118546MARKET INTERVENTION01/10/2024 02:03:22 PM

Direction - SA region 01/10/2024

AEMO ELECTRICITY MARKET NOTICE

Direction - SA region 01/10/2024

Refer to Market Notice 118541


In accordance with section 116 of the National Electricity Law, AEMO is issuing a direction to AGL SA Generation Pty Limited. For the purposes of the National Electricity Rules this is a direction under clause 4.8.9(a1)(1).

Direction issued to: AGL SA Generation Pty Limited - TORRB4 TORRENS ISLAN at 1400 hrs 01/10/2024
Type of resource: generating unit
Required actions: remain synchronised and follow dispatch targets at 0730 hrs 02/10/2024
Services provided: Voltage Control
Circumstances necessitating the Direction: Voltage
Circumstances necessitating the Direction additional detail: intervention is required to maintain the power system in a secure operating state
Expected duration: 0400 hrs 03/10/2024

AGL SA Generation Pty Limited does not incur any civil monetary liability for a relevant action taken in accordance with this direction unless the action is taken in bad faith.

Manager NEM Real Time Operations
     
118545MARKET INTERVENTION01/10/2024 02:02:12 PM

Direction - SA region 01/10/2024

AEMO ELECTRICITY MARKET NOTICE

Direction - SA region 01/10/2024

Refer to Market Notice 118541


In accordance with section 116 of the National Electricity Law, AEMO is issuing a direction to AGL SA Generation Pty Limited. For the purposes of the National Electricity Rules this is a direction under clause 4.8.9(a1)(1).

Direction issued to: AGL SA Generation Pty Limited - TORRB2 TORRENS ISLAN at 1400 hrs 01/10/2024
Type of resource: generating unit
Required actions: remain synchronised and follow dispatch targets at 0730 hrs 02/10/2024
Services provided: Voltage Control
Circumstances necessitating the Direction: Voltage
Circumstances necessitating the Direction additional detail: intervention is required to maintain the power system in a secure operating state
Expected duration: 1530 hrs 02/10/2024

AGL SA Generation Pty Limited does not incur any civil monetary liability for a relevant action taken in accordance with this direction unless the action is taken in bad faith.

Manager NEM Real Time Operations
     
118541MARKET INTERVENTION01/10/2024 10:48:11 AM

Update - Foreseeable AEMO intervention in SA region

AEMO ELECTRICITY MARKET NOTICE

Update - Foreseeable AEMO intervention in SA region

Refer AEMO Electricity Market Notice 118540

AEMO has identified a foreseeable circumstance that may require an AEMO intervention event in the SA region from 2230 hrs 01/10/2024.

The foreseeable circumstance requiring the need for intervention is Voltage.

AEMO estimates that, in the absence of sufficient market response by 1400 hrs 01/10/2024, AEMO may need to intervene by issuing a direction.

Manager NEM Real Time Operations
     
118540MARKET INTERVENTION01/10/2024 08:33:43 AM

Foreseeable AEMO intervention under clause 4.8.5A (a) of the NER in SA region

AEMO ELECTRICITY MARKET NOTICE

Foreseeable AEMO intervention under clause 4.8.5A (a) of the NER in SA region

AEMO has identified a foreseeable circumstance that may require an AEMO intervention event in the SA region from 2230 hrs 01/10/2024.

The foreseeable circumstance requiring the need for intervention is Voltage.

Manager NEM Real Time Operations
     
118537MARKET INTERVENTION30/09/2024 03:02:10 PM

Cancellation - AEMO Intervention Event - SA region 26/09/2024

AEMO ELECTRICITY MARKET NOTICE

Cancellation - AEMO Intervention Event - SA region 24/09/2024

Refer to Market Notice 118455

The AEMO Intervention Event and all associated directions are cancelled from 1500 hrs on 30/09/2024.



Manager NEM Real Time Operations
     
118536MARKET INTERVENTION30/09/2024 03:03:13 PM

Cancellation: Direction issued to: AGL SA Generation Pty Limited - TORRB4 TORRENS ISLAN

AEMO ELECTRICITY MARKET NOTICE

Cancellation: Direction issued to: AGL SA Generation Pty Limited - TORRB4 TORRENS ISLAN

Refer to Market Notice 118509

Direction is cancelled from: 1500 hrs 30/09/2024

Manager NEM Real Time Operations
     
118535MARKET INTERVENTION30/09/2024 03:00:53 PM

Cancellation: Direction issued to: AGL SA Generation Pty Limited - TORRB2 TORRENS ISLAN

AEMO ELECTRICITY MARKET NOTICE

Cancellation: Direction issued to: AGL SA Generation Pty Limited - TORRB2 TORRENS ISLAN

Refer to Market Notice 118510

Direction is cancelled from: 1500 hrs 30/09/2024

Manager NEM Real Time Operations
     
118534MARKET INTERVENTION30/09/2024 02:38:25 PM

Direction - AGL SA Generation Pty Limited - TORRB2 TORRENS ISLA

AEMO ELECTRICITY MARKET NOTICE

Direction - AGL SA Generation Pty Limited - TORRB2 TORRENS ISLA

Refer to Market Notice 118532


In accordance with section 116 of the National Electricity Law, AEMO is issuing a direction to AGL SA Generation Pty Limited. For the purposes of the National Electricity Rules this is a direction under clause 4.8.9(a1)(1).

Direction issued to: AGL SA Generation Pty Limited - TORRB2 TORRENS ISLAN at 1435 hrs 30/09/2024
Type of resource: generating unit
Required actions: Remain synchronised and follow dispatch targets at 0830 hrs 01/10/2024
Services provided: Voltage Control
Circumstances necessitating the Direction: Voltage
Circumstances necessitating the Direction additional detail: intervention is required to maintain the power system in a secure operating state
Expected duration: 1530 hrs 01/10/2024 / further notice.

AGL SA Generation Pty Limited does not incur any civil monetary liability for a relevant action taken in accordance with this direction unless the action is taken in bad faith.

Manager NEM Real Time Operations
     
118532MARKET INTERVENTION30/09/2024 02:33:16 PM

Update - Foreseeable AEMO intervention in SA region

AEMO ELECTRICITY MARKET NOTICE

Update - Foreseeable AEMO intervention in SA region

Refer AEMO Electricity Market Notice 118530

AEMO has identified a foreseeable circumstance that may require an AEMO intervention event in the SA region from 0830 hrs 01/10/2024.

The foreseeable circumstance requiring the need for intervention is Voltage.

AEMO estimates that, in the absence of sufficient market response by 1430 hrs 30/09/2024, AEMO may need to intervene by issuing a direction.

Manager NEM Real Time Operations
     