122436GENERAL NOTICE23/12/2024 10:28:53 AM

NEM Local Temperature Alerts for SA, VIC from 23 Dec 2024 to 27 Dec 2024

AEMO ELECTRICITY MARKET NOTICE

AEMO's weather service provider has issued forecast temperatures equal to or greater than the NEM Local Temperature Alert Levels for listed weather stations below.

SA
Port Augusta Ap (39+ Deg C): 25th Dec, 26th Dec

VIC
Ararat Prison (39+ Deg C): 26th Dec
Melbourne Olympic Park (39+ Deg C): 26th Dec
Mildura Ap (39+ Deg C): 26th Dec
Mortlake (39+ Deg C): 26th Dec

The NEM Local Temperature Alert Levels are:

Launceston Ti Tree Bend: 33 Deg C, Dalby Airport: 37 Deg C, for all other selected weather stations: 39 Deg C.

AEMO requests Market Participants to:

1. review the weather forecast in the local area where their generating units / MNSP converter stations are located and,

2. if required, update the available capacity in their dispatch offers or availability submissions consistent with the forecast temperatures.

Further information is available at:

https://aemo.com.au/energy-systems/electricity/national-electricity-market-nem/nem-forecasting-and-planning/forecasting-and-reliability/projected-assessment-of-system-adequacy/nem-local-temperature-alerts

AEMO Operations Planning
     
122326MARKET SYSTEMS20/12/2024 04:16:29 PM

INC0139532 | Impact to Prudentials

AEMO ELECTRICITY MARKET NOTICE

SERVICE INTERRUPTION - ALERT

The service interruption relating to Prudentials & Settlements have now been resolved.
AEMO is working on the issue and will provide updates as more information becomes available.

For further enquiries please contact the AEMO Support Hub
Phone: 1300 236 600
Email: supporthub@aemo.com.au
AEMO IT Duty Manager
     
122306GENERAL NOTICE20/12/2024 10:33:57 AM

NEM Local Temperature Alerts for QLD from 20 Dec 2024 to 24 Dec 2024

AEMO ELECTRICITY MARKET NOTICE

AEMO's weather service provider has issued forecast temperatures equal to or greater than the NEM Local Temperature Alert Levels for listed weather stations below.

QLD
Rockhampton Ap (39+ Deg C): 24th Dec

The NEM Local Temperature Alert Levels are:

Launceston Ti Tree Bend: 33 Deg C, Dalby Airport: 37 Deg C, for all other selected weather stations: 39 Deg C.

AEMO requests Market Participants to:

1. review the weather forecast in the local area where their generating units / MNSP converter stations are located and,

2. if required, update the available capacity in their dispatch offers or availability submissions consistent with the forecast temperatures.

Further information is available at:

https://aemo.com.au/energy-systems/electricity/national-electricity-market-nem/nem-forecasting-and-planning/forecasting-and-reliability/projected-assessment-of-system-adequacy/nem-local-temperature-alerts

AEMO Operations Planning
     
122281MARKET SYSTEMS19/12/2024 04:40:39 PM

INC0139532 - ALERT - Impact to Prudentials

AEMO ELECTRICITY MARKET NOTICE

SERVICE INTERRUPTION - ALERT

AEMO is experiencing a service interruption relating to: Prudentials & Settlements.

AEMO is working on the issue and will provide updates as more information becomes available.

For further enquiries please contact the AEMO Support Hub
Phone: 1300 236 600

Email: supporthub@aemo.com.au

AEMO IT Duty Manager
     
122156GENERAL NOTICE18/12/2024 10:32:22 AM

Network Augmentation Commissioned - SA Region - 18/12/2024

AEMO ELECTRICITY MARKET NOTICE


Network Augmentation Commissioned - SA Region - 18/12/2024

At 0910 hrs 18/12/2024, the Para East Left Bus 275 kV Reactor has been commissioned.

Manager NEM Real Time Operations
     
122115GENERAL NOTICE17/12/2024 05:34:04 PM

Project Energy Connect (PEC-1) testing 18th December 2024 0700-2200 for flows in both directions up to 150 MW

AEMO ELECTRICITY MARKET NOTICE

Refer to market notice 120706

There is an opportunity for testing Project Energy Connect (PEC-1) for flows in both directions up to 150 MW on 18th December from 07:00hrs to 22:00hrs

This test includes switching of transmission lines and reactive plant in South Australia and in New South Wales.

