123340SETTLEMENTS RESIDUE15/01/2025 06:00:28 PM

[EventId:202501151800_NRM_NSW1_VIC1_stopped] NEGRES CONSTRAINT NRM_NSW1_VIC1 ceased operating from 15 January 2025 18:00

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1800 hrs on 15 January 2025

CANCELLATION - ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 15 January 2025.

Refer to market notice: 123319

AEMO has ceased taking action to minimize the further accumulation of negative settlement residues on the NSW to VIC directional interconnector.

The negative residue constraint NRM_NSW1_VIC1 ceased operating at 1800 hrs on 15 January 2025.

This is an AEMO autogenerated Market Notice.
     
123334INTER-REGIONAL TRANSFER15/01/2025 05:12:38 PM

Inter-regional transfer limit variation - constraint automation to manage Power System Security in NSW region - 15/01/2025

AEMO ELECTRICITY MARKET NOTICE

In order to maintain the power system in a secure operating state in the NSW region, AEMO has invoked automated constraint set CA_BRIS_5699E75F from 1655 hrs until further notice.

This constraint set contains equations with the following interconnector on the LHS;

V-S-MNSP1
VIC1-NSW1

Manager NEM Real Time Operations
     
123319SETTLEMENTS RESIDUE15/01/2025 04:40:41 PM

[EventId:202501151630_NRM_NSW1_VIC1_started] NEGRES CONSTRAINT NRM_NSW1_VIC1 started operating from 15 January 2025 16:30

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1630 hrs on 15 January 2025

ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 15 January 2025.

Electricity Market outcomes have resulted in the accumulation of negative settlement residues that have exceeded the allowable negative residue threshold for the NSW to VIC directional interconnector.

The negative residue constraint set NRM_NSW1_VIC1 commenced operating from 1630 hrs on 15 January 2025.

This constraint set contains an equation with the following interconnectors on the LHS:
VIC1-NSW1

The RHS of the constraint equation may be adjusted to manage residues.


This is an AEMO autogenerated Market Notice.
     
123305SETTLEMENTS RESIDUE15/01/2025 04:02:08 PM

[EventId:202501151600_NRM_NSW1_VIC1_stopped] NEGRES CONSTRAINT NRM_NSW1_VIC1 ceased operating from 15 January 2025 16:00

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1600 hrs on 15 January 2025

CANCELLATION - ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 15 January 2025.

Refer to market notice: 123270

AEMO has ceased taking action to minimize the further accumulation of negative settlement residues on the NSW to VIC directional interconnector.

The negative residue constraint NRM_NSW1_VIC1 ceased operating at 1600 hrs on 15 January 2025.

This is an AEMO autogenerated Market Notice.
     
123293MARKET INTERVENTION15/01/2025 05:01:31 PM

Update Direction - AGL SA Generation Pty Limited - TORRB3 TORRENS ISLAN

AEMO ELECTRICITY MARKET NOTICE.

Update Direction - AGL SA Generation Pty Limited - TORRB3 TORRENS ISLAN

Refer to Market Notice 123224

The TORRB3 TORRENS ISLAN direction is now expected to stay in place until 0400 hrs 17/01/2025.

The direction update is issued at 1700 hrs 15/01/2025.

Manager NEM Real Time Operations
     
123292MARKET INTERVENTION15/01/2025 04:58:31 PM

Update Direction - AGL SA Generation Pty Limited - TORRB2 TORRENS ISLAN

AEMO ELECTRICITY MARKET NOTICE.

Update Direction - AGL SA Generation Pty Limited - TORRB2 TORRENS ISLAN

Refer to Market Notice 123216

The TORRB2 TORRENS ISLAN direction is now expected to stay in place until 0400 hrs 17/01/2025.

The direction update is issued at 1700 hrs 15/01/2025.

Manager NEM Real Time Operations
     
123276INTER-REGIONAL TRANSFER15/01/2025 02:21:49 PM

Inter-regional transfer limit variation - Murray - Lower Tumut 330 kV 66 line - NSW region - 15/01/2025

AEMO ELECTRICITY MARKET NOTICE

Inter-regional transfer limit variation - Murray - Lower Tumut 330 kV 66 line - NSW region - 15/01/2025

At 1400 hrs 15/01/2025 there was an unplanned outage of Murray - Lower Tumut 330 kV 66 line.

The following constraint set(s) invoked at 1415 hrs 15/01/2025
I-LTMS

This constraint set(s) contains equations with the following interconnectors on the LHS.
VIC1-NSW1,V-S-MNSP1,NSW1-QLD1,T-V-MNSP1

Refer to the AEMO Network Outage Scheduler for further information.

Manager NEM Real Time Operations
     
123273INTER-REGIONAL TRANSFER15/01/2025 02:28:14 PM

Inter-regional transfer limit variation - Lower Tumut - Yass 330 kV 03 Line - NSW region - 15/01/2025

AEMO ELECTRICITY MARKET NOTICE

Inter-regional transfer limit variation - Lower Tumut - Yass 330 kV 03 Line - NSW region - 15/01/2025

At 1358 hrs 15/01/2025 there was an unplanned outage of Lower Tumut - Yass 330 kV 03 Line.

The following constraint set(s) invoked at 1400 hrs 15/01/2025
N-X_LTYS_MNYS

This constraint set(s) contains equations with the following interconnectors on the LHS.
VIC1-NSW1,N-Q-MNSP1,NSW1-QLD1,V-S-MNSP1

Refer to the AEMO Network Outage Scheduler for further information.

Manager NEM Real Time Operations
     
123270SETTLEMENTS RESIDUE15/01/2025 02:06:54 PM

[EventId:202501151405_NRM_NSW1_VIC1_started] NEGRES CONSTRAINT NRM_NSW1_VIC1 started operating from 15 January 2025 14:05

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1405 hrs on 15 January 2025

ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 15 January 2025.

Electricity Market outcomes have resulted in the accumulation of negative settlement residues that have exceeded the allowable negative residue threshold for the NSW to VIC directional interconnector.

The negative residue constraint set NRM_NSW1_VIC1 commenced operating from 1405 hrs on 15 January 2025.

This constraint set contains an equation with the following interconnectors on the LHS:
VIC1-NSW1

The RHS of the constraint equation may be adjusted to manage residues.