122705GENERAL NOTICE02/01/2025 10:38:18 AM

NEM Local Temperature Alerts for SA, VIC from 02 Jan 2025 to 06 Jan 2025

AEMO ELECTRICITY MARKET NOTICE

AEMO's weather service provider has issued forecast temperatures equal to or greater than the NEM Local Temperature Alert Levels for listed weather stations below.

SA
Clare High School (39+ Deg C): 4th Jan
Port Augusta Ap (39+ Deg C): 3rd Jan, 4th Jan, 5th Jan

VIC
Ararat Prison (39+ Deg C): 4th Jan
Mildura Ap (39+ Deg C): 4th Jan, 5th Jan

The NEM Local Temperature Alert Levels are:

Launceston Ti Tree Bend: 33 Deg C, Dalby Airport: 37 Deg C, for all other selected weather stations: 39 Deg C.

AEMO requests Market Participants to:

1. review the weather forecast in the local area where their generating units / MNSP converter stations are located and,

2. if required, update the available capacity in their dispatch offers or availability submissions consistent with the forecast temperatures.

Further information is available at:

https://aemo.com.au/energy-systems/electricity/national-electricity-market-nem/nem-forecasting-and-planning/forecasting-and-reliability/projected-assessment-of-system-adequacy/nem-local-temperature-alerts

AEMO Operations Planning
     
122697RESERVE NOTICE02/01/2025 06:51:33 AM

STPASA - Update of the Forecast Lack Of Reserve Level 2 (LOR2) in the NSW Region on 06/01/2025

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR2 condition in the NSW region advised in AEMO Electricity Market Notice No. 122695 has been updated at 0645 hrs 02/01/2025 to the following:

From 1500 hrs 06/01/2025 to 1830 hrs 06/01/2025.
The forecast capacity reserve requirement is 700 MW.
The minimum capacity reserve available is 103 MW.

AEMO is seeking a market response.

AEMO has not yet estimated the latest time it would need to intervene through an AEMO intervention event.

Manager NEM Real Time Operations
     
122695RESERVE NOTICE02/01/2025 04:28:27 AM

STPASA - Forecast Lack Of Reserve Level 2 (LOR2) in the NSW Region on 06/01/2025

AEMO ELECTRICITY MARKET NOTICE

AEMO declares a Forecast LOR2 condition under clause 4.8.4(b) of the National Electricity Rules for the NSW region for the following period[s]:

[1.] From 1600 hrs 06/01/2025 to 1700 hrs 06/01/2025.
The forecast capacity reserve requirement is 700 MW.
The minimum capacity reserve available is 509 MW.

AEMO is seeking a market response.

AEMO has not yet estimated the latest time it would need to intervene through an AEMO intervention event.

Manager NEM Real Time Operations
     
122666MARKET INTERVENTION01/01/2025 03:56:53 PM

Update Direction - Pelican Point Power Limited - PPCCGT PELICAN POINT

AEMO ELECTRICITY MARKET NOTICE.

Update Direction - Pelican Point Power Limited - PPCCGT PELICAN POINT

Refer to Market Notice 122631


The PPCCGT PELICAN POINT direction is now expected to stay in place until 0400 hrs 03/01/2025.

The direction update is issued at 1600 hrs 01/01/2025.

Manager NEM Real Time Operations
     
122665MARKET INTERVENTION01/01/2025 03:55:31 PM

Update Direction - AGL SA Generation Pty Limited - TORRB3 TORRENS ISLAN

AEMO ELECTRICITY MARKET NOTICE.

Update Direction - AGL SA Generation Pty Limited - TORRB3 TORRENS ISLAN

Refer to Market Notice 122630

The TORRB3 TORRENS ISLAN direction is now expected to stay in place until 0400 hrs 03/01/2025.

The direction update is issued at 1600 hrs 01/01/2025.

