123668MARKET SYSTEMS24/01/2025 01:45:37 PM

CHG0100719 | Production | Participant FTP File Server Maintenance

Change Number: CHG0100719
Notification issued to: Market Notice
Notification Type: Initial
Change Type: Normal
Service/ Component: EMMS - Dispatch
Change Title: Participant FTP File Server Maintenance
Change Start Date & Time: 29/01/2025 10:00:00 AEST
Change End Date & Time: 29/01/2025 11:00:00 AEST
Outage Start Date & Time: 29/01/2025 10:15:00 AEST
Outage End Date & Time: 29/01/2025 10:15:30 AEST
Environment: Production
Participant Impact and Requirements: All external participants will be briefly disconnected (up to 30 seconds) and then automatically reconnected.
Support Information:
Report any impacts to the AEMO Information and Support Hub or call 1300 236 600.
Please refer to https://aemo.service-now.com/participantportal?id=pp_services_status for any
planned/unplanned maintenance activities .

     
123646MARKET SYSTEMS24/01/2025 07:21:37 AM

CHG0100766 | Completed | Production | Planned Maintenance to Brisbane ISE Server

Change Number: CHG0100766
Notification issued to: Market Notice
Notification Type: Completed
Change Type: Normal
Service/Component: Local Area Network
Change Title: Planned Maintenance to Brisbane ISE Server
Support Information: Report any impacts to the AEMO Information and Support Hub or on External 1300 236 600.
     
123624MARKET INTERVENTION23/01/2025 02:57:06 PM

Update Direction - AGL SA Generation Pty Limited - TORRB3 TORRENS ISLAN

AEMO ELECTRICITY MARKET NOTICE.

Update Direction - AGL SA Generation Pty Limited - TORRB3 TORRENS ISLAN

Refer to Market Notice 123579

TORRB3 TORRENS ISLAN at 0400 hrs 24/01/2025 to Remain synchronised and follow dispatch targets.

The TORRB3 TORRENS ISLAN direction is now expected to stay in place until 0400 hrs 25/01/2025.

The direction update is issued at 1500 hrs 23/01/2025.

Manager NEM Real Time Operations
     
123623MARKET INTERVENTION23/01/2025 02:55:48 PM

Update Direction - Pelican Point Power Limited - PPCCGT PELICAN POINT

AEMO ELECTRICITY MARKET NOTICE.

Update Direction - Pelican Point Power Limited - PPCCGT PELICAN POINT

Refer to Market Notice 123618

PPCCGT PELICAN POINT at 1800 hrs 23/01/2025 to Remain synchronised and follow dispatch targets.

The PPCCGT PELICAN POINT direction is now expected to stay in place until 1730 hrs 24/01/2025.

The direction update is issued at 1500 hrs 23/01/2025.

Manager NEM Real Time Operations
     
123618MARKET INTERVENTION23/01/2025 08:46:10 AM

Update Direction - Pelican Point Power Limited - PPCCGT PELICAN POINT

AEMO ELECTRICITY MARKET NOTICE.

Update Direction - Pelican Point Power Limited - PPCCGT PELICAN POINT

Refer to Market Notice 123582

PPCCGT PELICAN POINT at 1000 hrs 23/01/2025 to Remain synchronised and follow dispatch targets.

The PPCCGT PELICAN POINT direction is expected to stay in place until 1800 hrs 23/01/2025.

The direction update is issued at 0840 hrs 23/01/2025.

Manager NEM Real Time Operations
     
123582MARKET INTERVENTION22/01/2025 04:01:56 PM

Direction - SA region to Pelican Point Power Limited - PPCCGT PELICAN POINT

AEMO ELECTRICITY MARKET NOTICE

Direction - SA region to Pelican Point Power Limited - PPCCGT PELICAN POINT

Refer to Market Notice 123506


In accordance with section 116 of the National Electricity Law, AEMO is issuing a direction to Pelican Point Power Limited. For the purposes of the National Electricity Rules this is a direction under clause 4.8.9(a1)(1).

Direction issued to: Pelican Point Power Limited - PPCCGT PELICAN POINT at 1600 hrs 22/01/2025
Type of resource: generating unit
Required actions: Remain synchronised and follow dispatch targets at 0900 hrs 23/01/2025
Services provided: Voltage Control
Circumstances necessitating the Direction:Voltage
Circumstances necessitating the Direction additional detail: intervention is required to maintain the power system in a secure operating state
Expected duration: 1800 hrs 23/01/2025 / further notice.

Pelican Point Power Limited does not incur any civil monetary liability for a relevant action taken in accordance with this direction unless the action is taken in bad faith.

Manager NEM Real Time Operations
     
123580MARKET INTERVENTION23/01/2025 03:40:17 AM

Cancellation: Direction issued to: Pelican Point Power Limited - PPCCGT PELICAN POINT

AEMO ELECTRICITY MARKET NOTICE

Cancellation: Direction issued to: Pelican Point Power Limited - PPCCGT PELICAN POINT

Refer to Market Notice 123529

Direction is cancelled from: 0400 hrs 23/01/2025

Manager NEM Real Time Operations
     
123579MARKET INTERVENTION22/01/2025 03:58:22 PM

Update Direction - AGL SA Generation Pty Limited - TORRB3 TORRENS ISLAN

AEMO ELECTRICITY MARKET NOTICE.

Update Direction - AGL SA Generation Pty Limited - TORRB3 TORRENS ISLAN

Refer to Market Notice 123528

TORRB3 TORRENS ISLAN at 0800 hrs 21/01/2025 to Remain synchronised and follow dispatch targets.

The TORRB3 TORRENS ISLAN direction is now expected to stay in place until 0400 hrs 24/01/2025.

The direction update is issued at 1600 hrs 22/01/2025.

Manager NEM Real Time Operations
     
123529MARKET INTERVENTION21/01/2025 04:00:12 PM

Direction - SA region to Pelican Point Power Limited - PPCCGT PELICAN POINT

AEMO ELECTRICITY MARKET NOTICE

Direction - SA region to Pelican Point Power Limited - PPCCGT PELICAN POINT

Refer to Market Notice 123506


In accordance with section 116 of the National Electricity Law, AEMO is issuing a direction to Pelican Point Power Limited. For the purposes of the National Electricity Rules this is a direction under clause 4.8.9(a1)(1).

Direction issued to: Pelican Point Power Limited - PPCCGT PELICAN POINT at 1600 hrs 21/01/2025
Type of resource: generating unit
Required actions: Remain synchronised and follow dispatch targets at 2230 hrs 21/01/2025
Services provided: Voltage Control
Circumstances necessitating the Direction:Voltage
Circumstances necessitating the Direction additional detail: intervention is required to maintain the power system in a secure operating state
Expected duration: 0400 hrs 23/01/2025 / further notice.

Pelican Point Power Limited does not incur any civil monetary liability for a relevant action taken in accordance with this direction unless the action is taken in bad faith.

Manager NEM Real Time Operations
     