124469INTER-REGIONAL TRANSFER11/02/2025 03:59:36 PM

Inter-regional transfer limit variation - MLTS-SMTS No1 500 kV line CB at SYTS - VIC region - 11/02/2025

AEMO ELECTRICITY MARKET NOTICE

Inter-regional transfer limit variation - MLTS-SMTS No1 500 kV line CB at SYTS - VIC region - 11/02/2025

At 1538 hrs 11/02/2025 there was an unplanned outage of MLTS-SMTS No1 500 kV line CB at SYTS .

The following constraint set(s) invoked at 1600 hrs 11/02/2025
V-SY_CB

This constraint set(s) contains equations with the following interconnectors on the LHS.
T-V-MNSP1,V-S-MNSP1,V-SA,VIC1-NSW1

Refer to the AEMO Network Outage Scheduler for further information.

Manager NEM Real Time Operations
     
124468INTER-REGIONAL TRANSFER11/02/2025 03:40:29 PM

Cancellation - Inter-regional transfer limit variation - constraint automation to manage Power System Security in SA region - 11/02/2025

AEMO ELECTRICITY MARKET NOTICE

Referring to Market Notice 124466.

The power system security condition in the SA region, requiring AEMO to invoke the automated constraint set CA_SYDS_56BD5936 has ended at 1520 hrs.

Constraint set revoked: CA_SYDS_56BD5936

Manager NEM Real Time Operations
     
124466INTER-REGIONAL TRANSFER11/02/2025 02:19:04 PM

Inter-regional transfer limit variation - constraint automation to manage Power System Security in SA region - 11/02/2025

AEMO ELECTRICITY MARKET NOTICE

In order to maintain the power system in a secure operating state in the SA region, AEMO has invoked automated constraint set CA_SYDS_56BD5936 from 1410 hrs until further notice.

This constraint set contains equations with the following interconnector on the LHS;

V-SA

Manager NEM Real Time Operations
     
124465MARKET SYSTEMS11/02/2025 02:04:53 PM

CHG0100111 | Completed | Pre-Production | Pre-Prod eMDM February Maintenance Release

Change Number: CHG0100111

Notification issued to: Market Notice

Notification Type: Completed

Change Type: Normal

Service/Component: MDM - Meter Data Management_PreProd

Change Title: Pre-Prod eMDM February Maintenance Release

Support Information: Report any impacts to the AEMO Information and Support Hub or on External 1300 236 600.
     
124418MARKET SYSTEMS10/02/2025 11:43:25 AM

INC0140978 - ALERT - Frequency Performance Payments (FPP) System

AEMO ELECTRICITY MARKET NOTICE

ALERT - Frequency Performance Payments (FPP) System

AEMO experienced service interruption relating to Frequency Performance Payments (FPP) System. The FPP System was unable to calculate & publish Contribution Factors (CFs) from 14:36 Hrs AEST on 9/02/2025 till 09:34 Hrs AEST on 10/02/2025.

The service interruption relating to Frequency Performance Payments (FPP) System has now been resolved.

Default Contribution Factors (DCFs) will be applicable for the trading intervals where CFs were not calculated.

For further enquiries please contact the AEMO Support Hub
Phone: 1300 236 600
Email: supporthub@aemo.com.au
     
124416INTER-REGIONAL TRANSFER10/02/2025 10:09:20 AM

Inter-regional transfer limit variation - Ingleburn - Wallerawang (77) 330 kV line - NSW region - 10/02/2025

AEMO ELECTRICITY MARKET NOTICE

Inter-regional transfer limit variation - Ingleburn - Wallerawang (77) 330 kV line - NSW region - 10/02/2025

At 0945 hrs 10/02/2025 there was an unplanned outage of Ingleburn - Wallerawang (77) 330 kV line.

The following constraint set(s) invoked at 0955 hrs 10/02/2025
N-X_AVMA_SSWW

This constraint set(s) contains equations with the following interconnectors on the LHS.
N-Q-MNSP1,NSW1-QLD1,VIC1-NSW1

Refer to the AEMO Network Outage Scheduler for further information.

Manager NEM Real Time Operations
     
124400RESERVE NOTICE09/02/2025 05:51:30 PM

Cancellation of Actual (LOR1) condition in the NSW region - 09/02/2025

AEMO ELECTRICITY MARKET NOTICE

Cancellation of Actual (LOR1) condition in the NSW region - 09/02/2025

The Actual LOR1 Condition in the NSW Region advised in AEMO Electricity Market Notice No.124399 is cancelled at 1749 hrs 09/02/2025.

Manager NEM Real Time Operations
     
124399RESERVE NOTICE09/02/2025 04:44:17 PM

Actual Lack Of Reserve Level 1 (LOR1) in the NSW region - 09/02/2025

AEMO ELECTRICITY MARKET NOTICE

Actual Lack Of Reserve Level 1 (LOR1) in the NSW region - 09/02/2025

An Actual LOR1 condition has been declared under clause 4.8.4(b) of the National Electricity Rules for the NSW region from 1630 hrs.
The Actual LOR1 condition is forecast to exist until 1730 hrs

The capacity reserve requirement is 1320 MW
The minimum capacity reserve available is 1171 MW

Manager NEM Real Time Operations
     
124322RESERVE NOTICE07/02/2025 07:40:53 PM

Cancellation of Actual (LOR1) condition in the NSW region - 07/02/2025

AEMO ELECTRICITY MARKET NOTICE

Cancellation of Actual (LOR1) condition in the NSW region - 07/02/2025

The Actual LOR1 Condition in the NSW Region advised in AEMO Electricity Market Notice No.124305 is cancelled at 1940 hrs 07/02/2025.