Market Notices

122587RESERVE NOTICE30/12/2024 02:54:53 PM

STPASA - Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 06/01/2025

AEMO ELECTRICITY MARKET NOTICE

AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the NSW region for the following periods:

1. From 1500 hrs to 1700 hrs 06/01/2025.
The forecast capacity reserve requirement is 1400 MW.
The minimum capacity reserve available is 1142 MW.

2. From 1730 hrs to 1800 hrs 06/01/2025.
The forecast capacity reserve requirement is 1400 MW.
The minimum capacity reserve available is 1328 MW.


AEMO Operations

     
122522PRICES SUBJECT TO REVIEW27/12/2024 03:25:27 PM

[EventId:202412271530_review] Prices for interval 27-Dec-2024 15:30 are subject to review

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1525 hrs on 27 December 2024

PRICES ARE SUBJECT TO REVIEW for trading interval 27-Dec-2024 15:30.

AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs


This is an AEMO autogenerated Market Notice.
     
122521PRICES SUBJECT TO REVIEW27/12/2024 03:20:28 PM

[EventId:202412271525_review] Prices for interval 27-Dec-2024 15:25 are subject to review

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1520 hrs on 27 December 2024

PRICES ARE SUBJECT TO REVIEW for trading interval 27-Dec-2024 15:25.

AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs


This is an AEMO autogenerated Market Notice.
     
122520PRICES SUBJECT TO REVIEW27/12/2024 03:15:22 PM

[EventId:202412271520_review] Prices for interval 27-Dec-2024 15:20 are subject to review

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1515 hrs on 27 December 2024

PRICES ARE SUBJECT TO REVIEW for trading interval 27-Dec-2024 15:20.

AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs


This is an AEMO autogenerated Market Notice.
     
122519PRICES SUBJECT TO REVIEW27/12/2024 03:10:29 PM

[EventId:202412271515_review] Prices for interval 27-Dec-2024 15:15 are subject to review

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1510 hrs on 27 December 2024

PRICES ARE SUBJECT TO REVIEW for trading interval 27-Dec-2024 15:15.

AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs


This is an AEMO autogenerated Market Notice.
     
122518PRICES SUBJECT TO REVIEW27/12/2024 03:05:21 PM

[EventId:202412271510_review] Prices for interval 27-Dec-2024 15:10 are subject to review

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1505 hrs on 27 December 2024

PRICES ARE SUBJECT TO REVIEW for trading interval 27-Dec-2024 15:10.

AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs


This is an AEMO autogenerated Market Notice.
     
122516PRICES SUBJECT TO REVIEW27/12/2024 03:00:22 PM

[EventId:202412271505_review] Prices for interval 27-Dec-2024 15:05 are subject to review

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1500 hrs on 27 December 2024

PRICES ARE SUBJECT TO REVIEW for trading interval 27-Dec-2024 15:05.

AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs


This is an AEMO autogenerated Market Notice.
     
122515INTER-REGIONAL TRANSFER27/12/2024 03:03:14 PM

Inter-regional transfer limit variation - South East SVC - SA region - 27/12/2024

AEMO ELECTRICITY MARKET NOTICE

Inter-regional transfer limit variation - South East SVC - SA region - 27/12/2024

At 1452 hrs 27/12/2024 there was an unplanned outage of the South East SVC.

The following constraint set(s) invoked at 1500 hrs 27/12/2024
S-SE_VC1

This constraint set(s) contains equations with the following interconnectors on the LHS.
V-SA

Refer to the AEMO Network Outage Scheduler for further information.

Manager NEM Real Time Operations
     
122487INTER-REGIONAL TRANSFER26/12/2024 08:50:33 AM

Inter-Regional Transfer limit variation - Directlink - NSW Region

AEMO ELECTRICITY MARKET NOTICE

Inter-Regional Transfer limit variation - Directlink - NSW Region

There has been an unplanned outage of all of Directlink.

The following constraint set was invoked at 0840 hrs 26/12/2024

N-X_MBTE_3

The constraint set contains the following interconnector on the left hand side.

N-Q-MNSP1

Refer AEMO Network Outage Scheduler (NOS) for further details.

Manager NEM Real Time Operations
     