[EventId:202501051520_review] Prices for interval 05-Jan-2025 15:20 are subject to review
Issued by Australian Energy Market Operator Ltd at 1515 hrs on 5 January 2025
PRICES ARE SUBJECT TO REVIEW for trading interval 05-Jan-2025 15:20.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
PDPASA - Forecast Lack Of Reserve Level 2 (LOR2) in the NSW Region on 06/01/2025
AEMO declares a Forecast LOR2 condition under clause 4.8.4(b) of the National Electricity Rules for the NSW region for the following Period:
[1.] From 1700 hrs 06/01/2025 to 1730 hrs 06/01/2025.
The forecast capacity reserve requirement is 1036 MW.
The minimum capacity reserve available is 982 MW.
AEMO is seeking a market response.
AEMO has not yet estimated the latest time at which it would need to intervene through an AEMO intervention event.
Manager NEM Real Time Operations
PDPASA - Update of the Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 06/01/2025
The Forecast LOR1 condition in the NSW region advised in AEMO Electricity Market Notice No. 122853 has been updated to the following:
[1.] From 1530 hrs 06/01/2025 to 1830 hrs 06/01/2025.
The forecast capacity reserve requirement is 1400 MW.
The minimum capacity reserve available is 992 MW.
Manager NEM Real Time Operations
PDPASA - Cancellation of the Forecast Lack Of Reserve Level 2 (LOR2) in the NSW Region on 06/01/2025
The Forecast LOR2 condition in the NSW region advised in AEMO Electricity Market Notice No. 122852 is cancelled at 1345 hrs 05/01/2025.
Manager NEM Real Time Operations
PDPASA - Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 06/01/2025
AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the NSW region for the following Periods:
[1.] From 1530 hrs 06/01/2025 to 1630 hrs 06/01/2025.
The forecast capacity reserve requirement is 1400 MW.
The minimum capacity reserve available is 1044 MW.
[2.] From 1800 hrs 06/01/2025 to 1830 hrs 06/01/2025.
The forecast capacity reserve requirement is 1400 MW.
The minimum capacity reserve available is 1146 MW.
Manager NEM Real Time Operations
PDPASA - Forecast Lack Of Reserve Level 2 (LOR2) in the NSW Region on 06/01/2025
AEMO declares a Forecast LOR2 condition under clause 4.8.4(b) of the National Electricity Rules for the NSW region for the following Period:
[1.] From 1630 hrs 06/01/2025 to 1800 hrs 06/01/2025.
The forecast capacity reserve requirement is 922 MW.
The minimum capacity reserve available is 825 MW.
AEMO is seeking a market response.
AEMO has not yet estimated the latest time at which it would need to intervene through an AEMO intervention event.
Manager NEM Real Time Operations
STPASA - Cancellation of the Forecast Lack Of Reserve Level 2 (LOR2) in the NSW Region on 06/01/2025
The Forecast LOR2 condition in the NSW region advised in AEMO Electricity Market Notice No. 122848 is cancelled at 1225 hrs 05/01/2025.
No LOR2 condition is currently forecast in the STPASA period.
Manager NEM Real Time Operations
STPASA - Update of the Forecast Lack Of Reserve Level 2 (LOR2) in the NSW Region on 06/01/2025
The Forecast LOR2 condition in the NSW region advised in AEMO Electricity Market Notice No. 122847 has been updated at 1030 hrs 05/01/2025 to the following:
[1.] From 1700 hrs 06/01/2025 to 1730 hrs 06/01/2025.
The forecast capacity reserve requirement is 895 MW.
The minimum capacity reserve available is 859 MW.
AEMO is seeking a market response.
AEMO has not yet estimated the latest time it would need to intervene through an AEMO intervention event.
Manager NEM Real Time Operations
STPASA - Update of the Forecast Lack Of Reserve Level 2 (LOR2) in the NSW Region on 06/01/2025
The Forecast LOR2 condition in the NSW region advised in AEMO Electricity Market Notice No. 122846 has been updated at 0830 hrs 05/01/2025 to the following:
From 1600 hrs 06/01/2025 to 1830 hrs 06/01/2025.
The forecast capacity reserve requirement is 1047 MW.
The minimum capacity reserve available is 718 MW.
AEMO is seeking a market response.
AEMO has not yet estimated the latest time it would need to intervene through an AEMO intervention event.
Manager NEM Real Time Operations