122499NON-CONFORMANCE27/12/2024 01:15:22 AM

NON-CONFORMANCE Region VIC1 Friday, 27 December 2024

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE VIC1 Region Friday, 27 December 2024

AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:

Unit: LYA3
Duration: 27/12/2024 01:05 to 27/12/2024 01:15
Amount: 28 MW
Constraint: NC-V_LYA3

Auto-generated on behalf of Manager NEM Real Time Operations
     
122496NON-CONFORMANCE26/12/2024 04:20:19 PM

NON-CONFORMANCE Region VIC1 Thursday, 26 December 2024

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE VIC1 Region Thursday, 26 December 2024

AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:

Unit: LYA4
Duration: 26/12/2024 16:00 to 26/12/2024 16:20
Amount: -13 MW
Constraint: NC-V_LYA4

Auto-generated on behalf of Manager NEM Real Time Operations
     
122493NON-CONFORMANCE26/12/2024 03:55:18 PM

NON-CONFORMANCE Region SA1 Thursday, 26 December 2024

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE SA1 Region Thursday, 26 December 2024

AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:

Unit: HPR1
Duration: 26/12/2024 15:50 to 26/12/2024 15:55
Amount: 14 MW
Constraint: NC-S_HPR1

Auto-generated on behalf of Manager NEM Real Time Operations
     
122488NON-CONFORMANCE26/12/2024 01:10:18 PM

NON-CONFORMANCE Region SA1 Thursday, 26 December 2024

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE SA1 Region Thursday, 26 December 2024

AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:

Unit: TBSF1
Duration: 26/12/2024 09:35 to 26/12/2024 13:10
Amount: 17 MW
Constraint: NC-S_TBSF1

Auto-generated on behalf of Manager NEM Real Time Operations
     
122435NON-CONFORMANCE23/12/2024 09:40:24 AM

NON-CONFORMANCE Region QLD1 Monday, 23 December 2024

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE QLD1 Region Monday, 23 December 2024

AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:

Unit: MPP_2
Duration: 23/12/2024 09:25 to 23/12/2024 09:40
Amount: 36 MW
Constraint: NC-Q_MPP_2

Auto-generated on behalf of Manager NEM Real Time Operations
     
122290NON-CONFORMANCE20/12/2024 03:00:17 AM

NON-CONFORMANCE Region NSW1 Friday, 20 December 2024

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE NSW1 Region Friday, 20 December 2024

AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:

Unit: VP6
Duration: 20/12/2024 02:35 to 20/12/2024 03:00
Amount: -27 MW
Constraint: NC-N_VP6

Auto-generated on behalf of Manager NEM Real Time Operations
     
121994NON-CONFORMANCE16/12/2024 03:30:16 AM

NON-CONFORMANCE Region QLD1 Monday, 16 December 2024

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE QLD1 Region Monday, 16 December 2024

AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:

Unit: MPP_1
Duration: 16/12/2024 02:20 to 16/12/2024 03:30
Amount: -18 MW
Constraint: NC-Q_MPP_1

Auto-generated on behalf of Manager NEM Real Time Operations
     
121993NON-CONFORMANCE16/12/2024 01:50:14 AM

NON-CONFORMANCE Region QLD1 Monday, 16 December 2024

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE QLD1 Region Monday, 16 December 2024

AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:

Unit: MPP_1
Duration: 16/12/2024 01:10 to 16/12/2024 01:50
Amount: -21 MW
Constraint: NC-Q_MPP_1

Auto-generated on behalf of Manager NEM Real Time Operations
     
121941NON-CONFORMANCE15/12/2024 10:55:20 AM

NON-CONFORMANCE Region NSW1 Sunday, 15 December 2024

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE NSW1 Region Sunday, 15 December 2024

AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:

Unit: WTAHB1
Duration: 15/12/2024 10:45 to 15/12/2024 10:55
Amount: 11 MW
Constraint: NC-N_WTAHB1

Auto-generated on behalf of Manager NEM Real Time Operations
     