NON-CONFORMANCE Region NSW1 Friday, 10 January 2025
NON-CONFORMANCE NSW1 Region Friday, 10 January 2025
AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:
Unit: VP6
Duration: 10/01/2025 05:15 to 10/01/2025 05:25
Amount: -47 MW
Constraint: NC-N_VP6
Auto-generated on behalf of Manager NEM Real Time Operations
Inter-regional transfer limit variation - Armidale-Uralla 8U 330kV Line - NSW region - 09/01/2025
Inter-regional transfer limit variation - Armidale-Uralla 8U 330kV Line - NSW region - 09/01/2025
A planned outage of Armidale-Uralla 8U 330kV Line in the NSW region was scheduled from 0500 hrs 09/01/2025 to 1700 hrs 09/01/2025.
The outage has been completed and Armidale-Uralla 8U 330kV Line returned to service at 1250 hrs 09/01/2025
Constraint set revoked: N-ARUL_8U
Manager NEM Real Time Operations
NON-CONFORMANCE Region QLD1 Thursday, 9 January 2025
NON-CONFORMANCE QLD1 Region Thursday, 9 January 2025
AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:
Unit: KINGASF1
Duration: 09/01/2025 08:15 to 09/01/2025 08:30
Amount: 35 MW
Constraint: NC-Q_KINGASF1
Auto-generated on behalf of Manager NEM Real Time Operations
Inter-regional transfer limit variation - Hummocks - Bungama - Snowtown 132kV Line - SA region - 08/01/2025
Inter-regional transfer limit variation - Hummocks - Bungama - Snowtown 132kV Line - SA region - 08/01/2025
At 1210 hrs 08/01/2025 there was a short notice outage of Hummocks - Bungama - Snowtown 132kV Line.
The following constraint set(s) invoked at 1210 hrs 08/01/2025
S-HUBG
This constraint set(s) contains equations with the following interconnectors on the LHS.
V-S-MNSP1
Refer to the AEMO Network Outage Scheduler for further information.
Manager NEM Real Time Operations
Inter-regional transfer limit variation - constraint automation to manage Power System Security in NSW region - 08/01/2025
In order to maintain the power system in a secure operating state in the NSW region, AEMO has invoked automated constraint set CA_BRIS_56906542 from 1155 hrs until further notice.
This constraint set contains equations with the following interconnector on the LHS;
V-S-MNSP1
VIC1-NSW1
Manager NEM Real Time Operations
NEM Local Temperature Alerts for SA, VIC from 07 Jan 2025 to 11 Jan 2025
AEMO's weather service provider has issued forecast temperatures equal to or greater than the NEM Local Temperature Alert Levels for listed weather stations below.
SA
Port Augusta Ap (39+ Deg C): 11th Jan
VIC
Mildura Ap (39+ Deg C): 11th Jan
The NEM Local Temperature Alert Levels are:
Launceston Ti Tree Bend: 33 Deg C, Dalby Airport: 37 Deg C, for all other selected weather stations: 39 Deg C.
AEMO requests Market Participants to:
1. review the weather forecast in the local area where their generating units / MNSP converter stations are located and,
2. if required, update the available capacity in their dispatch offers or availability submissions consistent with the forecast temperatures.
Further information is available at:
https://aemo.com.au/energy-systems/electricity/national-electricity-market-nem/nem-forecasting-and-planning/forecasting-and-reliability/projected-assessment-of-system-adequacy/nem-local-temperature-alerts
AEMO Operations Planning
Inter-regional transfer limit variation - constraint automation to manage Power System Security in VIC region - 07/01/2025
In order to maintain the power system in a secure operating state in the VIC region, AEMO has invoked automated constraint set CA_BRIS_5687999A from 0330 hrs until further notice.
This constraint set contains equations with the following interconnector on the LHS;
V-S-MNSP1
Refer to AEMO Network Outage Scheduler (NOS) for further information.
Manager NEM Real Time Operations
PDPASA - Cancellation of the Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 06/01/2025
The Forecast LOR1 condition in the NSW region advised in AEMO Electricity Market Notice No. 122896 is cancelled at 1430 hrs 06/01/2025.
Manager NEM Real Time Operations
NEM Local Temperature Alerts for SA from 06 Jan 2025 to 10 Jan 2025
AEMO's weather service provider has issued forecast temperatures equal to or greater than the NEM Local Temperature Alert Levels for listed weather stations below.
SA
Port Augusta Ap (39+ Deg C): 9th Jan, 10th Jan
The NEM Local Temperature Alert Levels are:
Launceston Ti Tree Bend: 33 Deg C, Dalby Airport: 37 Deg C, for all other selected weather stations: 39 Deg C.
AEMO requests Market Participants to:
1. review the weather forecast in the local area where their generating units / MNSP converter stations are located and,
2. if required, update the available capacity in their dispatch offers or availability submissions consistent with the forecast temperatures.
Further information is available at:
https://aemo.com.au/energy-systems/electricity/national-electricity-market-nem/nem-forecasting-and-planning/forecasting-and-reliability/projected-assessment-of-system-adequacy/nem-local-temperature-alerts