STPASA - Forecast Lack Of Reserve Level 2 (LOR2) in the NSW Region on 25/11/2024
AEMO declares a Forecast LOR2 condition under clause 4.8.4(b) of the National Electricity Rules for the NSW region for the following period:
[1.] From 1730 hrs 25/11/2024 to 1830 hrs 25/11/2024.
The forecast capacity reserve requirement is 730 MW.
The minimum capacity reserve available is 647 MW.
AEMO is seeking a market response.
AEMO has not yet estimated the latest time it would need to intervene through an AEMO intervention event.
Manager NEM Real Time Operations
Cancellation: Direction issued to: Synergen Power Pty Limited - MINTARO MINTARO GAS
Cancellation: Direction issued to: Synergen Power Pty Limited - MINTARO MINTARO GAS
Refer to Market Notice 120609
Direction is cancelled from: 1830 hrs 18/11/2024
Manager NEM Real Time Operations
[EventId:202411181600_confirmed] Prices for interval 18-Nov-2024 16:00 are now confirmed
Issued by Australian Energy Market Operator Ltd at 1625 hrs on 18 November 2024
PRICES ARE NOW CONFIRMED for trading interval 18-Nov-2024 16:00.
In accordance with Market Notice 120617 AEMO has reviewed this trading interval and determined that:
- Manifestly Incorrect Inputs did not apply
Prices remain unchanged.
This is an AEMO autogenerated Market Notice.
[EventId:202411181625_confirmed] Prices for interval 18-Nov-2024 16:25 are now confirmed
Issued by Australian Energy Market Operator Ltd at 1625 hrs on 18 November 2024
PRICES ARE NOW CONFIRMED for trading interval 18-Nov-2024 16:25.
In accordance with Market Notice 120624 AEMO has reviewed this trading interval and determined that:
- Manifestly Incorrect Inputs did not apply
Prices remain unchanged.
This is an AEMO autogenerated Market Notice.
[EventId:202411181620_confirmed] Prices for interval 18-Nov-2024 16:20 are now confirmed
Issued by Australian Energy Market Operator Ltd at 1625 hrs on 18 November 2024
PRICES ARE NOW CONFIRMED for trading interval 18-Nov-2024 16:20.
In accordance with Market Notice 120623 AEMO has reviewed this trading interval and determined that:
- Manifestly Incorrect Inputs did not apply
Prices remain unchanged.
This is an AEMO autogenerated Market Notice.
[EventId:202411181615_confirmed] Prices for interval 18-Nov-2024 16:15 are now confirmed
Issued by Australian Energy Market Operator Ltd at 1625 hrs on 18 November 2024
PRICES ARE NOW CONFIRMED for trading interval 18-Nov-2024 16:15.
In accordance with Market Notice 120622 AEMO has reviewed this trading interval and determined that:
- Manifestly Incorrect Inputs did not apply
Prices remain unchanged.
This is an AEMO autogenerated Market Notice.
[EventId:202411181610_confirmed] Prices for interval 18-Nov-2024 16:10 are now confirmed
Issued by Australian Energy Market Operator Ltd at 1625 hrs on 18 November 2024
PRICES ARE NOW CONFIRMED for trading interval 18-Nov-2024 16:10.
In accordance with Market Notice 120621 AEMO has reviewed this trading interval and determined that:
- Manifestly Incorrect Inputs did not apply
Prices remain unchanged.
This is an AEMO autogenerated Market Notice.
[EventId:202411181605_confirmed] Prices for interval 18-Nov-2024 16:05 are now confirmed
Issued by Australian Energy Market Operator Ltd at 1625 hrs on 18 November 2024
PRICES ARE NOW CONFIRMED for trading interval 18-Nov-2024 16:05.
In accordance with Market Notice 120619 AEMO has reviewed this trading interval and determined that:
- Manifestly Incorrect Inputs did not apply
Prices remain unchanged.
This is an AEMO autogenerated Market Notice.
Update Direction - AGL SA Generation Pty Limited - TORRB3 TORRENS ISLAN
Update Direction - AGL SA Generation Pty Limited - TORRB3 TORRENS ISLAN
Refer AEMO Electricity Participant Notice 120553
The TORRB3 TORRENS ISLAN direction is now expected to stay in place until 0400 hrs 20/11/2024.
The direction update is issued at 1630 hrs 18/11/2024.
Manager NEM Real Time Operations