124022RESERVE NOTICE02/02/2025 11:08:04 PM

PDPASA - Forecast Lack Of Reserve Level 2 (LOR2) in the VIC Region on 03/02/2025

AEMO ELECTRICITY MARKET NOTICE

AEMO declares a Forecast LOR2 condition under clause 4.8.4(b) of the National Electricity Rules for the VIC region for the following Period:


[1.] From 1830 hrs 03/02/2025 to 1900 hrs 03/02/2025.
The forecast capacity reserve requirement is 823 MW.
The minimum capacity reserve available is 801 MW.


AEMO is seeking a market response.

AEMO has not yet estimated the latest time at which it would need to intervene through an AEMO intervention event.


Manager NEM Real Time Operations
     
124021RESERVE NOTICE02/02/2025 10:51:15 PM

PDPASA - Forecast Lack Of Reserve Level 2 (LOR2) in the SA Region on 03/02/2025

AEMO ELECTRICITY MARKET NOTICE

AEMO declares a Forecast LOR2 condition under clause 4.8.4(b) of the National Electricity Rules for the SA region for the following Period:


[1.] From 1830 hrs 03/02/2025 to 1930 hrs 03/02/2025.
The forecast capacity reserve requirement is 404 MW.
The minimum capacity reserve available is 333 MW.


AEMO is seeking a market response.

AEMO has not yet estimated the latest time at which it would need to intervene through an AEMO intervention event.


Manager NEM Real Time Operations
     
124020INTER-REGIONAL TRANSFER02/02/2025 10:38:53 PM

Update - Inter-regional transfer limit variation - Ararat to Waubra to Ballarat 220 kV line - VIC region - 02/02/2025

AEMO ELECTRICITY MARKET NOTICE

Inter-regional transfer limit variation - Ararat to Waubra to Ballarat 220 kV line - VIC region - 02/02/2025

At 2138 hrs 02/02/2025 there was an unplanned outage of Ararat to Waubra to Ballarat 220 kV line.

The following constraint set(s) invoked at 2150 hrs 02/02/2025
V-AR_WB_BA

The following constraint set(s) invoked at 2230 hrs 02/02/2025
V-KIAMAL_SC_220CB

This constraint set(s) contains equations with the following interconnectors on the LHS.
V-S-MNSP1,T-V-MNSP1,V-SA,VIC1-NSW1

Refer to the AEMO Network Outage Scheduler for further information.

Manager NEM Real Time Operations
     
124017INTER-REGIONAL TRANSFER02/02/2025 10:04:02 PM

Inter-regional transfer limit variation - Ararat to Waubra to Ballarat 220 kV line - VIC region - 02/02/2025

AEMO ELECTRICITY MARKET NOTICE

Inter-regional transfer limit variation - Ararat to Waubra to Ballarat 220 kV line - VIC region - 02/02/2025

At 2138 hrs 02/02/2025 there was an unplanned outage of Ararat to Waubra to Ballarat 220 kV line.

The following constraint set(s) invoked at 2150 hrs 02/02/2025
V-AR_WB_BA

This constraint set(s) contains equations with the following interconnectors on the LHS.
V-S-MNSP1,T-V-MNSP1,V-SA,VIC1-NSW1

Refer to the AEMO Network Outage Scheduler for further information.

Manager NEM Real Time Operations
     
123980INTER-REGIONAL TRANSFER01/02/2025 08:53:03 AM

Inter-regional transfer limit variation - Armidale - Tamworth No. 86 330 kV Line - NSW region - 01/02/2025

AEMO ELECTRICITY MARKET NOTICE

Inter-regional transfer limit variation - Armidale - Tamworth No. 86 330 kV Line - NSW region - 01/02/2025

A planned outage of Armidale - Tamworth No. 86 330 kV Line in the NSW region was scheduled to be completed at 1030 hrs 01/02/2025

The outage has been completed by 0835 hrs 01/02/2025

Constraint set(s) invoked:
N-ARTW_86
N-DM_SVC
N-TW_SVC


This constraint set(s) contains equations with the following interconnectors on the LHS.
N-Q-MNSP1
NSW1-QLD1
T-V-MNSP1

Refer to the AEMO Network Outage Scheduler for further information.

Manager NEM Real Time Operations
     
123961MARKET SYSTEMS31/01/2025 02:09:43 PM

CHG0101137 | Production | Planned Maintenance to Norwest Marketnet Site to Site VPN Router

Change Number: CHG0101137

Notification issued to: Market Notice

Notification Type: Initial

Change Type: Normal

Service/ Component: Local Area Network

Change Title: Planned Maintenance to Norwest Marketnet Site to Site VPN Router

Change Start Date & Time: 04/02/2025 11:00:00 AEST
Change End Date & Time: 04/02/2025 15:00:00 AEST
Outage Start Date & Time:
Outage End Date & Time:

Environment: Production

Participant Impact and Requirements: The following impacts are expected to participant connectivity during this planned maintenance:

IPWAN Participants - Nil

Lan-2-Lan VPN Participants (IPSEC) - Nil

B2B VPN - Nil

SSL VPN Participants: Nil

GASHUB: Nil

Other Impacts will have been communicated in advance.

Support Information:
Report any impacts to the AEMO Information and Support Hub or call 1300 236 600.
Please refer to https://aemo.service-now.com/participantportal?id=pp_services_status for any
planned/unplanned maintenance activities .
     
123949PRICES UNCHANGED30/01/2025 07:12:37 PM

[EventId:202501301815_confirmed] Prices for interval 30-Jan-2025 18:15 are now confirmed

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1835 hrs on 30 January 2025

PRICES ARE NOW CONFIRMED for trading interval 30-Jan-2025 18:15.

In accordance with Market Notice 123939 AEMO has reviewed this trading interval and determined that:
- Manifestly Incorrect Inputs did not apply

Prices remain unchanged.


This is an AEMO autogenerated Market Notice.
     
123948PRICES UNCHANGED30/01/2025 07:06:46 PM

[EventId:202501301835_confirmed] Prices for interval 30-Jan-2025 18:35 are now confirmed

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1835 hrs on 30 January 2025

PRICES ARE NOW CONFIRMED for trading interval 30-Jan-2025 18:35.

In accordance with Market Notice 123943 AEMO has reviewed this trading interval and determined that:
- Manifestly Incorrect Inputs did not apply

Prices remain unchanged.


This is an AEMO autogenerated Market Notice.
     
123947PRICES UNCHANGED30/01/2025 07:00:52 PM

[EventId:202501301830_confirmed] Prices for interval 30-Jan-2025 18:30 are now confirmed

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1835 hrs on 30 January 2025

PRICES ARE NOW CONFIRMED for trading interval 30-Jan-2025 18:30.

In accordance with Market Notice 123942 AEMO has reviewed this trading interval and determined that:
- Manifestly Incorrect Inputs did not apply

Prices remain unchanged.


This is an AEMO autogenerated Market Notice.
     