STPASA - Forecast Lack Of Reserve Level 2 (LOR2) in the QLD Region on 24/01/2025
AEMO declares a Forecast LOR2 condition under clause 4.8.4(b) of the National Electricity Rules for the QLD region for the following period:
From 1530 hrs 24/01/2025 to 1600 hrs 24/01/2025.
The forecast capacity reserve requirement is 350 MW.
The minimum capacity reserve available is 247 MW.
AEMO is seeking a market response.
AEMO has not yet estimated the latest time it would need to intervene through an AEMO intervention event.
Manager NEM Real Time Operations
PDPASA - Cancellation of the Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 15/01/2025
The Forecast LOR1 condition in the NSW region advised in AEMO Electricity Market Notice No. 123295 is cancelled at 1545 hrs 15/01/2025.
Manager NEM Real Time Operations
PDPASA - Update of the Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 15/01/2025
The Forecast LOR1 condition in the NSW region advised in AEMO Electricity Market Notice No. 123289 has been updated at 1515 hrs to the following:
[1.] From 1630 hrs 15/01/2025 to 1800 hrs 15/01/2025.
The forecast capacity reserve requirement is 1558 MW.
The minimum capacity reserve available is 1347 MW.
Manager NEM Real Time Operations
PDPASA - Update of the Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 15/01/2025
The Forecast LOR1 condition in the NSW region advised in AEMO Electricity Market Notice No. 123248 has been updated at 0800 hrs to the following:
[1.] From 1630 hrs 15/01/2025 to 1830 hrs 15/01/2025.
The forecast capacity reserve requirement is 1751 MW.
The minimum capacity reserve available is 1629 MW.
Manager NEM Real Time Operations
PDPASA - Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 15/01/2025
AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the NSW region for the following Period:
[1.] From 1730 hrs 15/01/2025 to 1800 hrs 15/01/2025.
The forecast capacity reserve requirement is 1765 MW.
The minimum capacity reserve available is 1739 MW.
Manager NEM Real Time Operations
PDPASA - Cancellation of the Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 15/01/2025
The Forecast LOR1 condition in the NSW region advised in AEMO Electricity Market Notice No. 123206 is cancelled at 0450 hrs 15/01/2025.
Manager NEM Real Time Operations
PDPASA - Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 14/01/2025
AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the NSW region for the following Period:
[1.] From 1800 hrs 14/01/2025 to 1900 hrs 14/01/2025.
The forecast capacity reserve requirement is 1580 MW.
The minimum capacity reserve available is 1423 MW.
Manager NEM Real Time Operations
PDPASA - Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 15/01/2025
AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the NSW region for the following Period:
[1.] From 1630 hrs 15/01/2025 to 1830 hrs 15/01/2025.
The forecast capacity reserve requirement is 1720 MW.
The minimum capacity reserve available is 1570 MW.
Manager NEM Real Time Operations
Cancellation of Actual (LOR2) condition in the NSW region - 13/01/2025
Cancellation of Actual (LOR2) condition in the NSW region - 13/01/2025
The Actual LOR2 Condition in the NSW Region advised in AEMO Electricity Market Notice No.123176 is cancelled at 1815 hrs 13/01/2025.