Please also refer to the published formal PEC Stage 1 and HIC capacity release testing information at the following link https://aemo.com.au/-/media/files/stakeholder_consultation/consultations/nem-consultations/2023/project-energyconnect-stage-1-and-hic-capacity-release/pec-stage-1-and-hic---final-test-program.pdf?la=en.

Ben Blake
AEMO Operations
     
122047MARKET SYSTEMS16/12/2024 06:07:34 PM

CHG0100502 | Production | Planned maintenance affecting the AEMO Market Network.

Change Number: CHG0100502
Notification issued to: Market Notice
Notification Type: Initial
Change Type: Normal
Service/ Component: MarketNet
Change Title: Planned maintenance affecting the AEMO Market Network ***Outage Updated***
Change Start Date & Time: 19/12/2024 07:00:00 AEST
Change End Date & Time: 20/12/2024 17:00:00 AEST
Outage 1 Start Date & Time: 19/12/2024 09:12:00 AEST
Outage 1 End Date & Time: 19/12/2024 09:13:00 AEST
Outage 2 Start Date & Time: 19/12/2024 15:12:00 AEST
Outage 2 End Date & Time: 19/12/2024 15:13:00 AEST

Environment: Production
Participant Impact and Requirements: Planned maintenance will be conducted on the 19th of December 2024, between 07:00AM and 05:00PM AEST on the core network infrastructure within the AEMO Market Network in Brisbane.

During there change, there will be two instances of 1-3 second service disruption to MarketNet Services accessed via Brisbane as traffic moves from the active to the standby load balancing unit. All Services should return to normal after this time. Traffic via Sydney will not be affected during this time. AEMO recommends that all market participants with site to site VPN connections currently connected via Brisbane, to switch these connections to the Sydney site as a precaution.

Participants connecting via IPWAN and/or SSL VPN will be automatically connected to the Sydney site and do not need to take any action.
Support Information:
Report any impacts to the AEMO Information and Support Hub or call 1300 236 600.
Please refer to https://aemo.service-now.com/participantportal?id=pp_services_status for any
planned/unplanned maintenance activities .

     
121997GENERAL NOTICE16/12/2024 10:59:19 AM

NEM Local Temperature Alerts for SA, VIC from 16 Dec 2024 to 20 Dec 2024

AEMO ELECTRICITY MARKET NOTICE

AEMO's weather service provider has issued forecast temperatures equal to or greater than the NEM Local Temperature Alert Levels for listed weather stations below.

SA
Clare High School (39+ Deg C): 16th Dec
Port Augusta Ap (39+ Deg C): 16th Dec

VIC
Ararat Prison (39+ Deg C): 16th Dec
Latrobe Valley Ap (39+ Deg C): 16th Dec
Melbourne Olympic Park (39+ Deg C): 16th Dec
Mildura Ap (39+ Deg C): 16th Dec, 20th Dec
Mortlake (39+ Deg C): 16th Dec

The NEM Local Temperature Alert Levels are:

Launceston Ti Tree Bend: 33 Deg C, Dalby Airport: 37 Deg C, for all other selected weather stations: 39 Deg C.

AEMO requests Market Participants to:

1. review the weather forecast in the local area where their generating units / MNSP converter stations are located and,

2. if required, update the available capacity in their dispatch offers or availability submissions consistent with the forecast temperatures.

Further information is available at:

https://aemo.com.au/energy-systems/electricity/national-electricity-market-nem/nem-forecasting-and-planning/forecasting-and-reliability/projected-assessment-of-system-adequacy/nem-local-temperature-alerts

AEMO Operations Planning
     
121842GENERAL NOTICE13/12/2024 01:14:02 PM

CORRECTION: Update - Vulnerable lines in QLD region

AEMO ELECTRICITY MARKET NOTICE.

Update - Lightning vulnerable lines in QLD region

Refer to AEMO Electricity Market Notice 121840

Fix typo: Line 7141 should read Line 7143

At 2026 hrs 12/12/2024 the Kamerunga to Barron Gorge 132 kV Line 7184 and the Kamerunga to Barron Gorge 132 kV Line 7143 tripped.

The cause of the trip was identified as due to lightning.

In accordance with SO_OP_3715, AEMO now considers the Kamerunga to Barron Gorge 132 kV Line 7184 and the Kamerunga to Barron Gorge 132 kV Line 7143 to be vulnerable with a category of probable due to lightning.

Manager NEM Real Time Operations
     