120674RESERVE NOTICE19/11/2024 03:27:06 PM

STPASA - Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 26/11/2024

AEMO ELECTRICITY MARKET NOTICE

AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the NSW region for the following period:

1. From 1230 hrs to 1430 hrs 26/11/2024.
The forecast capacity reserve requirement is 1400 MW.
The minimum capacity reserve available is 891 MW.

2. From 2030 hrs to 2330 hrs 26/11/2024.
The forecast capacity reserve requirement is 1400 MW.
The minimum capacity reserve available is 700 MW.

AEMO Operations
     
120673RESERVE NOTICE19/11/2024 03:28:04 PM

STPASA - Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 24/11/2024

AEMO ELECTRICITY MARKET NOTICE

AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the NSW region for the following period:

From 1730 hrs to 1900 hrs 24/11/2024.
The forecast capacity reserve requirement is 1400 MW.
The minimum capacity reserve available is 1259 MW.

AEMO Operations
     
120654NON-CONFORMANCE19/11/2024 10:50:22 AM

NON-CONFORMANCE Region NSW1 Tuesday, 19 November 2024

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE NSW1 Region Tuesday, 19 November 2024

AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:

Unit: AVLSF1
Duration: 19/11/2024 10:40 to 19/11/2024 10:50
Amount: 19 MW
Constraint: NC-N_AVLSF1

Auto-generated on behalf of Manager NEM Real Time Operations
     
120637RESERVE NOTICE18/11/2024 06:26:28 PM

PDPASA - Cancellation of the Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region [beginning] on 18/11/2024

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR1 condition in the NSW region advised in AEMO Electricity Market Notice No. 120618 is cancelled at 1822 hrs 18/11/2024.

Manager NEM Real Time Operations
     
120636MARKET INTERVENTION18/11/2024 06:24:54 PM

Cancellation: Direction issued to: Synergen Power Pty Limited - MINTARO MINTARO GAS

AEMO ELECTRICITY MARKET NOTICE

Cancellation: Direction issued to: Synergen Power Pty Limited - MINTARO MINTARO GAS

Refer to Market Notice 120609

Direction is cancelled from: 1830 hrs 18/11/2024

Manager NEM Real Time Operations
     
120635NON-CONFORMANCE18/11/2024 05:40:14 PM

NON-CONFORMANCE Region NSW1 Monday, 18 November 2024

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE NSW1 Region Monday, 18 November 2024

AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:

Unit: WTAHB1
Duration: 18/11/2024 17:25 to 18/11/2024 17:40
Amount: -13 MW
Constraint: NC-N_WTAHB1

Auto-generated on behalf of Manager NEM Real Time Operations
     
120634RESERVE NOTICE18/11/2024 04:48:39 PM

PDPASA - Cancellation of the Forecast Lack Of Reserve Level 1 (LOR1) in the QLD Region beginning on 18/11/2024

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR1 condition in the QLD region advised in AEMO Electricity Market Notice No. 120611 is cancelled at 1630 hrs 18/11/2024.

Manager NEM Real Time Operations
     
120626MARKET INTERVENTION18/11/2024 04:33:11 PM

Update Direction - AGL SA Generation Pty Limited - TORRB3 TORRENS ISLAN

AEMO ELECTRICITY MARKET NOTICE.

Update Direction - AGL SA Generation Pty Limited - TORRB3 TORRENS ISLAN

Refer AEMO Electricity Participant Notice 120553

The TORRB3 TORRENS ISLAN direction is now expected to stay in place until 0400 hrs 20/11/2024.

The direction update is issued at 1630 hrs 18/11/2024.

Manager NEM Real Time Operations
     
120625MARKET INTERVENTION18/11/2024 04:37:54 PM

Direction - SA region to AGL SA Generation Pty Limited - TORRB2 TORRENS ISLAN

AEMO ELECTRICITY MARKET NOTICE

Direction - SA region to AGL SA Generation Pty Limited - TORRB2 TORRENS ISLAN

Refer to Market Notice 120499


In accordance with section 116 of the National Electricity Law, AEMO is issuing a direction to AGL SA Generation Pty Limited. For the purposes of the National Electricity Rules this is a direction under clause 4.8.9(a1)(1).

Direction issued to: AGL SA Generation Pty Limited - TORRB2 TORRENS ISLAN at 1630 hrs 18/11/2024
Type of resource: generating unit
Required actions: Synchronise and follow dispatch targets at 0800 hrs 19/11/2024
Services provided: Voltage Control
Circumstances necessitating the Direction: Voltage
Circumstances necessitating the Direction additional detail: The synchronous generating units currently expected to be synchronised in SA will be inadequate to maintain sufficient Voltage Control in SA. Intervention is required to maintain the power system in a secure operating state
Expected duration: 0400 hrs 20/11/2024 / further notice.

AGL SA Generation Pty Limited does not incur any civil monetary liability for a relevant action taken in accordance with this direction unless the action is taken in bad faith.

Manager NEM Real Time Operations
     
X
Cookies help us improve your website experience.
By using our website, you agree to our use of cookies.
Confirm