NON-CONFORMANCE Region NSW1 Thursday, 6 February 2025
NON-CONFORMANCE NSW1 Region Wednesday, 5 February 2025
AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:
Unit: VP5
Duration: 05/02/2025 23:15 to 06/02/2025 00:25
Amount: -20 MW
Constraint: NC-N_VP5
Auto-generated on behalf of Manager NEM Real Time Operations
Cancellation of Actual (LOR1) condition in the NSW region - 05/02/2025
Cancellation of Actual (LOR1) condition in the NSW region - 05/02/2025
The Actual LOR1 Condition in the NSW Region advised in AEMO Electricity Market Notice No.124200 is cancelled at 2019 hrs 05/02/2025.
Manager NEM Real Time Operations
Actual Lack Of Reserve Level 1 (LOR1) in the NSW region - 05/02/2025
Actual Lack Of Reserve Level 1 (LOR1) in the NSW region - 05/02/2025
An Actual LOR1 condition has been declared under clause 4.8.4(b) of the National Electricity Rules for the NSW region from 1730 hrs.
The Actual LOR1 condition is forecast to exist until 1900 hrs
The capacity reserve requirement is 1430 MW
The minimum capacity reserve available is 1214 MW
Manager NEM Real Time Operations
CHG0100111 | Pre-Production | Pre-Prod eMDM February Maintenance Release
Notification issued to: Market Notice
Notification Type: Initial
Change Type: Normal
Service/ Component: MDM - Meter Data Management_PreProd
Change Title: Pre-Prod eMDM February Maintenance Release
Change Start Date & Time: 11/02/2025 13:00:00 AEST
Change End Date & Time: 11/02/2025 17:00:00 AEST
Outage Start Date & Time: 11/02/2025 13:00:00 AEST
Outage End Date & Time: 11/02/2025 15:00:00 AEST
Environment: Pre-Production
Participant Impact and Requirements: Users will not be able to access MSATS during the outage period.
Meter data processing and RM reports will not be available during the outage period.
User Rights Management (URM) will continue to operate, however the administration screens will not be accessible.
MSATS B2B/B2M Transactions and B2B MSATS Screens will be unavailable during this outage
NMI Discovery will not be available during the outage period.
CDR and CDP will not be available during the outage period.
Support Information:
Report any impacts to the AEMO Information and Support Hub or call 1300 236 600.
Please refer to https://aemo.service-now.com/participantportal?id=pp_services_status for any
planned/unplanned maintenance activities .
Update - Non-credible contingency event - TAS region - 03/02/2025
Update - Non-credible contingency event - TAS region - 03/02/2025
Refer AEMO Electricity Market Notice 124044
The cause of this non-credible contingency event has been identified and AEMO is satisfied that another occurrence of this event is unlikely under the current circumstances.
AEMO will cancel the reclassification of this event as a credible contingency event.
Manager NEM Real Time Operations
Cancellation of Actual (LOR1) condition in the NSW region - 05/02/2025
Cancellation of Actual (LOR1) condition in the NSW region - 05/02/2025
The Actual LOR1 Condition in the NSW Region advised in AEMO Electricity Market Notice No.124176 is cancelled at 1444 hrs 05/02/2025.
Manager NEM Real Time Operations
Actual Lack Of Reserve Level 1 (LOR1) in the NSW region - 05/02/2025
Actual Lack Of Reserve Level 1 (LOR1) in the NSW region - 05/02/2025
An Actual LOR1 condition has been declared under clause 4.8.4(b) of the National Electricity Rules for the NSW region from 1330 hrs.
The Actual LOR1 condition is forecast to exist until 1430 hrs
The capacity reserve requirement is 1320 MW
The minimum capacity reserve available is 1254 MW
Manager NEM Real Time Operations
Cancellation of Actual (LOR1) condition in the NSW region - 04/02/2025
Cancellation of Actual (LOR1) condition in the NSW region - 04/02/2025
The Actual LOR1 Condition in the NSW Region advised in AEMO Electricity Market Notice No.124131 is cancelled at 1930 hrs 04/02/2025.
Manager NEM Real Time Operations
Actual Lack Of Reserve Level 1 (LOR1) in the NSW region - 04/02/2025
Actual Lack Of Reserve Level 1 (LOR1) in the NSW region - 04/02/2025
An Actual LOR1 condition has been declared under clause 4.8.4(b) of the National Electricity Rules for the NSW region from 1730 hrs.
The Actual LOR1 condition is forecast to exist until 1800 hrs
The capacity reserve requirement is 1370 MW
The minimum capacity reserve available is 1161 MW
Manager NEM Real Time Operations