Cancellation of Actual (LOR1) condition in the NSW region - 13/01/2025
Cancellation of Actual (LOR1) condition in the NSW region - 13/01/2025
The Actual LOR1 Condition in the NSW Region advised in AEMO Electricity Market Notice No.123180 is cancelled at 2045 hrs 13/01/2025.
Manager NEM Real Time Operations
Update - Actual Lack Of Reserve Level 1 (LOR1) in the NSW region - 13/01/2025
Update - Actual Lack Of Reserve Level 1 (LOR1) in the NSW region - 13/01/2025
Refer market notice: 123171
An Actual LOR1 condition has been declared under clause 4.8.4(b) of the National Electricity Rules for the NSW region from 1800 hrs.
The Actual LOR1 condition is forecast to exist until 2000 hrs.
The forecast capacity reserve requirement is 1365 MW.
The minimum capacity reserve available is 966 MW.
Manager NEM Real Time Operations
Actual Lack Of Reserve Level 1 (LOR1) in the NSW region - 13/01/2025
Actual Lack Of Reserve Level 1 (LOR1) in the NSW region - 13/01/2025
An Actual LOR1 condition has been declared under clause 4.8.4(b) of the National Electricity Rules for the NSW region from 1630 hrs.
The Actual LOR1 condition is forecast to exist until 1700 hrs
The capacity reserve requirement is 1390 MW
The minimum capacity reserve available is 861 MW
Manager NEM Real Time Operations
Update - Non-credible contingency event - SA region - 23/12/2024
Update - Non-credible contingency event - SA region - 23/12/2024
Refer AEMO Electricity Market Notice 122442
At 2036 hrs the Happy Valley - Morphett Vale East and the Morphett Vale - Cherry Gardens 275kV lines were returned to service.
The cause of this non-credible contingency event has been identified and AEMO is satisfied that another occurrence of this event is unlikely under the current circumstances.
AEMO will not reclassify this event as a credible contingency event.
Manager NEM Real Time Operations
Non-credible contingency event - SA region - 23/12/2024
Non-credible contingency event - SA region - 23/12/2024
At 1632 hrs the Happy Valley - Morphett Vale East 275kV Line and the Morphett Vale - Cherry Gardens 275kV line tripped.
AEMO did not instruct load shedding.
AEMO has not been advised of any disconnection of bulk electrical load.
The cause of this non credible contingency event is not known at this stage.
Manager NEM Real Time Operations
INC0139532 | Impact to Prudentials
SERVICE INTERRUPTION - ALERT
The service interruption relating to Prudentials & Settlements have now been resolved.
AEMO is working on the issue and will provide updates as more information becomes available.
For further enquiries please contact the AEMO Support Hub
Phone: 1300 236 600
Email: supporthub@aemo.com.au
AEMO IT Duty Manager
INC0139532 - ALERT - Impact to Prudentials
SERVICE INTERRUPTION - ALERT
AEMO is experiencing a service interruption relating to: Prudentials & Settlements.
AEMO is working on the issue and will provide updates as more information becomes available.
For further enquiries please contact the AEMO Support Hub
Phone: 1300 236 600
Email: supporthub@aemo.com.au
AEMO IT Duty Manager
Cancellation of the Actual Lack Of Reserve Level 1 (LOR1) condition in the NSW Region on 17/12/2024
The Actual LOR1 condition in the NSW region advised in AEMO Electricity Market Notice No. 122113 is cancelled at 1745 hrs 17/12/2024.
Manager NEM Real Time Operations
Actual Lack Of Reserve Level 1 (LOR1) in the NSW region - 17/12/2024
Actual Lack Of Reserve Level 1 (LOR1) in the NSW region - 17/12/2024
An Actual LOR1 condition has been declared under clause 4.8.4(b) of the National Electricity Rules for the NSW region from 1530 hrs.
The Actual LOR1 condition is forecast to exist until 1800 hrs
The capacity reserve requirement is 1340 MW
The minimum capacity reserve available is 1082 MW
Manager NEM Real Time Operations