Market Notices

124253MARKET INTERVENTION06/02/2025 03:00:02 PM

Direction - SA region 06/02/2025

AEMO ELECTRICITY MARKET NOTICE

Direction - SA region 06/02/2025

In accordance with section 116 of the National Electricity Law, AEMO has issued a direction to a participant in the SA region. For the purposes of the National Electricity Rules this is a direction under clause 4.8.9(a1)(1).

The issue of the direction commences an AEMO intervention event. AEMO declares all trading intervals during the event to be intervention trading intervals, commencing from the interval ending 1505 hrs on 06/02/2025.

Intervention pricing does not apply to this AEMO intervention event.

AEMO may issue or revoke additional directions in order to meet the current requirement, unless sufficient market response is provided. A further market notice will be issued when all directions related to this requirement have been cancelled.


Manager NEM Real Time Operations
     
124250MARKET INTERVENTION06/02/2025 02:19:47 PM

Update - Foreseeable AEMO intervention in SA region

AEMO ELECTRICITY MARKET NOTICE

Update - Foreseeable AEMO intervention in SA region

Refer AEMO Electricity Market Notice 124240

AEMO has identified a foreseeable circumstance that may require an AEMO intervention event in the SA region from 0730 hrs 06/02/2025.

The foreseeable circumstance requiring the need for intervention is Voltage.

AEMO estimates that, in the absence of sufficient market response by 1500 hrs 06/02/2025, AEMO may need to intervene by issuing a direction.

Manager NEM Real Time Operations
     
124245NON-CONFORMANCE06/02/2025 01:19:02 PM

NON-CONFORMANCE Region NSW1 Thursday, 6 February 2025

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE NSW1 Region Thursday, 6 February 2025

AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:

Unit: BERYLSF1
Duration: 06/02/2025 12:35 to 06/02/2025 13:15
Amount: 78 MW
Constraint: NC-N_BERYLSF1

Auto-generated on behalf of Manager NEM Real Time Operations
     
124244MARKET INTERVENTION06/02/2025 01:12:52 PM

Cancellation - AEMO Intervention Event - SA region 06/02/2025

AEMO ELECTRICITY MARKET NOTICE

Cancellation - AEMO Intervention Event - SA region 06/02/2025

Refer to Market Notice 124204

The AEMO Intervention Event and all associated directions are cancelled from 1300 hrs on 06/02/2025.


Manager NEM Real Time Operations
     
124243MARKET INTERVENTION06/02/2025 01:11:26 PM

Cancellation: Direction issued to: Pelican Point Power Limited - PPCCGT PELICAN POINT

AEMO ELECTRICITY MARKET NOTICE

Cancellation: Direction issued to: Pelican Point Power Limited - PPCCGT PELICAN POINT

Refer to Market Notice 124182

Direction is cancelled from: 1300 hrs 06/02/2025

Manager NEM Real Time Operations
     
124242NON-CONFORMANCE06/02/2025 01:05:16 PM

NON-CONFORMANCE Region SA1 Thursday, 6 February 2025

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE SA1 Region Thursday, 6 February 2025

AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:

Unit: BLYTHB1
Duration: 06/02/2025 13:00 to 06/02/2025 13:05
Amount: -199 MW
Constraint: NC-S_BLYTHB1

Auto-generated on behalf of Manager NEM Real Time Operations
     
124240MARKET INTERVENTION06/02/2025 12:48:27 PM

Foreseeable AEMO intervention under clause 4.8.5A (a) of the NER in SA region

AEMO ELECTRICITY MARKET NOTICE

Foreseeable AEMO intervention under clause 4.8.5A (a) of the NER in SA region

AEMO has identified a foreseeable circumstance that may require an AEMO intervention event in the SA region from 0730 hrs 07/02/2025.

The foreseeable circumstance requiring the need for intervention is Voltage.

Manager NEM Real Time Operations
     
124236GENERAL NOTICE06/02/2025 10:41:59 AM

NEM Local Temperature Alerts for SA, VIC from 06 Feb 2025 to 10 Feb 2025

AEMO ELECTRICITY MARKET NOTICE

AEMO's weather service provider has issued forecast temperatures equal to or greater than the NEM Local Temperature Alert Levels for listed weather stations below.

SA
Port Augusta Ap (39+ Deg C): 6th Feb, 10th Feb

VIC
Mildura Ap (39+ Deg C): 6th Feb, 7th Feb

The NEM Local Temperature Alert Levels are:

Launceston Ti Tree Bend: 33 Deg C, Dalby Airport: 37 Deg C, for all other selected weather stations: 39 Deg C.

AEMO requests Market Participants to:

1. review the weather forecast in the local area where their generating units / MNSP converter stations are located and,

2. if required, update the available capacity in their dispatch offers or availability submissions consistent with the forecast temperatures.

Further information is available at:

https://aemo.com.au/energy-systems/electricity/national-electricity-market-nem/nem-forecasting-and-planning/forecasting-and-reliability/projected-assessment-of-system-adequacy/nem-local-temperature-alerts

AEMO Operations Planning
     
124233RESERVE NOTICE06/02/2025 08:47:41 AM

PDPASA - Cancellation of the Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 06/02/2025

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR1 condition in the NSW region advised in AEMO Electricity Market Notice No. 124225 is cancelled at 0840 hrs 06/02/2025.

Manager NEM Real Time Operations
     
X
Cookies help us improve your website experience.
By using our website, you agree to our use of cookies.
Confirm