PDPASA - Cancellation of the Forecast Lack Of Reserve Level 2 (LOR2) in the NSW Region on 16/03/2025
The Forecast LOR2 condition in the NSW region advised in AEMO Electricity Market Notice No. 125699 is cancelled at 1415 hrs.
Manager NEM Real Time Operations
Non-credible contingency event - QLD region - 16/03/2025
Non-credible contingency event - QLD region - 16/03/2025
At 1131 hrs the H35 Strathmore 132 kV No 2 bus tripped. Whitsunday Solar farm and Hamilton Solar farm were disconnected.
AEMO did not instruct load shedding.
The cause of this non credible contingency event is not known at this stage.
Manager NEM Real Time Operations
PDPASA - Update of the Forecast Lack Of Reserve Level 2 (LOR2) in the NSW Region on 16/03/2025
The Forecast LOR2 condition in the NSW region advised in AEMO Electricity Market Notice No. 125697 has been updated at 1045 hrs to the following:
From 1700 hrs 16/03/2025 to 1830 hrs 16/03/2025.
The forecast capacity reserve requirement is 730 MW.
The minimum capacity reserve available is 656 MW.
AEMO is seeking a market response.
AEMO has not yet estimated the latest time it would need to intervene through an AEMO intervention event.
Manager NEM Real Time Operations
PDPASA - Forecast Lack Of Reserve Level 2 (LOR2) in the NSW Region on 16/03/2025
AEMO declares a Forecast LOR2 condition under clause 4.8.4(b) of the National Electricity Rules for the NSW region for the following Period:
[1.] From 1730 hrs 16/03/2025 to 1800 hrs 16/03/2025.
The forecast capacity reserve requirement is 1105 MW.
The minimum capacity reserve available is 1017 MW.
AEMO is seeking a market response.
AEMO has not yet estimated the latest time at which it would need to intervene through an AEMO intervention event.
Manager NEM Real Time Operations
[EventId:202503151645_review] Prices for interval 15-Mar-2025 16:45 are subject to review
Issued by Australian Energy Market Operator Ltd at 1640 hrs on 15 March 2025
PRICES ARE SUBJECT TO REVIEW for trading interval 15-Mar-2025 16:45.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
[EventId:202503151640_review] Prices for interval 15-Mar-2025 16:40 are subject to review
Issued by Australian Energy Market Operator Ltd at 1635 hrs on 15 March 2025
PRICES ARE SUBJECT TO REVIEW for trading interval 15-Mar-2025 16:40.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
[EventId:202503151635_review] Prices for interval 15-Mar-2025 16:35 are subject to review
Issued by Australian Energy Market Operator Ltd at 1630 hrs on 15 March 2025
PRICES ARE SUBJECT TO REVIEW for trading interval 15-Mar-2025 16:35.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
[EventId:202503151630_review] Prices for interval 15-Mar-2025 16:30 are subject to review
Issued by Australian Energy Market Operator Ltd at 1625 hrs on 15 March 2025
PRICES ARE SUBJECT TO REVIEW for trading interval 15-Mar-2025 16:30.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
[EventId:202503151625_review] Prices for interval 15-Mar-2025 16:25 are subject to review
Issued by Australian Energy Market Operator Ltd at 1620 hrs on 15 March 2025
PRICES ARE SUBJECT TO REVIEW for trading interval 15-Mar-2025 16:25.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.