123980INTER-REGIONAL TRANSFER01/02/2025 08:53:03 AM

Inter-regional transfer limit variation - Armidale - Tamworth No. 86 330 kV Line - NSW region - 01/02/2025

AEMO ELECTRICITY MARKET NOTICE

Inter-regional transfer limit variation - Armidale - Tamworth No. 86 330 kV Line - NSW region - 01/02/2025

A planned outage of Armidale - Tamworth No. 86 330 kV Line in the NSW region was scheduled to be completed at 1030 hrs 01/02/2025

The outage has been completed by 0835 hrs 01/02/2025

Constraint set(s) invoked:
N-ARTW_86
N-DM_SVC
N-TW_SVC


This constraint set(s) contains equations with the following interconnectors on the LHS.
N-Q-MNSP1
NSW1-QLD1
T-V-MNSP1

Refer to the AEMO Network Outage Scheduler for further information.

Manager NEM Real Time Operations
     
123979MARKET INTERVENTION01/02/2025 07:29:01 AM

Foreseeable AEMO intervention under clause 4.8.5A (a) of the NER in SA region

AEMO ELECTRICITY MARKET NOTICE

Foreseeable AEMO intervention under clause 4.8.5A (a) of the NER in SA region

AEMO has identified a foreseeable circumstance that may require an AEMO intervention event in the SA region from 0030 hrs 02/02/2025.

The foreseeable circumstance requiring the need for intervention is Voltage.

Manager NEM Real Time Operations
     
123966MARKET INTERVENTION01/02/2025 03:57:13 AM

Cancellation: Direction issued to: AGL SA Generation Pty Limited - TORRB2 TORRENS ISLAN

AEMO ELECTRICITY MARKET NOTICE

Cancellation: Direction issued to: AGL SA Generation Pty Limited - TORRB2 TORRENS ISLAN

Refer to Market Notice 123925

Direction is cancelled from: 0400 hrs 01/02/2025

Manager NEM Real Time Operations
     
123965MARKET INTERVENTION31/01/2025 03:59:12 PM

Update Direction - Pelican Point Power Limited - PPCCGT PELICAN POINT

AEMO ELECTRICITY MARKET NOTICE.

Update Direction - Pelican Point Power Limited - PPCCGT PELICAN POINT

Refer to Market Notice 123924

PPCCGT PELICAN POINT at 0100 hrs 27/01/2025 to Remain synchronised and follow dispatch targets.

The PPCCGT PELICAN POINT direction is now expected to stay in place until 1600 hrs 01/02/2025.

The direction update is issued at 1600 hrs 31/01/2025.

Manager NEM Real Time Operations
     
123961MARKET SYSTEMS31/01/2025 02:09:43 PM

CHG0101137 | Production | Planned Maintenance to Norwest Marketnet Site to Site VPN Router

Change Number: CHG0101137

Notification issued to: Market Notice

Notification Type: Initial

Change Type: Normal

Service/ Component: Local Area Network

Change Title: Planned Maintenance to Norwest Marketnet Site to Site VPN Router

Change Start Date & Time: 04/02/2025 11:00:00 AEST
Change End Date & Time: 04/02/2025 15:00:00 AEST
Outage Start Date & Time:
Outage End Date & Time:

Environment: Production

Participant Impact and Requirements: The following impacts are expected to participant connectivity during this planned maintenance:

IPWAN Participants - Nil

Lan-2-Lan VPN Participants (IPSEC) - Nil

B2B VPN - Nil

SSL VPN Participants: Nil

GASHUB: Nil

Other Impacts will have been communicated in advance.

Support Information:
Report any impacts to the AEMO Information and Support Hub or call 1300 236 600.
Please refer to https://aemo.service-now.com/participantportal?id=pp_services_status for any
planned/unplanned maintenance activities .
     
123949PRICES UNCHANGED30/01/2025 07:12:37 PM

[EventId:202501301815_confirmed] Prices for interval 30-Jan-2025 18:15 are now confirmed

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1835 hrs on 30 January 2025

PRICES ARE NOW CONFIRMED for trading interval 30-Jan-2025 18:15.

In accordance with Market Notice 123939 AEMO has reviewed this trading interval and determined that:
- Manifestly Incorrect Inputs did not apply

Prices remain unchanged.


This is an AEMO autogenerated Market Notice.
     
123948PRICES UNCHANGED30/01/2025 07:06:46 PM

[EventId:202501301835_confirmed] Prices for interval 30-Jan-2025 18:35 are now confirmed

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1835 hrs on 30 January 2025

PRICES ARE NOW CONFIRMED for trading interval 30-Jan-2025 18:35.

In accordance with Market Notice 123943 AEMO has reviewed this trading interval and determined that:
- Manifestly Incorrect Inputs did not apply

Prices remain unchanged.


This is an AEMO autogenerated Market Notice.
     
123947PRICES UNCHANGED30/01/2025 07:00:52 PM

[EventId:202501301830_confirmed] Prices for interval 30-Jan-2025 18:30 are now confirmed

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1835 hrs on 30 January 2025

PRICES ARE NOW CONFIRMED for trading interval 30-Jan-2025 18:30.

In accordance with Market Notice 123942 AEMO has reviewed this trading interval and determined that:
- Manifestly Incorrect Inputs did not apply

Prices remain unchanged.


This is an AEMO autogenerated Market Notice.
     
123946PRICES UNCHANGED30/01/2025 06:54:38 PM

[EventId:202501301825_confirmed] Prices for interval 30-Jan-2025 18:25 are now confirmed

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1835 hrs on 30 January 2025

PRICES ARE NOW CONFIRMED for trading interval 30-Jan-2025 18:25.

In accordance with Market Notice 123941 AEMO has reviewed this trading interval and determined that:
- Manifestly Incorrect Inputs did not apply

Prices remain unchanged.


This is an AEMO autogenerated Market Notice.
     