Network Augmentation Commissioned - Vic Region - 16/01/2025
Network Augmentation Commissioned - Vic Region - 16/01/2025
At 2128 hrs 16/01/2025, the Koorangie 220 kV Terminal Station has been cut in to the existing Kerang - Wemen 220 kV transmission line resulting in the following network augmentations being commissioned:
Koorangie 220 kV Terminal Station
Koorangie - Wemen 220 kV transmission line
Kerang - Koorangie 220 kV transmission line
Manager NEM Real Time Operations
NEM Local Temperature Alerts for QLD, SA, VIC from 16 Jan 2025 to 20 Jan 2025
AEMO's weather service provider has issued forecast temperatures equal to or greater than the NEM Local Temperature Alert Levels for listed weather stations below.
QLD
Rockhampton Ap (39+ Deg C): 16th Jan
SA
Port Augusta Ap (39+ Deg C): 19th Jan
VIC
Mildura Ap (39+ Deg C): 20th Jan
The NEM Local Temperature Alert Levels are:
Launceston Ti Tree Bend: 33 Deg C, Dalby Airport: 37 Deg C, for all other selected weather stations: 39 Deg C.
AEMO requests Market Participants to:
1. review the weather forecast in the local area where their generating units / MNSP converter stations are located and,
2. if required, update the available capacity in their dispatch offers or availability submissions consistent with the forecast temperatures.
Further information is available at:
https://aemo.com.au/energy-systems/electricity/national-electricity-market-nem/nem-forecasting-and-planning/forecasting-and-reliability/projected-assessment-of-system-adequacy/nem-local-temperature-alerts
AEMO Operations Planning
Fast Frequency Response Market - Increase in R1 FCAS dispatch cap from 20th January 2025
Following review of the operation of the Very Fast FCAS market, from 1300 hrs AEST on Monday 20th January AEMO will increase the cap on dispatch of Very Fast Raise (R1) Contingency FCAS from 425 MW to 500 MW
No other changes to the dispatch of Very Fast FCAS or FCAS constraint equations will be made on this date.
For information on the Fast Frequency Response (FFR) initiative please visit the website at: https://www.aemo.com.au/initiatives/major-programs/fast-frequency-response
Andrew Groom
AEMO Operations
[EventId:202501151700_review] Prices for interval 15-Jan-2025 17:00 are subject to review
Issued by Australian Energy Market Operator Ltd at 1655 hrs on 15 January 2025
PRICES ARE SUBJECT TO REVIEW for trading interval 15-Jan-2025 17:00.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
[EventId:202501151655_review] Prices for interval 15-Jan-2025 16:55 are subject to review
Issued by Australian Energy Market Operator Ltd at 1650 hrs on 15 January 2025
PRICES ARE SUBJECT TO REVIEW for trading interval 15-Jan-2025 16:55.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
[EventId:202501151650_review] Prices for interval 15-Jan-2025 16:50 are subject to review
Issued by Australian Energy Market Operator Ltd at 1645 hrs on 15 January 2025
PRICES ARE SUBJECT TO REVIEW for trading interval 15-Jan-2025 16:50.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
[EventId:202501151645_review] Prices for interval 15-Jan-2025 16:45 are subject to review
Issued by Australian Energy Market Operator Ltd at 1640 hrs on 15 January 2025
PRICES ARE SUBJECT TO REVIEW for trading interval 15-Jan-2025 16:45.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
[EventId:202501151640_review] Prices for interval 15-Jan-2025 16:40 are subject to review
Issued by Australian Energy Market Operator Ltd at 1635 hrs on 15 January 2025
PRICES ARE SUBJECT TO REVIEW for trading interval 15-Jan-2025 16:40.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
[EventId:202501151635_review] Prices for interval 15-Jan-2025 16:35 are subject to review
Issued by Australian Energy Market Operator Ltd at 1630 hrs on 15 January 2025
PRICES ARE SUBJECT TO REVIEW for trading interval 15-Jan-2025 16:35.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.