(s) invoked at 1545 hrs 18/11/2024
Q-RLSP_809
This constraint set(s) contains equations with the following interconnectors on the LHS.
N-Q-MNSP1,NSW1-QLD1
Refer to the AEMO Network Outage Scheduler for further information.
Manager NEM Real Time Operations
STPASA - Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 25/11/2024
AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the NSW region for the following period:
From 1630 hrs to 1930 hrs 25/11/2024.
The forecast capacity reserve requirement is 1400 MW.
The minimum capacity reserve available is 862 MW.
AEMO Operations
PDPASA - Forecast Lack Of Reserve Level 1 (LOR1) in the QLD Region on 18/11/2024
AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the QLD region for the following Period:
[1.] From 1830 hrs 18/11/2024 to 1900 hrs 18/11/2024.
The forecast capacity reserve requirement is 1124 MW.
The minimum capacity reserve available is 1099 MW.
Manager NEM Real Time Operations
PDPASA - Cancellation of the Forecast Lack Of Reserve Level 1 (LOR1) in the QLD Region [beginning] on 18/11/2024
The Forecast LOR1 condition in the QLD region advised in AEMO Electricity Market Notice No. 120595 is cancelled at 1200 hrs 18/11/2024.
Manager NEM Real Time Operations
PDPASA - Update of the Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 18/11/2024
The Forecast LOR1 condition in the NSW region advised in AEMO Electricity Market Notice No. 120593 has been updated at 0930 hrs to the following:
[1.] From 1800 hrs 18/11/2024 to 1930 hrs 18/11/2024.
The forecast capacity reserve requirement is 1450 MW.
The minimum capacity reserve available is 1202 MW.
Manager NEM Real Time Operations