Forecast Minimum System Load (MSL1) condition in the VIC region on 16/02/2025
AEMO has detected that there is an elevated risk of insufficient demand to maintain a secure operating state in the VIC region on 16/02/2025.
Minimum System Load (MSL) conditions are forecast when regional demand is less than the relevant MSL threshold. The advisory MSL thresholds are:
o MSL1 - 2060 MW
o MSL2 - 1560 MW
o MSL3 - 1060 MW
The regional demand is forecast to be below the MSL1 threshold for the following period:
From 1130 hrs to 1430 hrs 16/02/2025. Minimum regional demand is forecast to be 1838 MW at 1330 hrs.
Forecast regional demand (DEMAND50) is published in Short Term and Pre-Dispatch PASA region solution reports available on Market Data NEMWEB: https://aemo.com.au/en/energy-systems/electricity/national-electricity-market-nem/data-nem/market-data-nemweb .
AEMO Operations
[EventId:202502101255_review] Prices for interval 10-Feb-2025 12:55 are subject to review
Issued by Australian Energy Market Operator Ltd at 1250 hrs on 10 February 2025
PRICES ARE SUBJECT TO REVIEW for trading interval 10-Feb-2025 12:55.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
[EventId:202502101250_review] Prices for interval 10-Feb-2025 12:50 are subject to review
Issued by Australian Energy Market Operator Ltd at 1245 hrs on 10 February 2025
PRICES ARE SUBJECT TO REVIEW for trading interval 10-Feb-2025 12:50.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
[EventId:202502101245_review] Prices for interval 10-Feb-2025 12:45 are subject to review
Issued by Australian Energy Market Operator Ltd at 1240 hrs on 10 February 2025
PRICES ARE SUBJECT TO REVIEW for trading interval 10-Feb-2025 12:45.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
[EventId:202502101240_review] Prices for interval 10-Feb-2025 12:40 are subject to review
Issued by Australian Energy Market Operator Ltd at 1235 hrs on 10 February 2025
PRICES ARE SUBJECT TO REVIEW for trading interval 10-Feb-2025 12:40.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
[EventId:202502101235_review] Prices for interval 10-Feb-2025 12:35 are subject to review
Issued by Australian Energy Market Operator Ltd at 1230 hrs on 10 February 2025
PRICES ARE SUBJECT TO REVIEW for trading interval 10-Feb-2025 12:35.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
[EventId:202502101230_review] Prices for interval 10-Feb-2025 12:30 are subject to review
Issued by Australian Energy Market Operator Ltd at 1225 hrs on 10 February 2025
PRICES ARE SUBJECT TO REVIEW for trading interval 10-Feb-2025 12:30.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
INC0140978 - ALERT - Frequency Performance Payments (FPP) System
ALERT - Frequency Performance Payments (FPP) System
AEMO experienced service interruption relating to Frequency Performance Payments (FPP) System. The FPP System was unable to calculate & publish Contribution Factors (CFs) from 14:36 Hrs AEST on 9/02/2025 till 09:34 Hrs AEST on 10/02/2025.
The service interruption relating to Frequency Performance Payments (FPP) System has now been resolved.
Default Contribution Factors (DCFs) will be applicable for the trading intervals where CFs were not calculated.
For further enquiries please contact the AEMO Support Hub
Phone: 1300 236 600
Email: supporthub@aemo.com.au
Inter-regional transfer limit variation - Ingleburn - Wallerawang (77) 330 kV line - NSW region - 10/02/2025
Inter-regional transfer limit variation - Ingleburn - Wallerawang (77) 330 kV line - NSW region - 10/02/2025
At 0945 hrs 10/02/2025 there was an unplanned outage of Ingleburn - Wallerawang (77) 330 kV line.
The following constraint set(s) invoked at 0955 hrs 10/02/2025
N-X_AVMA_SSWW
This constraint set(s) contains equations with the following interconnectors on the LHS.
N-Q-MNSP1,NSW1-QLD1,VIC1-NSW1
Refer to the AEMO Network Outage Scheduler for further information.
Manager NEM Real Time Operations