[EventId:202503241715_NRM_NSW1_VIC1_started] NEGRES CONSTRAINT NRM_NSW1_VIC1 started operating from 24 March 2025 17:15
Issued by Australian Energy Market Operator Ltd at 1715 hrs on 24 March 2025
ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 24 March 2025.
Electricity Market outcomes have resulted in the accumulation of negative settlement residues that have exceeded the allowable negative residue threshold for the NSW to VIC directional interconnector.
The negative residue constraint set NRM_NSW1_VIC1 commenced operating from 1715 hrs on 24 March 2025.
This constraint set contains an equation with the following interconnectors on the LHS:
VIC1-NSW1
The RHS of the constraint equation may be adjusted to manage residues.
This is an AEMO autogenerated Market Notice.
Direction - SA region to AGL SA Generation Pty Limited - TORRB2 TORRENS ISLAN
Direction - SA region to AGL SA Generation Pty Limited - TORRB2 TORRENS ISLAN
Refer to Market Notice 125898
In accordance with section 116 of the National Electricity Law, AEMO is issuing a direction to AGL SA Generation Pty Limited. For the purposes of the National Electricity Rules this is a direction under clause 4.8.9(a1)(1).
Direction issued to: AGL SA Generation Pty Limited - TORRB2 TORRENS ISLAN at 1600 hrs 24/03/2025
Type of resource: generating unit
Required actions: Remain synchronised and follow dispatch targets at 0900 hrs 25/03/2025
Services provided: Voltage Control
Circumstances necessitating the Direction: Voltage
Circumstances necessitating the Direction additional detail: The synchronous generating units currently expected to be synchronised in SA will be inadequate to maintain sufficient Voltage Control in SA. Intervention is required to maintain the power system in a secure operating state
Expected duration: 0400 hrs 26/03/2025.
AGL SA Generation Pty Limited does not incur any civil monetary liability for a relevant action taken in accordance with this direction unless the action is taken in bad faith.
Manager NEM Real Time Operations
Update Direction - Pelican Point Power Limited - PPCCGT PELICAN POINT
Update Direction - Pelican Point Power Limited - PPCCGT PELICAN POINT
Refer to Market Notice 125899
The PPCCGT PELICAN POINT direction is now expected to stay in place until 0400 hrs 26/03/2025.
The direction update is issued at 1600 hrs 24/03/2025.
Manager NEM Real Time Operations
CHG0102167 - Planned Maintenance to NSW Marketnet Site to Site VPN Router
Notification issued to: Market Notice
Notification Type: Initial
Change Type: Normal
Service/ Component: Local Area Network
Change Title: Planned Maintenance to NSW Marketnet Site to Site VPN Router
Change Start Date & Time: 29/03/2025 09:00:00
Change End Date & Time: 29/03/2025 17:00:00
Outage Start Date & Time:
Outage End Date & Time:
Environment: Production
Participant Impact and Requirements: The following impacts are expected to participant connectivity during this planned maintenance:
IPWAN Participants - Nil
Lan-2-Lan VPN Participants (IPSEC) - Up to 2 hour outage for participants who have established their VPN connection/s via the AEMO NSW datacenter termination point (202.44.78.10 for Policy Based VPN's or 202.44.78.12 for Route Based VPN) only - All L2L connections should be established to both QLD / NSW.
Note: Participants are encouraged to ensure their VPN connections are already established or are configured (as per AEMO best practice) to automatically failover to the alternate AEMO QLD datacenter termination point (202.44.76.10 or 202.44.76.12) prior to this scheduled outage. *** Failure to do so will impact connectivity to Marketnet Services ***.
B2B VPN - Nil
SSL VPN Participants: Nil
GASHUB: Nil
Other Impacts will have been communicated in advance.
Support Information:
Report any impacts to the AEMO Information and Support Hub or call 1300 236 600.
Please refer to https://aemo.service-now.com/participantportal?id=pp_services_status for any planned/unplanned maintenance activities .
Cancellation - AEMO Intervention Event - SA region 22/03/2025
Cancellation - AEMO Intervention Event - SA region 22/03/2025
Refer to Market Notice 125868
The AEMO Intervention Event and all associated directions are cancelled from 0400 hrs on 24/03/2025.
Manager NEM Real Time Operations
Cancellation: Direction issued to: AGL SA Generation Pty Limited - TORRB2 TORRENS ISLAN
Cancellation: Direction issued to: AGL SA Generation Pty Limited - TORRB2 TORRENS ISLAN
Refer to Market Notice 125870
Direction is cancelled from: 0400 hrs 24/03/2025
Manager NEM Real Time Operations
Direction - SA region to AGL SA Generation Pty Limited - TORRB2 TORRENS ISLAN
Direction - SA region to AGL SA Generation Pty Limited - TORRB2 TORRENS ISLAN
Refer to Market Notice 125898
In accordance with section 116 of the National Electricity Law, AEMO is issuing a direction to AGL SA Generation Pty Limited. For the purposes of the National Electricity Rules this is a direction under clause 4.8.9(a1)(1).
Direction issued to: AGL SA Generation Pty Limited - TORRB2 TORRENS ISLAN at 1600 hrs 23/03/2025
Type of resource: generating unit
Required actions: Remain synchronised and follow dispatch targets at 0900 hrs 24/03/2025
Services provided: Voltage Control
Circumstances necessitating the Direction: Voltage
Circumstances necessitating the Direction additional detail: The synchronous generating units currently expected to be synchronised in SA will be inadequate to maintain sufficient Voltage Control in SA. Intervention is required to maintain the power system in a secure operating state
Expected duration: 0400 hrs 25/03/2025.
AGL SA Generation Pty Limited does not incur any civil monetary liability for a relevant action taken in accordance with this direction unless the action is taken in bad faith.
Manager NEM Real Time Operations
Direction - SA region to Pelican Point Power Limited - PPCCGT PELICAN POINT
Direction - SA region to Pelican Point Power Limited - PPCCGT PELICAN POINT
Refer to Market Notice 125898
In accordance with section 116 of the National Electricity Law, AEMO is issuing a direction to Pelican Point Power Limited. For the purposes of the National Electricity Rules this is a direction under clause 4.8.9(a1)(1).
Direction issued to: Pelican Point Power Limited - PPCCGT PELICAN POINT at 1600 hrs 23/03/2025
Type of resource: generating unit
Required actions: Remain synchronised and follow dispatch targets at 0800 hrs 24/03/2025
Services provided: Voltage Control
Circumstances necessitating the Direction: Voltage
Circumstances necessitating the Direction additional detail: The synchronous generating units currently expected to be synchronised in SA will be inadequate to maintain sufficient Voltage Control in SA. Intervention is required to maintain the power system in a secure operating state
Expected duration: 0400 hrs 25/03/2025.
Pelican Point Power Limited does not incur any civil monetary liability for a relevant action taken in accordance with this direction unless the action is taken in bad faith.
Manager NEM Real Time Operations
Direction - SA region 23/03/2025
Direction - SA region 23/03/2025
In accordance with section 116 of the National Electricity Law, AEMO has issued a direction to a participant in the SA region. For the purposes of the National Electricity Rules this is a direction under clause 4.8.9(a1)(1).
The issue of the direction commences an AEMO intervention event. AEMO declares all trading intervals during the event to be intervention trading intervals, commencing from the interval ending 1605 hrs on 23/03/2025.
Intervention pricing does not apply to this AEMO intervention event.
AEMO may issue or revoke additional directions in order to meet the current requirement, unless sufficient market response is provided. A further market notice will be issued when all directions related to this requirement have been cancelled.
Manager NEM Real Time Operations