Market Notices

122444POWER SYSTEM EVENTS23/12/2024 08:40:02 PM

Update - Non-credible contingency event - SA region - 23/12/2024

AEMO ELECTRICITY MARKET NOTICE.

Update - Non-credible contingency event - SA region - 23/12/2024

Refer AEMO Electricity Market Notice 122442

At 2036 hrs the Happy Valley - Morphett Vale East and the Morphett Vale - Cherry Gardens 275kV lines were returned to service.

The cause of this non-credible contingency event has been identified and AEMO is satisfied that another occurrence of this event is unlikely under the current circumstances.

AEMO will not reclassify this event as a credible contingency event.

Manager NEM Real Time Operations
     
122442POWER SYSTEM EVENTS23/12/2024 04:44:55 PM

Non-credible contingency event - SA region - 23/12/2024

AEMO ELECTRICITY MARKET NOTICE.

Non-credible contingency event - SA region - 23/12/2024

At 1632 hrs the Happy Valley - Morphett Vale East 275kV Line and the Morphett Vale - Cherry Gardens 275kV line tripped.

AEMO did not instruct load shedding.

AEMO has not been advised of any disconnection of bulk electrical load.

The cause of this non credible contingency event is not known at this stage.

Manager NEM Real Time Operations
     
122435NON-CONFORMANCE23/12/2024 09:40:24 AM

NON-CONFORMANCE Region QLD1 Monday, 23 December 2024

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE QLD1 Region Monday, 23 December 2024

AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:

Unit: MPP_2
Duration: 23/12/2024 09:25 to 23/12/2024 09:40
Amount: 36 MW
Constraint: NC-Q_MPP_2

Auto-generated on behalf of Manager NEM Real Time Operations
     
122290NON-CONFORMANCE20/12/2024 03:00:17 AM

NON-CONFORMANCE Region NSW1 Friday, 20 December 2024

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE NSW1 Region Friday, 20 December 2024

AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:

Unit: VP6
Duration: 20/12/2024 02:35 to 20/12/2024 03:00
Amount: -27 MW
Constraint: NC-N_VP6

Auto-generated on behalf of Manager NEM Real Time Operations
     
121994NON-CONFORMANCE16/12/2024 03:30:16 AM

NON-CONFORMANCE Region QLD1 Monday, 16 December 2024

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE QLD1 Region Monday, 16 December 2024

AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:

Unit: MPP_1
Duration: 16/12/2024 02:20 to 16/12/2024 03:30
Amount: -18 MW
Constraint: NC-Q_MPP_1

Auto-generated on behalf of Manager NEM Real Time Operations
     
121993NON-CONFORMANCE16/12/2024 01:50:14 AM

NON-CONFORMANCE Region QLD1 Monday, 16 December 2024

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE QLD1 Region Monday, 16 December 2024

AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:

Unit: MPP_1
Duration: 16/12/2024 01:10 to 16/12/2024 01:50
Amount: -21 MW
Constraint: NC-Q_MPP_1

Auto-generated on behalf of Manager NEM Real Time Operations
     
121941NON-CONFORMANCE15/12/2024 10:55:20 AM

NON-CONFORMANCE Region NSW1 Sunday, 15 December 2024

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE NSW1 Region Sunday, 15 December 2024

AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:

Unit: WTAHB1
Duration: 15/12/2024 10:45 to 15/12/2024 10:55
Amount: 11 MW
Constraint: NC-N_WTAHB1

Auto-generated on behalf of Manager NEM Real Time Operations
     
121940NON-CONFORMANCE15/12/2024 09:10:14 AM

NON-CONFORMANCE Region QLD1 Sunday, 15 December 2024

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE QLD1 Region Sunday, 15 December 2024

AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:

Unit: MPP_2
Duration: 15/12/2024 09:00 to 15/12/2024 09:10
Amount: 11 MW
Constraint: NC-Q_MPP_2

Auto-generated on behalf of Manager NEM Real Time Operations
     
121870NON-CONFORMANCE13/12/2024 04:55:23 PM

NON-CONFORMANCE Region QLD1 Friday, 13 December 2024

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE QLD1 Region Friday, 13 December 2024

AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:

Unit: KAREEYA1
Duration: 13/12/2024 16:50 to 13/12/2024 16:55
Amount: -21 MW
Constraint: NC-Q_KAREEYA1

Auto-generated on behalf of Manager NEM Real Time Operations
     
X
Cookies help us improve your website experience.
By using our website, you agree to our use of cookies.
Confirm