Market Notices

124579RESERVE NOTICE12/02/2025 08:44:30 PM

Cancellation of Actual (LOR1) condition in the SA region - 12/02/2025

AEMO ELECTRICITY MARKET NOTICE

Cancellation of Actual (LOR1) condition in the SA region - 12/02/2025

The Actual LOR1 Condition in the SA Region advised in AEMO Electricity Market Notice No.124572 is cancelled at 2040 hrs 12/02/2025.

Manager NEM Real Time Operations
     
124572RESERVE NOTICE12/02/2025 06:53:15 PM

Actual Lack Of Reserve Level 1 (LOR1) in the SA region - 12/02/2025

AEMO ELECTRICITY MARKET NOTICE

Actual Lack Of Reserve Level 1 (LOR1) in the SA region - 12/02/2025

An Actual LOR1 condition has been declared under clause 4.8.4(b) of the National Electricity Rules for the SA region from 1830 hrs.
The Actual LOR1 condition is forecast to exist until 1930 hrs

The capacity reserve requirement is 524 MW
The minimum capacity reserve available is 470 MW

Manager NEM Real Time Operations
     
124465MARKET SYSTEMS11/02/2025 02:04:53 PM

CHG0100111 | Completed | Pre-Production | Pre-Prod eMDM February Maintenance Release

Change Number: CHG0100111

Notification issued to: Market Notice

Notification Type: Completed

Change Type: Normal

Service/Component: MDM - Meter Data Management_PreProd

Change Title: Pre-Prod eMDM February Maintenance Release

Support Information: Report any impacts to the AEMO Information and Support Hub or on External 1300 236 600.
     
124418MARKET SYSTEMS10/02/2025 11:43:25 AM

INC0140978 - ALERT - Frequency Performance Payments (FPP) System

AEMO ELECTRICITY MARKET NOTICE

ALERT - Frequency Performance Payments (FPP) System

AEMO experienced service interruption relating to Frequency Performance Payments (FPP) System. The FPP System was unable to calculate & publish Contribution Factors (CFs) from 14:36 Hrs AEST on 9/02/2025 till 09:34 Hrs AEST on 10/02/2025.

The service interruption relating to Frequency Performance Payments (FPP) System has now been resolved.

Default Contribution Factors (DCFs) will be applicable for the trading intervals where CFs were not calculated.

For further enquiries please contact the AEMO Support Hub
Phone: 1300 236 600
Email: supporthub@aemo.com.au
     
124400RESERVE NOTICE09/02/2025 05:51:30 PM

Cancellation of Actual (LOR1) condition in the NSW region - 09/02/2025

AEMO ELECTRICITY MARKET NOTICE

Cancellation of Actual (LOR1) condition in the NSW region - 09/02/2025

The Actual LOR1 Condition in the NSW Region advised in AEMO Electricity Market Notice No.124399 is cancelled at 1749 hrs 09/02/2025.

Manager NEM Real Time Operations
     
124399RESERVE NOTICE09/02/2025 04:44:17 PM

Actual Lack Of Reserve Level 1 (LOR1) in the NSW region - 09/02/2025

AEMO ELECTRICITY MARKET NOTICE

Actual Lack Of Reserve Level 1 (LOR1) in the NSW region - 09/02/2025

An Actual LOR1 condition has been declared under clause 4.8.4(b) of the National Electricity Rules for the NSW region from 1630 hrs.
The Actual LOR1 condition is forecast to exist until 1730 hrs

The capacity reserve requirement is 1320 MW
The minimum capacity reserve available is 1171 MW

Manager NEM Real Time Operations
     
124322RESERVE NOTICE07/02/2025 07:40:53 PM

Cancellation of Actual (LOR1) condition in the NSW region - 07/02/2025

AEMO ELECTRICITY MARKET NOTICE

Cancellation of Actual (LOR1) condition in the NSW region - 07/02/2025

The Actual LOR1 Condition in the NSW Region advised in AEMO Electricity Market Notice No.124305 is cancelled at 1940 hrs 07/02/2025.

Manager NEM Real Time Operations
     
124305RESERVE NOTICE07/02/2025 05:21:00 PM

Actual Lack Of Reserve Level 1 (LOR1) in the NSW region - 07/02/2025

AEMO ELECTRICITY MARKET NOTICE

Actual Lack Of Reserve Level 1 (LOR1) in the NSW region - 07/02/2025

An Actual LOR1 condition has been declared under clause 4.8.4(b) of the National Electricity Rules for the NSW region from 1700 hrs.
The Actual LOR1 condition is forecast to exist until 2000 hrs

The capacity reserve requirement is 1370 MW
The minimum capacity reserve available is 936 MW

Manager NEM Real Time Operations
     
124301POWER SYSTEM EVENTS07/02/2025 03:34:46 PM

Update - Non-credible contingency event - NSW region - 23/01/2025

AEMO ELECTRICITY MARKET NOTICE.

Update - Non-credible contingency event - NSW region - 23/01/2025

Refer AEMO Electricity Market Notice 123615

At 0240 hrs on the 23/01/2025 there was a trip and auto reclose of the Kempsey - Macksville 9W5 and the Kempsey - Raleigh 9W2 132kV Lines

The cause of this non-credible contingency event has been identified and AEMO is satisfied that another occurrence of this event is unlikely under the current circumstances.

AEMO will not reclassify this event as a credible contingency event.

Manager NEM Real Time Operations
     