Update Direction - AGL SA Generation Pty Limited - TORRB2 TORRENS ISLAN
Update Direction - AGL SA Generation Pty Limited - TORRB2 TORRENS ISLAN
Refer to Market Notice 125275
TORRB2 TORRENS ISLAN at 0730 hrs 05/03/2025 to Remain synchronised and follow dispatch targets.
The TORRB2 TORRENS ISLAN direction is now expected to stay in place until 0400 hrs 08/03/2025.
The direction update is issued at 1600 hrs 06/03/2025.
Manager NEM Real Time Operations
Update Direction - Pelican Point Power Limited - PPCCGT PELICAN POINT
Update Direction - Pelican Point Power Limited - PPCCGT PELICAN POINT
Refer to Market Notice 125274
PPCCGT PELICAN POINT at 0700 hrs 05/03/2025 to Remain synchronised and follow dispatch targets.
The PPCCGT PELICAN POINT direction is now expected to stay in place until 1700 hrs 07/03/2025.
The direction update is issued at 1600 hrs 06/03/2025.
Manager NEM Real Time Operations
Inter-Regional Transfer limit variation - Directlink - NSW Region
Inter-Regional Transfer limit variation - Directlink - NSW Region
There has been an unplanned outage of the No. 1 and 2 Legs of Directlink.
The following constraint set was invoked at 1125 hrs 06/03/2025.
N-X_MBTE_3
The constraint set contains the following interconnector on the left hand side.
N-Q-MNSP1
Refer AEMO Network Outage Scheduler (NOS) for further details.
Manager NEM Real Time Operations
NEM Local Temperature Alerts for SA from 06 Mar 2025 to 10 Mar 2025
AEMO's weather service provider has issued forecast temperatures equal to or greater than the NEM Local Temperature Alert Levels for listed weather stations below.
SA
Port Augusta Ap (39+ Deg C): 10th Mar
The NEM Local Temperature Alert Levels are:
Launceston Ti Tree Bend: 33 Deg C, Dalby Airport: 37 Deg C, for all other selected weather stations: 39 Deg C.
AEMO requests Market Participants to:
1. review the weather forecast in the local area where their generating units / MNSP converter stations are located and,
2. if required, update the available capacity in their dispatch offers or availability submissions consistent with the forecast temperatures.
Further information is available at:
https://aemo.com.au/energy-systems/electricity/national-electricity-market-nem/nem-forecasting-and-planning/forecasting-and-reliability/projected-assessment-of-system-adequacy/nem-local-temperature-alerts
AEMO Operations Planning
Inter-regional transfer limit variation - Liddell - Tomago 82 330kV Line - NSW region - 05/03/2025
Inter-regional transfer limit variation - Liddell - Tomago 82 330kV Line - NSW region - 05/03/2025
A planned outage of Liddell - Tomago 82 330kV Line in the NSW region was scheduled from 0600 hrs 03/03/2025 to 1600 hrs 06/03/2025.
The outage has been completed and Liddell - Tomago 82 330kV Line returned to service at 1635 hrs 05/03/2025
Constraint set(s) revoked: N-LDTM_82
Manager NEM Real Time Operations
Inter-regional transfer limit variation - Ewingsdale-Mullumbimby 9G5 132kV line - NSW region - 05/03/2025
Inter-regional transfer limit variation - Ewingsdale-Mullumbimby 9G5 132kV line - NSW region - 05/03/2025
At 1603 hrs 05/03/2025 there was an unplanned outage of Ewingsdale-Mullumbimby 9G5 132kV line.
The following constraint set(s) invoked at 1615 hrs 05/03/2025
N-BAMB_132_OPEN
This constraint set(s) contains equations with the following interconnectors on the LHS.
N-Q-MNSP1
Refer to the AEMO Network Outage Scheduler for further information.
Manager NEM Real Time Operations
Update Direction - AGL SA Generation Pty Limited - TORRB2 TORRENS ISLAN
Update Direction - AGL SA Generation Pty Limited - TORRB2 TORRENS ISLAN
Refer to Market Notice 125259
TORRB2 TORRENS ISLAN at 0400 hrs 06/03/2025 to Remain synchronised and follow dispatch targets.
The TORRB2 TORRENS ISLAN direction is now expected to stay in place until 0400 hrs 07/03/2025.
The direction update is issued at 1630 hrs 05/03/2025.
Manager NEM Real Time Operations
Update Direction - Pelican Point Power Limited - PPCCGT PELICAN POINT
Update Direction - Pelican Point Power Limited - PPCCGT PELICAN POINT
Refer to Market Notice 125258
PPCCGT PELICAN POINT at 0400 hrs 06/03/2025 to Remain synchronised and follow dispatch targets.
The PPCCGT PELICAN POINT direction is now expected to stay in place until 0400 hrs 07/03/2025.
The direction update is issued at 1600 hrs 05/03/2025.
Manager NEM Real Time Operations
CHG0101704 - As part of the Platform Services Patching Program, webMethods Inactive Production Application Servers in Brisbane
Notification issued to: Market Notice
Notification Type: Initial
Change Type: Normal
Service/ Component: MSATS - Business to Business data exchange
Change Title: As part of the Platform Services Patching Program, webMethods Inactive Production Application Servers in Brisbane will have critical security patches applied.
Change Start Date & Time: 04/03/2025 08:00:00
Change End Date & Time: 06/03/2025 18:00:00
Outage Start Date & Time:
Outage End Date & Time:
Environment: Production
Participant Impact and Requirements: This is the Inactive Production environment, there is no impact for external participants.
Support Information:
Report any impacts to the AEMO Information and Support Hub or call 1300 236 600.
Please refer to https://aemo.service-now.com/participantportal?id=pp_services_status for any planned/unplanned maintenance activities .