NON-CONFORMANCE Region NSW1 Monday, 10 February 2025
NON-CONFORMANCE NSW1 Region Monday, 10 February 2025
AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:
Unit: GULLRWF2
Duration: 10/02/2025 11:15 to 10/02/2025 14:10
Amount: 13 MW
Constraint: NC-N_GULLRWF2
Auto-generated on behalf of Manager NEM Real Time Operations
[EventId:202502101255_review] Prices for interval 10-Feb-2025 12:55 are subject to review
Issued by Australian Energy Market Operator Ltd at 1250 hrs on 10 February 2025
PRICES ARE SUBJECT TO REVIEW for trading interval 10-Feb-2025 12:55.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
[EventId:202502101250_review] Prices for interval 10-Feb-2025 12:50 are subject to review
Issued by Australian Energy Market Operator Ltd at 1245 hrs on 10 February 2025
PRICES ARE SUBJECT TO REVIEW for trading interval 10-Feb-2025 12:50.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
[EventId:202502101245_review] Prices for interval 10-Feb-2025 12:45 are subject to review
Issued by Australian Energy Market Operator Ltd at 1240 hrs on 10 February 2025
PRICES ARE SUBJECT TO REVIEW for trading interval 10-Feb-2025 12:45.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
[EventId:202502101240_review] Prices for interval 10-Feb-2025 12:40 are subject to review
Issued by Australian Energy Market Operator Ltd at 1235 hrs on 10 February 2025
PRICES ARE SUBJECT TO REVIEW for trading interval 10-Feb-2025 12:40.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
[EventId:202502101235_review] Prices for interval 10-Feb-2025 12:35 are subject to review
Issued by Australian Energy Market Operator Ltd at 1230 hrs on 10 February 2025
PRICES ARE SUBJECT TO REVIEW for trading interval 10-Feb-2025 12:35.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
[EventId:202502101230_review] Prices for interval 10-Feb-2025 12:30 are subject to review
Issued by Australian Energy Market Operator Ltd at 1225 hrs on 10 February 2025
PRICES ARE SUBJECT TO REVIEW for trading interval 10-Feb-2025 12:30.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
Cancellation of Actual (LOR1) condition in the NSW region - 09/02/2025
Cancellation of Actual (LOR1) condition in the NSW region - 09/02/2025
The Actual LOR1 Condition in the NSW Region advised in AEMO Electricity Market Notice No.124399 is cancelled at 1749 hrs 09/02/2025.
Manager NEM Real Time Operations
Actual Lack Of Reserve Level 1 (LOR1) in the NSW region - 09/02/2025
Actual Lack Of Reserve Level 1 (LOR1) in the NSW region - 09/02/2025
An Actual LOR1 condition has been declared under clause 4.8.4(b) of the National Electricity Rules for the NSW region from 1630 hrs.
The Actual LOR1 condition is forecast to exist until 1730 hrs
The capacity reserve requirement is 1320 MW
The minimum capacity reserve available is 1171 MW
Manager NEM Real Time Operations