Filter by category
Filter by Date
Update Direction - AGL SA Generation Pty Limited - TORRB3 TORRENS ISLAN
Update Direction - AGL SA Generation Pty Limited - TORRB3 TORRENS ISLAN
Refer to Market Notice 123624
TORRB3 TORRENS ISLAN at 0400 hrs 25/01/2025 to Remain synchronised and follow dispatch targets.
The TORRB3 TORRENS ISLAN direction is now expected to stay in place until 0400 hrs 26/01/2025.
The direction update is issued at 1600 hrs 24/01/2025.
Manager NEM Real Time Operations
CHG0100610 | Production | Planned Maintenance to Brisbane Internet Router
Notification issued to: Market Notice
Notification Type: Initial
Change Type: Normal
Service/ Component: Internet Access
Change Title: Planned Maintenance to Brisbane Internet Router
Change Start Date & Time: 01/02/2025 11:00:57 AEST
Change End Date & Time: 01/02/2025 13:00:57 AEST
Outage Start Date & Time: 01/02/2025 11:00:31 AEST
Outage End Date & Time: 01/02/2025 13:00:31 AEST
Environment: Production
Participant Impact and Requirements: The following impacts are expected to participant connectivity during this planned outage:
IPWAN Participants - Nil
Lan-2-Lan VPN Participants (IPSEC) - Up to 1 Hour outage for participants who have established their VPN connection/s via the AEMO QLD datacenter termination point (202.44.76.10 for Policy Based VPN and 202.44.76.12 for Route Based VPN) only - All L2L connections should be established to both QLD / NSW.
B2B VPN - Up to 1 hour outage to TNSPs with B2B VPN to AEMO QLD Datacentre if VPN connection is only terminating in QLD only.
SSL VPN Participants: None expected as DNS entry will be updated to remove QLD IP.
GASHUB: Nil
Note: Participants are encouraged to ensure their VPN connections are already established or are configured (as per AEMO best practice) to automatically failover to the alternate AEMO NSW datacenter termination point 202.44.78.10 for Policy Based VPN and 202.44.78.12 for Route Based VPN) prior to this scheduled outage.
*** Failure to do so will impact connectivity to Marketnet Services. ***
Other Impacts will have been communicated in advance.
Support Information:
Report any impacts to the AEMO Information and Support Hub or call 1300 236 600.
Please refer to https://aemo.service-now.com/participantportal?id=pp_services_status for any
planned/unplanned maintenance activities .
CHG0100719 | Production | Participant FTP File Server Maintenance
Notification issued to: Market Notice
Notification Type: Initial
Change Type: Normal
Service/ Component: EMMS - Dispatch
Change Title: Participant FTP File Server Maintenance
Change Start Date & Time: 29/01/2025 10:00:00 AEST
Change End Date & Time: 29/01/2025 11:00:00 AEST
Outage Start Date & Time: 29/01/2025 10:15:00 AEST
Outage End Date & Time: 29/01/2025 10:15:30 AEST
Environment: Production
Participant Impact and Requirements: All external participants will be briefly disconnected (up to 30 seconds) and then automatically reconnected.
Support Information:
Report any impacts to the AEMO Information and Support Hub or call 1300 236 600.
Please refer to https://aemo.service-now.com/participantportal?id=pp_services_status for any
planned/unplanned maintenance activities .
[EventId:202501241110_confirmed] Prices for interval 24-Jan-2025 11:10 are now confirmed
Issued by Australian Energy Market Operator Ltd at 1130 hrs on 24 January 2025
PRICES ARE NOW CONFIRMED for trading interval 24-Jan-2025 11:10.
In accordance with Market Notice 123653 AEMO has reviewed this trading interval and determined that:
- Manifestly Incorrect Inputs did not apply
Prices remain unchanged.
This is an AEMO autogenerated Market Notice.
[EventId:202501241130_confirmed] Prices for interval 24-Jan-2025 11:30 are now confirmed
Issued by Australian Energy Market Operator Ltd at 1130 hrs on 24 January 2025
PRICES ARE NOW CONFIRMED for trading interval 24-Jan-2025 11:30.
In accordance with Market Notice 123658 AEMO has reviewed this trading interval and determined that:
- Manifestly Incorrect Inputs did not apply
Prices remain unchanged.
This is an AEMO autogenerated Market Notice.
[EventId:202501241125_confirmed] Prices for interval 24-Jan-2025 11:25 are now confirmed
Issued by Australian Energy Market Operator Ltd at 1130 hrs on 24 January 2025
PRICES ARE NOW CONFIRMED for trading interval 24-Jan-2025 11:25.
In accordance with Market Notice 123657 AEMO has reviewed this trading interval and determined that:
- Manifestly Incorrect Inputs did not apply
Prices remain unchanged.
This is an AEMO autogenerated Market Notice.
[EventId:202501241120_confirmed] Prices for interval 24-Jan-2025 11:20 are now confirmed
Issued by Australian Energy Market Operator Ltd at 1130 hrs on 24 January 2025
PRICES ARE NOW CONFIRMED for trading interval 24-Jan-2025 11:20.
In accordance with Market Notice 123656 AEMO has reviewed this trading interval and determined that:
- Manifestly Incorrect Inputs did not apply
Prices remain unchanged.
This is an AEMO autogenerated Market Notice.
[EventId:202501241115_confirmed] Prices for interval 24-Jan-2025 11:15 are now confirmed
Issued by Australian Energy Market Operator Ltd at 1130 hrs on 24 January 2025
PRICES ARE NOW CONFIRMED for trading interval 24-Jan-2025 11:15.
In accordance with Market Notice 123655 AEMO has reviewed this trading interval and determined that:
- Manifestly Incorrect Inputs did not apply
Prices remain unchanged.
This is an AEMO autogenerated Market Notice.
[EventId:202501241105_confirmed] Prices for interval 24-Jan-2025 11:05 are now confirmed
Issued by Australian Energy Market Operator Ltd at 1130 hrs on 24 January 2025
PRICES ARE NOW CONFIRMED for trading interval 24-Jan-2025 11:05.
In accordance with Market Notice 123651 AEMO has reviewed this trading interval and determined that:
- Manifestly Incorrect Inputs did not apply
Prices remain unchanged.
This is an AEMO autogenerated Market Notice.