Filter by category
Filter by Date
NON-CONFORMANCE Region VIC1 Tuesday, 25 February 2025
NON-CONFORMANCE VIC1 Region Tuesday, 25 February 2025
AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:
Unit: MOKOSF1
Duration: 25/02/2025 09:50 to 25/02/2025 11:00
Amount: 32 MW
Constraint: NC-V_MOKOSF1
Auto-generated on behalf of Manager NEM Real Time Operations
NON-CONFORMANCE Region QLD1 Tuesday, 25 February 2025
NON-CONFORMANCE QLD1 Region Tuesday, 25 February 2025
AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:
Unit: STAN-4
Duration: 25/02/2025 09:30 to 25/02/2025 10:20
Amount: -18 MW
Constraint: NC-Q_STAN-4
Auto-generated on behalf of Manager NEM Real Time Operations
NEM Local Temperature Alerts for SA, VIC from 24 Feb 2025 to 28 Feb 2025
AEMO's weather service provider has issued forecast temperatures equal to or greater than the NEM Local Temperature Alert Levels for listed weather stations below.
SA
Port Augusta Ap (39+ Deg C): 27th Feb
VIC
Mildura Ap (39+ Deg C): 26th Feb, 27th Feb
The NEM Local Temperature Alert Levels are:
Launceston Ti Tree Bend: 33 Deg C, Dalby Airport: 37 Deg C, for all other selected weather stations: 39 Deg C.
AEMO requests Market Participants to:
1. review the weather forecast in the local area where their generating units / MNSP converter stations are located and,
2. if required, update the available capacity in their dispatch offers or availability submissions consistent with the forecast temperatures.
Further information is available at:
https://aemo.com.au/energy-systems/electricity/national-electricity-market-nem/nem-forecasting-and-planning/forecasting-and-reliability/projected-assessment-of-system-adequacy/nem-local-temperature-alerts
AEMO Operations Planning
Completed - CHG0100546 - Production eMDM February Maintenance Release
Notification issued to: Market Notice
Notification Type: Completed
Change Type: Normal
Service/Component: MDM - Meter Data Management
Change Title: Production eMDM February Maintenance Release
Support Information: Report any impacts to the AEMO Information and Support Hub or on External 1300 236 600.
Inter-regional transfer limit variation - BassLink Harmonic Filter - TAS region - 23/02/2025
Inter-regional transfer limit variation - BassLink Harmonic Filter - TAS region - 23/02/2025
At 0305 hrs 23/02/2025 there was an unplanned outage of BassLink Harmonic Filter.
The following constraint set(s) invoked at 0305 hrs 23/02/2025
T-BLGC_HF_43MVAR
This constraint set(s) contains equations with the following interconnectors on the LHS.
T-V-MNSP1
Refer to the AEMO Network Outage Scheduler for further information.
Manager NEM Real Time Operations
Inter-regional transfer limit variation - Collector Windfarm - Yass (3L) 330 kV line - NSW region - 22/02/2025
Inter-regional transfer limit variation - Collector Windfarm - Yass (3L) 330 kV line - NSW region - 22/02/2025
A planned outage of Collector Windfarm - Yass (3L) 330 kV line in the NSW region was scheduled from 0600 hrs 17/02/2025 to 1600 hrs 24/02/2025.
The outage has been completed and Collector Windfarm - Yass (3L) 330 kV line returned to service at 0746 hrs 22/02/2025
Constraint set(s) revoked: N-CTYS_3L_WG_CLOSE
Manager NEM Real Time Operations
NON-CONFORMANCE Region VIC1 Friday, 21 February 2025
NON-CONFORMANCE VIC1 Region Friday, 21 February 2025
AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:
Unit: MCKAY1
Duration: 21/02/2025 12:00 to 21/02/2025 12:10
Amount: -54 MW
Constraint: NC-V_MCKAY1
Auto-generated on behalf of Manager NEM Real Time Operations
NON-CONFORMANCE Region SA1 Friday, 21 February 2025
NON-CONFORMANCE SA1 Region Friday, 21 February 2025
AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:
Unit: BLYTHB1
Duration: 21/02/2025 11:50 to 21/02/2025 12:05
Amount: -19 MW
Constraint: NC-S_BLYTHB1
Auto-generated on behalf of Manager NEM Real Time Operations
Update - Non-credible contingency event - NSW region - 21/02/2025
Update - Non-credible contingency event - NSW region - 21/02/2025
Refer AEMO Electricity Market Notice 124944
At 1030 hrs the Capital WF A and C 330kV Buses were returned to service.
The cause of this non-credible contingency event has been identified and AEMO is satisfied that another occurrence of this event is unlikely under the current circumstances.
AEMO will not reclassify this event as a credible contingency event.
Manager NEM Real Time Operations