124116RECLASSIFY CONTINGENCY04/02/2025 03:48:46 PM

Cancellation of a Non-Credible Contingency Event: Lindisfarne - Mornington No.1 TEE line and Lindisfarne - Mornington No.2 TEE line in TAS1 due to Lightning.

AEMO ELECTRICITY MARKET NOTICE

Cancellation of reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits is no longer reasonably possible. There is no longer any lightning activity in the vicinity of the following lines. Accordingly its classification has reverted to a non-credible contingency event.

Region: TAS1

Lines: Lindisfarne - Mornington No.1 TEE and Lindisfarne - Mornington No.2 TEE

Cancellation time: 04/02/2025 15:48

Constraint set(s) revoked:
NONE

Refer AEMO Electricity Market Notice 124087

Auto-generated on behalf of Manager NEM Real Time Operations
     
124109RECLASSIFY CONTINGENCY04/02/2025 03:38:46 PM

Reclassification of a Non-Credible Contingency Event: Guybal Munjan - Chalumbin 857 275kV line line and Guybal Munjan - Chalumbin 858 275kV line line in QLD1 due to Lightning.

AEMO ELECTRICITY MARKET NOTICE

Reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits to now be more likely and reasonably possible. Accordingly AEMO has reclassified it as a credible contingency event.

Region: QLD1

Lines: Guybal Munjan - Chalumbin 857 275kV line and Guybal Munjan - Chalumbin 858 275kV line

Duration: 04/02/2025 15:38 until further notice

Constraint set(s) invoked:
Q-RSCH_N-2 Constraint set contains the following interconnector(s) on the left hand side:
NONE


Auto-generated on behalf of Manager NEM Real Time Operations
     
124108RECLASSIFY CONTINGENCY04/02/2025 03:38:45 PM

Reclassification of a Non-Credible Contingency Event: Bayswater - Mt Piper No.5A3 500kV line and Wollar - Mt Piper No.5A5 500kV line in NSW1 due to Lightning.

AEMO ELECTRICITY MARKET NOTICE

Reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits to now be more likely and reasonably possible. Accordingly AEMO has reclassified it as a credible contingency event.

Region: NSW1

Lines: Bayswater - Mt Piper No.5A3 500kV and Wollar - Mt Piper No.5A5 500kV

Duration: 04/02/2025 15:38 until further notice

Constraint set(s) invoked:
NONE

Auto-generated on behalf of Manager NEM Real Time Operations
     
124102RECLASSIFY CONTINGENCY04/02/2025 03:18:45 PM

Reclassification of a Non-Credible Contingency Event: Kamerunga - Barron Gorge 7184 132kV line and Kamerunga - Barron Gorge 7143 132kV line in QLD1 due to Lightning.

AEMO ELECTRICITY MARKET NOTICE

Reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits to now be more likely and reasonably possible. Accordingly AEMO has reclassified it as a credible contingency event.

Region: QLD1

Lines: Kamerunga - Barron Gorge 7184 132kV and Kamerunga - Barron Gorge 7143 132kV

Duration: 04/02/2025 15:18 until further notice

Constraint set(s) invoked:
NONE

Auto-generated on behalf of Manager NEM Real Time Operations
     
124100RECLASSIFY CONTINGENCY04/02/2025 03:14:10 PM

Cancellation of a Non-Credible Contingency Event: Bayswater - Mt Piper No.5A3 500kV line and Wollar - Mt Piper No.5A5 500kV line in NSW1 due to Lightning.

AEMO ELECTRICITY MARKET NOTICE

Cancellation of reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits is no longer reasonably possible. There is no longer any lightning activity in the vicinity of the following lines. Accordingly its classification has reverted to a non-credible contingency event.

Region: NSW1

Lines: Bayswater - Mt Piper No.5A3 500kV and Wollar - Mt Piper No.5A5 500kV

Cancellation time: 04/02/2025 15:14

Constraint set(s) revoked:
NONE

Refer AEMO Electricity Market Notice 124072

Auto-generated on behalf of Manager NEM Real Time Operations
     
124094RESERVE NOTICE04/02/2025 03:58:27 PM

STPASA - Forecast Lack Of Reserve Level 1 (LOR1) in the SA Region on 11/02/2025

AEMO ELECTRICITY MARKET NOTICE

AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the SA region for the following period:

From 1730 hrs to 2100 hrs 11/02/2025.
The forecast capacity reserve requirement is 414 MW.
The minimum capacity reserve available is 344 MW.

AEMO Operations
     
124093RESERVE NOTICE04/02/2025 03:57:07 PM

STPASA - Update of the Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 07/02/2025

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR1 condition in the NSW region advised in AEMO Electricity Market Notice No. 124000 has been updated at 1400 hrs 04/02/2025 to the following:

1. From 1430 hrs to 1700 hrs 07/02/2025.
The forecast capacity reserve requirement is 1400 MW.
The minimum capacity reserve available is 700 MW.

2. From 1830 hrs to 1930 hrs 07/02/2025.
The forecast capacity reserve requirement is 1400 MW.
The minimum capacity reserve available is 898 MW.

AEMO Operations
     
124091RESERVE NOTICE04/02/2025 03:01:16 PM

PDPASA - Update of the Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 04/02/2025

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR1 condition in the NSW region advised in AEMO Electricity Market Notice No. 124059 has been updated at 1420 hrs 04/02/2025 to the following:

[1.] From 1530 hrs 04/02/2025 to 1630 hrs 04/02/2025.
The forecast capacity reserve requirement is 1663 MW.
The minimum capacity reserve available is 1277 MW.

[2.] From 1830 hrs 04/02/2025 to 2030 hrs 04/02/2025.
The forecast capacity reserve requirement is 1652 MW.
The minimum capacity reserve available is 974 MW.


Manager NEM Real Time Operations
     
124090RESERVE NOTICE04/02/2025 03:14:01 PM

PDPASA - Forecast Lack Of Reserve Level 2 (LOR2) in the NSW Region on 04/02/2025

AEMO ELECTRICITY MARKET NOTICE

AEMO declares a Forecast LOR2 condition under clause 4.8.4(b) of the National Electricity Rules for the NSW region for the following Period:


[1.] From 1630 hrs 04/02/2025 to 1830 hrs 04/02/2025.
The forecast capacity reserve requirement is 993 MW.
The minimum capacity reserve available is 768 MW.


AEMO is seeking a market response.

AEMO has not yet estimated the latest time at which it would need to intervene through an AEMO intervention event.