Manager NEM Real Time Operations
     
122663MINIMUM SYSTEM LOAD01/01/2025 02:06:40 PM

Cancellation of Actual Minimum System Load (MSL) MSL1 event in the VIC Region on 01/01/2025.

AEMO ELECTRICITY MARKET NOTICE

Cancellation of Actual Minimum System Load (MSL) MSL1 event in the VIC Region on 01/01/2025.

Cancellation - Actual MSL1- VIC Region at 1400 hrs 01/01/2025.

Refer to Market Notice 122654 for MSL1.

Manager NEM Real Time Operations
     
122654MINIMUM SYSTEM LOAD01/01/2025 11:56:13 AM

Actual Minimum System Load MSL1 condition in the VIC Region on 01/01/2025

AEMO ELECTRICITY MARKET NOTICE
Actual Minimum System Load MSL1 condition in the VIC Region on 01/01/2025

Update to Market Notice 122653 - AEMO has detected that there is an elevated risk of insufficient demand to maintain a secure operating state in the VIC on 01/01/2025.

Minimum regional demand is forecast to be 1398 MW at 1300 hrs, and the advisory threshold is:
- MSL1 - 1535 MW
- MSL2 - 1035 MW
- MSL3 - 535 MW

The regional demand is below the MSL1 threshold. The actual MSL1 condition is forecast to exist until 1400 hrs.

Manager NEM Real Time Operations
     
122653MINIMUM SYSTEM LOAD01/01/2025 09:43:04 AM

Forecast Minimum System Load MSL1 condition in the VIC Region on 01/01/2025

AEMO ELECTRICITY MARKET NOTICE
Forecast Minimum System Load MSL1 condition in the VIC Region on 01/01/2025

Update to Market Notice 122635
AEMO has detected that there is an elevated risk of insufficient demand to maintain a secure operating state in the VIC on 01/01/2025.

Minimum System Load (MSL) conditions are forecast when regional demand is less than the relevant MSL threshold. The advisory MSL thresholds are:
- MSL1 - 1560 MW
- MSL2 - 1060 MW
- MSL3 - 560 MW

The regional demand is forecast to be below the MSL1 threshold for the following period[s]:
- From 1200 hrs 01/01/2025 to 1400 hrs 01/01/2025. Minimum regional demand is forecast to be 1415 MW at 1300 hrs.


Forecast regional demand (DEMAND50) is published in Short Term and Pre-Dispatch PASA region solution reports available on Market Data NEMWEB: https://aemo.com.au/en/energy-systems/electricity/national-electricity-market-nem/data-nem/market-data-nemweb .

AEMO is seeking a market response.


Manager NEM Real Time Operations
     
122635MINIMUM SYSTEM LOAD31/12/2024 03:16:46 PM

Forecast Minimum System Load MSL1 condition in the VIC Region on 01/01/2025

AEMO ELECTRICITY MARKET NOTICE
Forecast Minimum System Load MSL1 condition in the VIC Region on 01/01/2025

Update to Market Notice 122588
AEMO has detected that there is an elevated risk of insufficient demand to maintain a secure operating state in the VIC on 01/01/2025.

Minimum System Load (MSL) conditions are forecast when regional demand is less than the relevant MSL threshold. The advisory MSL thresholds are:
- MSL1 - 1560 MW
- MSL2 - 1060 MW
- MSL3 - 560 MW

The regional demand is forecast to be below the MSL1 threshold for the following period[s]:
- From 1100 hrs 01/01/2025 to 1400 hrs 01/01/2025. Minimum regional demand is forecast to be 1321 MW at 1300 hrs.


Forecast regional demand (DEMAND50) is published in Short Term and Pre-Dispatch PASA region solution reports available on Market Data NEMWEB: https://aemo.com.au/en/energy-systems/electricity/national-electricity-market-nem/data-nem/market-data-nemweb .

AEMO is seeking a market response.


Manager NEM Real Time Operations
     