Market Notices

124879NON-CONFORMANCE19/02/2025 12:10:21 PM

NON-CONFORMANCE Region QLD1 Wednesday, 19 February 2025

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE QLD1 Region Wednesday, 19 February 2025

AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:

Unit: MPP_2
Duration: 19/02/2025 11:55 to 19/02/2025 12:10
Amount: -18 MW
Constraint: NC-Q_MPP_2

Auto-generated on behalf of Manager NEM Real Time Operations
     
124872SETTLEMENTS RESIDUE19/02/2025 11:25:40 AM

[EventId:202502191125_NRM_NSW1_VIC1_started] NEGRES CONSTRAINT NRM_NSW1_VIC1 started operating from 19 February 2025 11:25

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1125 hrs on 19 February 2025

ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 19 February 2025.

Electricity Market outcomes have resulted in the accumulation of negative settlement residues that have exceeded the allowable negative residue threshold for the NSW to VIC directional interconnector.

The negative residue constraint set NRM_NSW1_VIC1 commenced operating from 1125 hrs on 19 February 2025.

This constraint set contains an equation with the following interconnectors on the LHS:
VIC1-NSW1

The RHS of the constraint equation may be adjusted to manage residues.


This is an AEMO autogenerated Market Notice.
     
124870PRICES UNCHANGED19/02/2025 10:00:34 AM

[EventId:202502190940_confirmed] Prices for interval 19-Feb-2025 09:40 are now confirmed

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1000 hrs on 19 February 2025

PRICES ARE NOW CONFIRMED for trading interval 19-Feb-2025 09:40.

In accordance with Market Notice 124859 AEMO has reviewed this trading interval and determined that:
- Manifestly Incorrect Inputs did not apply

Prices remain unchanged.


This is an AEMO autogenerated Market Notice.
     
124869PRICES UNCHANGED19/02/2025 10:00:35 AM

[EventId:202502191000_confirmed] Prices for interval 19-Feb-2025 10:00 are now confirmed

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1000 hrs on 19 February 2025

PRICES ARE NOW CONFIRMED for trading interval 19-Feb-2025 10:00.

In accordance with Market Notice 124864 AEMO has reviewed this trading interval and determined that:
- Manifestly Incorrect Inputs did not apply

Prices remain unchanged.


This is an AEMO autogenerated Market Notice.
     
124868PRICES UNCHANGED19/02/2025 10:00:35 AM

[EventId:202502190955_confirmed] Prices for interval 19-Feb-2025 09:55 are now confirmed

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1000 hrs on 19 February 2025

PRICES ARE NOW CONFIRMED for trading interval 19-Feb-2025 09:55.

In accordance with Market Notice 124863 AEMO has reviewed this trading interval and determined that:
- Manifestly Incorrect Inputs did not apply

Prices remain unchanged.


This is an AEMO autogenerated Market Notice.
     
124867PRICES UNCHANGED19/02/2025 10:00:21 AM

[EventId:202502190950_confirmed] Prices for interval 19-Feb-2025 09:50 are now confirmed

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1000 hrs on 19 February 2025

PRICES ARE NOW CONFIRMED for trading interval 19-Feb-2025 09:50.

In accordance with Market Notice 124862 AEMO has reviewed this trading interval and determined that:
- Manifestly Incorrect Inputs did not apply

Prices remain unchanged.


This is an AEMO autogenerated Market Notice.
     
124866PRICES UNCHANGED19/02/2025 10:00:20 AM

[EventId:202502190945_confirmed] Prices for interval 19-Feb-2025 09:45 are now confirmed

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1000 hrs on 19 February 2025

PRICES ARE NOW CONFIRMED for trading interval 19-Feb-2025 09:45.

In accordance with Market Notice 124860 AEMO has reviewed this trading interval and determined that:
- Manifestly Incorrect Inputs did not apply

Prices remain unchanged.


This is an AEMO autogenerated Market Notice.
     
124865PRICES UNCHANGED19/02/2025 10:00:22 AM

[EventId:202502190935_confirmed] Prices for interval 19-Feb-2025 09:35 are now confirmed

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1000 hrs on 19 February 2025

PRICES ARE NOW CONFIRMED for trading interval 19-Feb-2025 09:35.

In accordance with Market Notice 124857 AEMO has reviewed this trading interval and determined that:
- Manifestly Incorrect Inputs did not apply

Prices remain unchanged.


This is an AEMO autogenerated Market Notice.
     
124861SETTLEMENTS RESIDUE19/02/2025 09:40:30 AM

[EventId:202502190940_NRM_VIC1_SA1_started] NEGRES CONSTRAINT NRM_VIC1_SA1 started operating from 19 February 2025 09:40

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 0940 hrs on 19 February 2025

ACTUAL NEGATIVE SETTLEMENT RESIDUES - VIC to SA - 19 February 2025.

Electricity Market outcomes have resulted in the accumulation of negative settlement residues that have exceeded the allowable negative residue threshold for the VIC to SA directional interconnector.

The negative residue constraint set NRM_VIC1_SA1 commenced operating from 0940 hrs on 19 February 2025.

This constraint set contains an equation with the following interconnectors on the LHS:
V-S-MNSP1
V-SA

The RHS of the constraint equation may be adjusted to manage residues.


This is an AEMO autogenerated Market Notice.
     
X
Cookies help us improve your website experience.
By using our website, you agree to our use of cookies.
Confirm