Filter by category
Filter by Date
[EventId:202503301730_review] Prices for interval 30-Mar-2025 17:30 are subject to review
Issued by Australian Energy Market Operator Ltd at 1725 hrs on 30 March 2025
PRICES ARE SUBJECT TO REVIEW for trading interval 30-Mar-2025 17:30.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
[EventId:202503301725_review] Prices for interval 30-Mar-2025 17:25 are subject to review
Issued by Australian Energy Market Operator Ltd at 1720 hrs on 30 March 2025
PRICES ARE SUBJECT TO REVIEW for trading interval 30-Mar-2025 17:25.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
[EventId:202503301720_review] Prices for interval 30-Mar-2025 17:20 are subject to review
Issued by Australian Energy Market Operator Ltd at 1715 hrs on 30 March 2025
PRICES ARE SUBJECT TO REVIEW for trading interval 30-Mar-2025 17:20.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
[EventId:202503301715_review] Prices for interval 30-Mar-2025 17:15 are subject to review
Issued by Australian Energy Market Operator Ltd at 1710 hrs on 30 March 2025
PRICES ARE SUBJECT TO REVIEW for trading interval 30-Mar-2025 17:15.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
[EventId:202503301710_review] Prices for interval 30-Mar-2025 17:10 are subject to review
Issued by Australian Energy Market Operator Ltd at 1705 hrs on 30 March 2025
PRICES ARE SUBJECT TO REVIEW for trading interval 30-Mar-2025 17:10.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
[EventId:202503301705_review] Prices for interval 30-Mar-2025 17:05 are subject to review
Issued by Australian Energy Market Operator Ltd at 1700 hrs on 30 March 2025
PRICES ARE SUBJECT TO REVIEW for trading interval 30-Mar-2025 17:05.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
Update to Victorian system normal Kerang voltage stability limit
AEMO has completed a review of a system normal voltage stability limit in north west Victoria as a result of commissioning of BESS at Koorangie. The revised limit manages pre-contingent flow on the Wemen to Koorangie 220 kV line to avoid voltage collapse at Koorangie, Kerang or Wemen on loss of the Crowlands to Bulgana to Horsham or Horsham to Murra Warra to Kiamal 220 kV line. The revised constraint equation includes the generators in south-west NSW and north-west Victoria on the left-hand side as well as Murraylink and V-SA. Full details on the limits advice are to be published shortly on the AEMO website: https://www.aemo.com.au/energy-systems/electricity/national-electricity-market-nem/system-operations/congestion-information-resource/limits-advice
The revised limit will be implemented at 0900 hrs on Monday 31st March 2025, by updating V^^V_NIL_KGTS.
For full details on the factors this constraint equation has now been loaded into AEMO's pre-production systems.
For further details on this constraint equation please contact terry.liu@aemo.com.au
Terry Liu
AEMO Operations
CHG0102344 - Maintenance activities to be performed on the Declared Wholesale Gas Market Systems Pre-Production.
Notification issued to: Market Notice
Notification Type: Initial
Change Type: Normal
Service/ Component: Declared Wholesale Gas Market (DWGM)
Change Title: Maintenance activities to be performed on the Declared Wholesale Gas Market Systems Pre-Production.
Change Start Date & Time: 02/04/2025 08:00:00
Change End Date & Time: 02/04/2025 17:30:00
Outage Start Date & Time: 02/04/2025 09:00:00
Outage End Date & Time: 02/04/2025 12:00:00
Environment: Pre-Production
Participant Impact and Requirements: This is a regular procedure to allow routine maintenance. short service outages over the day for DWGM services, includiing MIBB and Web Exchanger.
Pre-Production Declared Wholesale Gas Market Systems (DWGM)
Support Information:
Report any impacts to the AEMO Information and Support Hub or call 1300 236 600.
Please refer to https://aemo.service-now.com/participantportal?id=pp_services_status for any planned/unplanned maintenance activities .
CHG0101896 - EMMS Pre-Production Systems will be transferred to the alternative datacentre for maintenance activities .
Notification issued to: Market Notice
Notification Type: Initial
Change Type: Normal
Service/ Component: Electricity Market Management System_PreProd
Change Title: EMMS Pre-Production Systems will be transferred to the alternative datacentre for maintenance activities .
Change Start Date & Time: 01/04/2025 08:00:00
Change End Date & Time: 11/04/2025 17:00:00
Outage Start Date & Time: 03/04/2025 08:00:00
Outage End Date & Time: 03/04/2025 22:00:00
Environment: Pre-Production
Participant Impact and Requirements: EMMS Pre-Production Systems will be transferred to the alternative datacentre for maintenance activities. Maintenance activities will be conducted on the following dates:
1/04/2025
3/04/2025
8/04/2025
During the window,FPP calculations may be delayed at various points.
Support Information:
Report any impacts to the AEMO Information and Support Hub or call 1300 236 600.
Please refer to https://aemo.service-now.com/participantportal?id=pp_services_status for any planned/unplanned maintenance activities .