NON-CONFORMANCE Region NSW1 Tuesday, 11 March 2025
NON-CONFORMANCE NSW1 Region Tuesday, 11 March 2025
AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:
Unit: WTAHB1
Duration: 11/03/2025 11:25 to 11/03/2025 11:55
Amount: -9 MW
Constraint: NC-N_WTAHB1
Auto-generated on behalf of Manager NEM Real Time Operations
NON-CONFORMANCE Region QLD1 Monday, 10 March 2025
NON-CONFORMANCE QLD1 Region Monday, 10 March 2025
AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:
Unit: MPP_1
Duration: 10/03/2025 13:00 to 10/03/2025 13:05
Amount: -11 MW
Constraint: NC-Q_MPP_1
Auto-generated on behalf of Manager NEM Real Time Operations
PDPASA - Cancellation of the Forecast Lack Of Reserve Level 1 (LOR1) in the SA Region on 09/03/2025
The Forecast LOR1 condition in the SA region advised in AEMO Electricity Market Notice No. 125446 is cancelled at 2015 hrs 09/03/2025.
Manager NEM Real Time Operations
PDPASA - Forecast Lack Of Reserve Level 1 (LOR1) in the SA Region on 09/03/2025
AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the SA region for the following Period:
[1.] From 1930 hrs 09/03/2025 to 2030 hrs 09/03/2025.
The forecast capacity reserve requirement is 650 MW.
The minimum capacity reserve available is 600 MW.
Manager NEM Real Time Operations
Cancellation - AEMO Intervention Event - SA region 08/03/2025
Cancellation - AEMO Intervention Event - SA region 08/03/2025
Refer to Market Notice 125396
The AEMO Intervention Event and all associated directions are cancelled from 1330 hrs on 09/03/2025.
Manager NEM Real Time Operations
Cancellation: Direction issued to: Pelican Point Power Limited - PPCCGT PELICAN POINT
Cancellation: Direction issued to: Pelican Point Power Limited - PPCCGT PELICAN POINT
Refer to Market Notice 125398
Direction is cancelled from: 1330 hrs 09/03/2025
Manager NEM Real Time Operations
PDPASA - Cancellation of the Forecast Lack Of Reserve Level 1 (LOR1) in the SA Region on 09/03/2025
The Forecast LOR1 condition in the SA region advised in AEMO Electricity Market Notice No. 125424 is cancelled at 1200 hrs 09/03/2025.
Manager NEM Real Time Operations
PDPASA - Forecast Lack Of Reserve Level 1 (LOR1) in the SA Region on 09/03/2025
AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the SA region for the following Period:
[1.] From 1830 hrs 09/03/2025 to 1930 hrs 09/03/2025.
The forecast capacity reserve requirement is 650 MW.
The minimum capacity reserve available is 617 MW.
Manager NEM Real Time Operations
Direction - SA region to Pelican Point Power Limited - PPCCGT PELICAN POINT
Direction - SA region to Pelican Point Power Limited - PPCCGT PELICAN POINT
Refer to Market Notice 125396.
In accordance with section 116 of the National Electricity Law, AEMO is issuing a direction to Pelican Point Power Limited. For the purposes of the National Electricity Rules this is a direction under clause 4.8.9(a1)(1).
Direction issued to: Pelican Point Power Limited - PPCCGT PELICAN POINT at 1600 hrs 08/03/2025
Type of resource: generating unit
Required actions: Remain synchronised and follow dispatch targets at 0400 hrs 09/03/2025
Services provided: Voltage Control
Circumstances necessitating the Direction: Voltage
Circumstances necessitating the Direction additional detail: The synchronous generating units currently expected to be synchronised in SA will be inadequate to maintain sufficient Voltage Control in SA. Intervention is required to maintain the power system in a secure operating state
Expected duration: 1330 hrs 09/03/2025.
Pelican Point Power Limited does not incur any civil monetary liability for a relevant action taken in accordance with this direction unless the action is taken in bad faith.
Manager NEM Real Time Operations